§63.10. Recordkeeping and reporting requirements. — Inbound Citations
40 C.F.R. § 63.10
Statutory Authority
Cited by 1055 regulations in release Current.
Citations to 40 C.F.R. § 63.10 as a whole
-
Table 9 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 1 to this subpart shows which parts of the General Provisions in 40 CFR 63.1 through 63.16 apply to you.
-
(c) In addition to the records required by § 63.10, you must keep records to demonstrate compliance with the requirements for your pollution prevention plan in paragraph (a)(1) of this section and/or for the use of only restricted scrap in paragraph (a)(2) of this section and for mercury in paragraphs (b)(1) through (3) of this section as applicable. You must keep records documenting compliance with paragraph (b)(4) of this section for scrap that does not contain motor vehicle scrap.(1) If you are subject to the requirements for a site-specific plan for mercury under paragraph (b)(1) of this section, you must:(i) Maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered; and(ii) Submit semiannual reports of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, an estimate of the percent of mercury switches recovered, and a certification that the recovered mercury switches were recycled at RCRA-permitted facilities. The semiannual reports must include a certification that you have conducted inspections or taken other means of corroboration as required under paragraph (b)(1)(ii)(C) of this section. You may include this information in the semiannual compliance reports required under paragraph (c)(3) of this section.(2) If you are subject to the option for approved mercury programs under paragraph (b)(2) of this section, you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If you purchase motor vehicle scrap from a broker, you must maintain records identifying each broker and documentation that all scrap provided by the broker was obtained from other scrap providers who participate in an approved mercury switch removal program.(3) You must submit semiannual compliance reports to the Administrator for the control of contaminants from scrap according to the requirements in § 63.10(e). The report must clearly identify any deviation from the requirements in paragraphs (a) and (b) of this section and the corrective action taken. You must identify which compliance option in paragraph (b) of this section applies to each scrap provider, contract, or shipment.
-
Table 8 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 1 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.16 apply to you.
-
Table 1 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.16 apply to you.
-
Table 1 of this subpart shows which parts of the General Provisions in §§ 63.1 through 63.16 apply to you.
-
Table 1 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.16 apply to you.
-
Table 1 of this subpart shows which parts of the General Provisions in §§ 63.1 through 63.16 apply to you.
-
Table 1 of this subpart shows which parts of the General Provisions in §§ 63.1 through 63.16 apply to you.
-
Table 1 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.16 apply to you.
-
(d) Records must be maintained in a form suitable and readily available for expeditious review, according to § 63.10 of the General Provisions that are referenced in Table 1 to this subpart. Electronic recordkeeping is encouraged.
-
-
(a) The owner or operator of an affected source shall comply with the reporting requirements of paragraphs (b) through (n) of this section. Applicable reporting requirements of §§ 63.9 and 63.10 are also summarized in Table 1 of this subpart.
-
(b) The owner or operator of an affected source shall comply with the reporting requirements specified in § 63.10 of the general provisions of this part 63, subpart A as follows:(1) As required by § 63.10(d)(2), the owner or operator shall report the results of performance tests as part of the notification of compliance status.(2) As required by § 63.10(d)(3), the owner or operator of an affected source shall report the opacity results from tests required by § 63.1349.(3) As required by § 63.10(d)(4), the owner or operator of an affected source who is required to submit progress reports as a condition of receiving an extension of compliance under § 63.6(i) shall submit such reports by the dates specified in the written extension of compliance.(4) -(5) [Reserved](6) As required by § 63.10(e)(2), the owner or operator shall submit a written report of the results of the performance evaluation for the continuous monitoring system required by § 63.8(e). The owner or operator shall submit the report simultaneously with the results of the performance test.(7) As required by § 63.10(e)(2), the owner or operator of an affected source using a continuous opacity monitoring system to determine opacity compliance during any performance test required under § 63.7 and described in § 63.6(d)(6) shall report the results of the continuous opacity monitoring system performance evaluation conducted under § 63.8(e).(8) As required by § 63.10(e)(3), the owner or operator of an affected source equipped with a continuous emission monitor shall submit an excess emissions and continuous monitoring system performance report for any event when the continuous monitoring system data indicate the source is not in compliance with the applicable emission limitation or operating parameter limit.(9) The owner or operator shall submit a summary report semiannually within 60 days of the reporting period to the EPA via the Compliance and Emissions Data Reporting Interface (CEDRI). (CEDRI can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). You must use the appropriate electronic report in CEDRI for this subpart. Instead of using the electronic report in CEDRI for this subpart, you may submit an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/compliance-and-emissions-data-reporting-interface-cedri), once the XML schema is available. If the reporting form specific to this subpart is not available in CEDRI at the time that the report is due, you must submit the report the Administrator at the appropriate address listed in § 63.13. You must begin submitting reports via CEDRI no later than 90 days after the form becomes available in CEDRI. The excess emissions and summary reports must be submitted no later than 60 days after the end of the reporting period, regardless of the method in which the reports are submitted. The report must contain the information specified in § 63.10(e)(3)(vi). In addition, the summary report shall include:(i) All exceedances of maximum control device inlet gas temperature limits specified in § 63.1346(a) and (b);(ii) Notification of any failure to calibrate thermocouples and other temperature sensors as required under § 63.1350(g)(1)(iii) of this subpart; and(iii) Notification of any failure to maintain the activated carbon injection rate, and the activated carbon injection carrier gas flow rate or pressure drop, as applicable, as required under § 63.1346(c)(2).(iv) Notification of failure to conduct any combustion system component inspections conducted within the reporting period as required under § 63.1347(a)(3).(v) Any and all failures to comply with any provision of the operation and maintenance plan developed in accordance with § 63.1347(a).(vi) For each PM CPMS, HCl, Hg, and THC CEMS, SO2 CEMS, or Hg sorbent trap monitoring system, within 60 days after the reporting periods, you must report all of the calculated 30-operating day rolling average values derived from the CPMS, CEMS, CMS, or Hg sorbent trap monitoring systems.(vii) In response to each violation of an emissions standard or established operating parameter limit, the date, duration and description of each violation and the specific actions taken for each violation including inspections, corrective actions and repeat performance tests and the results of those actions.(10) If the total continuous monitoring system downtime for any CEM or any CMS for the reporting period is 10 percent or greater of the total operating time for the reporting period, the owner or operator shall submit an excess emissions and continuous monitoring system performance report along with the summary report.(i) You must submit the information specified in paragraphs (b)(11)(i)(A) and (B) of this section no later than 60 days following the initial performance test. All reports must be signed by a responsible official.(A) The initial performance test data as recorded under § 63.1349(a).(B) The values for the site-specific operating limits or parameters established pursuant to § 63.1349(b)(1), (3), (6), (7), and (8), as applicable, and a description, including sample calculations, of how the operating parameters were established during the initial performance test.(C) As of December 31, 2011, and within 60 days after the date of completing each performance evaluation or test, as defined in § 63.2, conducted to demonstrate compliance with any standard covered by this subpart, you must submit the relative accuracy test audit data and performance test data, except opacity data, to the EPA by successfully submitting the data electronically via CEDRI and by using the Electronic Reporting Tool (ERT) (see https://www.epa.gov/electronic-reporting-air-emissions/electronic-reporting-tool-ert). For any performance evaluations with no corresponding RATA pollutants listed on the ERT website, you must submit the results of the performance evaluation to the Administrator at the appropriate address listed in § 63.13.(ii) For PM performance test reports used to set a PM CPMS operating limit, the electronic submission of the test report must also include the make and model of the PM CPMS instrument, serial number of the instrument, analytical principle of the instrument (e.g. beta attenuation), span of the instruments primary analytical range, milliamp value equivalent to the instrument zero output, technique by which this zero value was determined, and the average milliamp signals corresponding to each PM compliance test run.(12) All reports required by this subpart not subject to the requirements in paragraphs (b)(9) introductory text and (b)(11)(i) of this section must be sent to the Administrator at the appropriate address listed in § 63.13. The Administrator or the delegated authority may request a report in any form suitable for the specific case (e.g., by commonly used electronic media such as Excel spreadsheet, on CD or hard copy). The Administrator retains the right to require submittal of reports subject to paragraphs (b)(9) introductory text and (b)(11)(i) of this section in paper format.
-
(a) The owner or operator of an affected source shall comply with the reporting requirements of paragraphs (b) through (l) of this section. The owner or operator shall also comply with applicable paragraphs of §§ 63.9 and 63.10 of subpart A of this part, as specified in Table 1 of this subpart.
-
Table 1 to this subpart shows which parts of the general provisions in §§ 63.1 through 63.15 apply to you.
-
-
Table 44 of this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Terms used in this subpart are defined in the Clean Air Act (CAA), in 40 CFR 63.2, the General Provisions of this part (§§ 63.1 through 63.15), and in this section as listed. If the same term is defined in subpart A of this part and in this section, it shall have the meaning given in this section for purposes of this subpart.
-
(a) You must comply with all of the recordkeeping and reporting requirements specified in § 63.10 of the General Provisions that are referenced in Table 1 to this subpart.(1) Records must be maintained in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). However, electronic recordkeeping and reporting is encouraged and required for some records and reports.(2) Records must be kept on site for at least 2 years after the date of occurrence, measurement, maintenance, corrective action, report, or record, according to § 63.10(b)(1).
-
(a) The owner or operator of a ferromanganese and silicomanganese production facility must comply with all of the reporting requirements under § 63.10 of subpart A, unless otherwise specified in this subpart.(1) As provided by § 63.10(a)(5), if the owner or operator is required to submit periodic reports to a State on an established time line, he or she may change the dates by which periodic reports submitted under this part may be submitted (without changing the frequency of reporting) to be consistent with the State's schedule by mutual agreement between the owner or operator and the State. This provision may be applied at any point after the source's compliance date.(2) As required by § 63.10(d)(2), the owner or operator of an affected source must report the results of the initial performance test as part of the notification of compliance status required in § 63.1658(f).(3) [Reserved](4) . If a malfunction occurred during the reporting period, the report must include the number, duration and a brief description for each type of malfunction which occurred during the reporting period and which caused or may have caused any applicable emission limitation to be exceeded. The report must also include a description of actions taken by an owner or operator during a malfunction of an affected source to minimize emissions in accordance with § 63.1652(f), including actions taken to correct a malfunction.
-
(1) The owner or operator of a ferromanganese and silicomanganese production facility must comply with all of the recordkeeping requirements under § 63.10.
-
(b) All provisions in §§ 63.1 through 63.15 of subpart A of this part which apply to owners and operators of sources subject to subparts I and H of this part, are:(1) The applicability provisions of § 63.1 (a)(1), (a)(2), (a)(10), (a)(12) through (a)(14);(3) The units and abbreviations in § 63.3;(4) The prohibited activities and circumvention provisions of § 63.4 (a)(1), (a)(2), (a)(3), (a)(5), and (b);(5) The construction and reconstruction provisions of § 63.5(a), (b)(1), (b)(3), (d) (except the review is limited to the equipment subject to the provisions of subpart H), (e), and (f);(i) Except as specified in paragraph (b)(12) of this section, the compliance with standards and maintenance requirements of § 63.6(a), (b)(3), (c)(5), (e), (i)(1), (i)(2), (i)(4)(i)(A), (i)(6)(i), (i)(8) through (i)(10), (i)(12) through (i)(14), (i)(16), and (j);(ii) Except as specified in paragraph (b)(12) of this section, the operational and maintenance requirements of § 63.6(e). The startup, shutdown, and malfunction plan requirement of § 63.6(e)(3) is limited to control devices subject to the provisions of subpart H of this part and is optional for other equipment subject to subpart H. The startup, shutdown, and malfunction plan may include written procedures that identify conditions that justify a delay of repair. On and after July 15, 2027, the last two sentences of this paragraph do not apply.(7) With respect to flares, except as specified in paragraph (b)(12) of this section, the performance testing requirements of § 63.7(a)(3), (d), (e)(1), (e)(2), (e)(4), and (h);(8) The notification requirements of § 63.9 (a)(1), (a)(3), (a)(4), (b)(1)(i), (b)(4), (b)(5) (except, use the schedule specified in subpart H), (c), (d), and (i);(10) Except as specified in paragraph (b)(12) of this section, the control device requirements of § 63.11(b); and(12) On and after July 15, 2027, § 63.6(e)(1)(i), (e)(1)(ii), and (e)(3), § 63.7(e)(1), and § 63.11(b) do not apply. Instead, you must comply with paragraphs (b)(12)(i) through (iii) of this section.(i) The owner or operator of a source subject to this subpart shall comply with the requirements at all times, except during periods of nonoperation of the source (or specific portion thereof) resulting in cessation of the emissions to which this subpart or subpart H of this part applies.(ii) At all times, owners and operators subject to this subpart must operate and maintain any source, including associated air pollution control equipment and monitoring equipment, in a manner consistent with safety and good air pollution control practices for minimizing emissions. The general duty to minimize emissions does not require owners and operators to make any further efforts to reduce emissions if levels required by the applicable standard have been achieved. Determination of whether a source is operating in compliance with operation and maintenance requirements will be based on information available to the Administrator which may include, but is not limited to, monitoring results, review of operation and maintenance procedures, review of operation and maintenance records, and inspection of the source.(iii) Owners and operators that use a flare to comply with this subpart must comply with § 63.108.
-
(2) The specific applicability provisions in § 63.1(b) through (e) except for the reference to § 63.10 for recordkeeping procedures.
-
Table 6 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Terms used in this subpart are defined in the Clean Air Act, in 40 CFR 63.2, in the General Provisions of this part (§§ 63.1 through 63.15), and in this section as follows:
-
Table 10 to this subpart shows which parts of the general provisions in §§ 63.1 through 63.16 apply to you.
-
Table 12 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 12 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 1 of this section shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you. Table 1 of § 63.2870 follows:
-
You must maintain records according to the procedures of § 63.10. You must maintain the records listed in paragraphs (a) through (i) of this section.
-
Table 2 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
-
Table 5 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
(a) You are subject to the requirements of this subpart if you own or operate a sterilization facility that has an affected source specified in paragraph (b) of this section. Table 6 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 2 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 2 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 3 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 2 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
(a) The owner or operator of each affected source subject to the requirements of this subpart shall comply with the recordkeeping requirements of § 63.10, as shown in Table 1 of this subpart, and the requirements specified in paragraphs (b) through (g) of this section for the monitoring parameters specified in § 63.453.
-
(i) Each owner or operator shall comply with the reporting requirements as specified in Table 1 of § 63.10.
-
Table 4 to this subpart indicates which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 2 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
(a) The owner or operator of any affected BLR source shall keep records of daily average values of equipment operating parameters specified to be monitored under § 63.526(a) or specified by the Administrator. Records shall be kept in accordance with the requirements of applicable paragraphs of § 63.10 of subpart A of this part, as specified in the General Provisions applicability table of this subpart. The owner or operator shall keep records up-to-date and readily accessible.(1) A daily (24-hour) average shall be calculated as the average of all values for a monitored parameter recorded during the operating day. The average shall cover a 24-hour period if operation is continuous, or the number of hours of operation per operating day if operation is not continuous.(2) The operating day shall be the period defined in the operating permit or the Notification of Compliance Status in § 63.9(h) of subpart A of this part. It may be from midnight to midnight or another continuous 24-hour period.(3) In the event of an excursion, the owner or operator must keep records of each 15-minute reading during the period in which the excursion occurred.
-
(a) The owner or operator of any affected BLR source, as well as the owner or operator of any affected WSR source that is subject to the emission limit for process vents, storage tanks, and wastewater systems and/or is subject to the dioxins and furans emission limit for process vents, shall comply with the reporting requirements of applicable paragraphs of § 63.10, as specified in the General Provisions applicability table in this subpart. The owner or operator shall also submit to the Administrator, as part of the quarterly excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e)(3), the following recorded information. On and after July 15, 2027 or once the reporting template for this subpart has been available on the CEDRI website for 1 year, whichever date is later, owners and operators must submit all subsequent reports following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Polymers and Resins Sector Lead. Owners and operators must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports under § 63.9(i) and § 63.10(a), the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. If a report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirements in § 63.10(e)(3)(v), § 63.10(e)(3)(vi)(L), and § 63.10(e)(3)(vi)(M) to submit the date of the report and the name, title, and signature of the responsible official who is certifying the accuracy of the report.(1) Reports of monitoring data, including 15-minute monitoring values as well as daily average values or per-unit operation average values, as applicable, of monitored parameters for all operating days or unit operations when the average values were outside the ranges established in the Notification of Compliance Status or operating permit, including reports specified in paragraph (a)(4) of this section.(2) Reports of the duration of periods when monitoring data is not collected for each excursion caused by insufficient monitoring data, including reports specified in paragraph (a)(4) of this section. An excursion means any of the three cases listed in paragraph (a)(2)(i) or (a)(2)(ii) of this section. For a control device where multiple parameters are monitored, if one or more of the parameters meets the excursion criteria in paragraph (a)(2)(i) or (a)(2)(ii) of this section, this is considered a single excursion for the control device. In the report, include the identification of the source, start date, start time, duration in hours, and monitored parameter(s) meeting the excursion criteria.(i) When the period of control device operation is 4 hours or greater in an operating day and monitoring data are insufficient to constitute a valid hour of data, as defined in paragraph (a)(2)(iii) of this section, for at least 75 percent of the operating hours.(ii) When the period of control device operation is less than 4 hours in an operating day and more than one of the hours during the period of operation does not constitute a valid hour of data due to insufficient monitoring data.(iii) Monitoring data are insufficient to constitute a valid hour of data, as used in paragraphs (a)(2)(i) and (ii) of this section, if measured values are unavailable for any of the 15-minute periods within the hour.(3) Whenever a process change, as defined in § 63.115(e), is made that causes the emission rate from a de minimis emission point to become a process vent with an emission rate of one pound per year or greater, the owner or operator shall submit a report within 180 calendar days after the process change. The report may be submitted as part of the next summary report required under § 63.10(e)(3). The report shall include:(i) A description of the process change; and(4) For each existing, new, or reconstructed affected BLR and WSR source, beginning no later than the compliance dates specified in § 63.521(c), for each excursion that is not an excused excursion, the report must include a list of the affected sources or equipment, the monitored parameter, an estimate of the quantity in pounds of each regulated pollutant emitted over any emission limit, a description of the method used to estimate the emissions, the cause of the excursion (including unknown cause, if applicable), as applicable, and the corrective action taken. Include the start date, start time, and duration in hours of each excursion.(5) For pressure relief device subject to § 63.527(f), report each pressure release to the atmosphere, including pressure relief device identification name or number, the start date, start time, and duration (in minutes) of the pressure release; and an estimate of the mass quantity in pounds of each organic HAP released.(6) For heat exchangers subject to § 63.104 of subpart F of this part, the information specified in § 63.104(f)(2) of subpart F of this part.
-
Table 2 of this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
(a) You must comply with all of the recordkeeping and reporting requirements specified in § 63.10 that are referenced in Table 1 to this subpart.(1) Records must be maintained in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). However, electronic recordkeeping and reporting if suitable for the specific case (e.g., by electronic media such as Excel spreadsheet, on CD or hard copy), and when required by this subpart.(2) Records must be kept on site for at least 2 years after the date of occurrence, measurement, maintenance, corrective action, report, or record, according to § 63.10(b)(1).
-
(b) Unless the Administrator has approved a different schedule for submitting reports under § 63.10, you must submit each compliance report by the date in Table 8 to this subpart and according to the requirements in paragraphs (b)(1) through (6) of this section.(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.5495 and ending on June 30 or December 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for your source in § 63.5495.(2) The first compliance report must be submitted no later than August 31 or February 28, whichever date follows the end of the first calendar half after the compliance date that is specified for your affected source in § 63.5495.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be submitted no later than August 31 or February 28, whichever date is the first date following the end of the semiannual reporting period.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) through (4) of this section.(6) Prior to December 29, 2020, all compliance reports submitted by mail must be postmarked or delivered no later than the dates specified in paragraphs (b)(1) through (5). Beginning on December 29, 2020, you must submit all compliance reports following the procedure specified in paragraph (g) of this section by the dates specified in paragraphs (b)(1) through (5).
-
(a) Table 10 to this subpart shows which provisions of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
(a) The owner or operator of an affected source shall fulfill all reporting and recordkeeping requirements in §§ 63.9 and 63.10 of subpart A of this part in accordance with the provisions for applicability of subpart A to this subpart in Table 1 of § 63.560 and fulfill all reporting and recordkeeping requirements in this section. These reports will be made to the Administrator at the appropriate address identified in § 63.13 of subpart A of this part.(1) Reports required by subpart A and this section may be sent by U.S. mail, facsimile (fax), or by another courier.(i) Submittals sent by U.S. mail shall be postmarked on or before the specified date.(ii) Submittals sent by other methods shall be received by the Administrator on or before the specified date.(2) If acceptable to both the Administrator and the owner or operator of a source, reports may be submitted on electronic media.
-
Table 15 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 17 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
(b) You must comply with the reporting and recordkeeping requirements in § 63.10 as specified in paragraphs (b)(1) through (5) of this section.(1) You must comply with the general recordkeeping requirements in § 63.10(b)(1).(2) As required by § 63.10(d), you must report the results of the initial and subsequent performance tests as part of the notification of compliance status required in § 63.9(h). You must verify in the performance test reports that the operating limits for each process have not changed or provide documentation of revised operating limits established according to § 63.605, as applicable. In the notification of compliance status, you must also:(i) Certify to the Administrator annually that you have complied with the evaporative cooling tower requirements specified in § 63.602(c).(ii) Submit analyses and supporting documentation demonstrating conformance with the Office Of Air Quality Planning And Standards (OAQPS), Fabric Filter Bag Leak Detection Guidance (incorporated by reference, see § 63.14) and specifications for bag leak detection systems as part of the notification of compliance status report.(iii) Submit the gypsum dewatering stack and cooling pond management plan specified in § 63.602(e).(iv) If you elect to demonstrate compliance by following the procedures in § 63.605(d)(1)(ii)(B), certify to the Administrator annually that the control devices and processes have not been modified since the date of the performance test from which you obtained the data used to establish the allowable ranges.(v) Each time a gypsum dewatering stack is closed, certify to the Administrator within 90 days of closure, that the final cover of the closed gypsum dewatering stack is a drought resistant vegetative cover that includes a barrier soil layer that will sustain vegetation.(3) As required by § 63.10(e)(3), you must submit an excess emissions report for any exceedance of an emission limit, work practice standard, or operating parameter limit if the total duration of the exceedances for the reporting period is 1 percent of the total operating time for the reporting period or greater. The report must contain the information specified in § 63.10 and paragraph (b)(4) of this section. When exceedances of an emission limit or operating parameter have not occurred, you must include such information in the report. You must submit the report semiannually and the report must be delivered or postmarked by the 30th day following the end of the calendar half. If you report exceedances, you must submit the excess emissions report quarterly until a request to reduce reporting frequency is approved as described in § 63.10(e)(3)(ii).(4) In the event that an affected unit fails to meet an applicable standard, record and report the following information for each failure:(v) A record of actions taken to minimize emissions in accordance with § 63.608(b), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.(5) You must submit a summary report containing the information specified in § 63.10(e)(3)(vi). You must submit the summary report semiannually and the report must be delivered or postmarked by the 30th day following the end of the calendar half.
-
(b) You must comply with the reporting and recordkeeping requirements in § 63.10 as specified in paragraphs (b)(1) through (5) of this section.(1) You must comply with the general recordkeeping requirements in § 63.10(b)(1); and(2) As required by § 63.10(d), you must report the results of the initial and subsequent performance tests as part of the notification of compliance status required in § 63.9(h). You must verify in the performance test reports that the operating limits for each process have not changed or provide documentation of revised operating limits established according to § 63.625, as applicable. In the notification of compliance status, you must also:(i) Certify to the Administrator that you have not shipped fresh granular triple superphosphate from an affected facility.(ii) Certify to the Administrator annually that you have complied with the evaporative cooling tower requirements specified in § 63.622(c).(iii) Submit analyses and supporting documentation demonstrating conformance with the Office Of Air Quality Planning And Standards (OAQPS), Fabric Filter Bag Leak Detection Guidance (incorporated by reference, see § 63.14) and specifications for bag leak detection systems as part of the notification of compliance status report.(iv) If you elect to demonstrate compliance by following the procedures in § 63.625(d)(1)(ii)(B), certify to the Administrator annually that the control devices and processes have not been modified since the date of the performance test from which you obtained the data used to establish the allowable ranges.(3) As required by § 63.10(e)(1), you must submit an excess emissions report for any exceedance of an emission or operating parameter limit if the total duration of the exceedances for the reporting period is 1 percent of the total operating time for the reporting period or greater. The report must contain the information specified in § 63.10 and paragraph (b)(4) of this section. When exceedances of an emission limit or operating parameter have not occurred, you must include such information in the report. You must submit the report semiannually and the report must be delivered or postmarked by the 30th day following the end of the calendar half. If exceedances are reported, you must submit the excess emissions report quarterly until a request to reduce reporting frequency is approved as described in § 63.10(e)(3).(4) In the event that an affected unit fails to meet an applicable standard, record and report the following information for each failure:(v) A record of actions taken to minimize emissions in accordance with § 63.628(b), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.(5) You must submit a summary report containing the information specified in § 63.10(e)(3)(vi). You must submit the summary report semiannually and the report must be delivered or postmarked by the 30th day following the end of the calendar half.
-
Table 8 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you. If you own or operate a new or reconstructed stationary RICE with a site rating of less than or equal to 500 brake HP located at a major source of HAP emissions (except new or reconstructed 4SLB engines greater than or equal to 250 and less than or equal to 500 brake HP), a new or reconstructed stationary RICE located at an area source of HAP emissions, or any of the following RICE with a site rating of more than 500 brake HP located at a major source of HAP emissions, you do not need to comply with any of the requirements of the General Provisions specified in Table 8: An existing 2SLB stationary RICE, an existing 4SLB stationary RICE, an existing stationary RICE that combusts landfill or digester gas equivalent to 10 percent or more of the gross heat input on an annual basis, an existing emergency stationary RICE, or an existing limited use stationary RICE. If you own or operate any of the following RICE with a site rating of more than 500 brake HP located at a major source of HAP emissions, you do not need to comply with the requirements in the General Provisions specified in Table 8 except for the initial notification requirements: A new stationary RICE that combusts landfill gas or digester gas equivalent to 10 percent or more of the gross heat input on an annual basis, a new emergency stationary RICE, or a new limited use stationary RICE.
-
-
(2) The owner or operator of an affected source must submit reports to the Administrator in accordance with the applicable reporting requirements in 40 CFR 63.10 as specified in Table 2 of this subpart.
-
(a) Except as stipulated in § 63.703 (b), (c)(5), and (h), the owner or operator of a magnetic tape manufacturing operation subject to this subpart shall fulfill all applicable recordkeeping requirements in § 63.10 of subpart A, as outlined in Table 1.
-
(a) Except as stipulated in § 63.703(b), (c)(5), and (h), the owner or operator of a magnetic tape manufacturing operation subject to this subpart shall fulfill all applicable reporting requirements in § 63.7 through § 63.10, as outlined in Table 1 to this subpart. These reports shall be submitted to the Administrator or delegated State.
-
Table 9 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.16 apply to you. When there is overlap between subpart A and subpart AAAAA, as indicated in the “Explanations” column in Table 8, subpart AAAAA takes precedence.
-
Table 2 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.13 apply to you.
-
Table 1 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 10 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 1 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 4 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 3 of this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
(a) The owner or operator of an affected source subject to this subpart shall fulfill all recordkeeping requirements of § 63.10 of subpart A, according to the applicability criteria in § 63.800(d) of this subpart.
-
(a) The owner or operator of an affected source subject to this subpart shall fulfill all reporting requirements of § 63.7 through § 63.10 of subpart A (General Provisions) according to the applicability criteria in § 63.800(d) of this subpart.
-
Table 10 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 10 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.13 apply to you.
-
(d) . In addition to the information required under § 63.10 of the General Provisions, the owner or operator must provide semiannual reports containing the information specified in paragraphs (d)(1) and (2) of this section to the Administrator or designated authority.(1) As required by § 63.10(e)(3), the owner or operator must submit a report (or a summary report) if measured emissions are in excess of the applicable standard. The report must contain the information specified in § 63.10(e)(3)(v) and be submitted semiannually unless quarterly reports are required as a result of excess emissions.(2) If there was a malfunction during the reporting period, the owner or operator must submit a report that includes the number, duration and a brief description for each type of malfunction which occurred during the reporting period and which caused or may have caused any applicable emission limitation to be exceeded. The report must also include a description of actions taken by an owner or operator during a malfunction of an affected source to minimize emissions in accordance with §§ 63.843(f) and 63.844(f), including actions taken to correct a malfunction.
-
Table 10 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.16 apply to you.
-
Table 11 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.16 apply to you.
-
Table 7 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 7 to this subpart shows which sections of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
(a) Table 7 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
-
Table 7 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 1 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
-
Table 4 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.16 apply to you.
-
Table 11 to this subpart shows which parts of the General Provisions specified in §§ 63.1 through 63.16 apply to you.
-
Table 4 to this subpart shows which parts of the General Provisions in §§ 63.1 through 63.15 apply to you.
Citations to §63.10(2)(i)
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
Citations to §63.10(a)
-
(j) You must comply with the following requirements of the general provisions in subpart A of this part: §§ 63.1 through 63.5; § 63.6(a), (b), and (c); § 63.9; § 63.10(a), (b)(1), (b)(2)(xiv), (b)(3), (d)(1) and (4), and (f); and §§ 63.13 through 63.16. Requirements of the general provisions not cited in the preceding sentence do not apply to the owner or operator of a new or existing affected source that is classified as a small foundry.
-
(ii) Beginning no later than the compliance dates specified in § 63.1102(c) through (e), the owner or operator must submit all subsequent Notification of Compliance Status reports required under paragraph (a)(4) of this section in portable document format (PDF) format to the EPA following the procedure specified in § 63.9(k). All subsequent Periodic Reports required under paragraph (a)(5) of this section must be submitted to the EPA via CEDRI using the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart and following the procedure specified in § 63.9(k) beginning no later than the compliance dates specified in § 63.1102(c) through (e) or once the report template has been available on the CEDRI website for 1 year, whichever date is later. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated State agency or other authority has approved a different schedule for submission of reports under §§ 63.9(i) and 63.10(a) of subpart A, the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Any medium submitted through mail under § 63.9(k) for a Notification of Compliance Status report or Periodic Report must be sent to the attention of the Ethylene Production Sector Lead, Cyanide Chemicals Manufacturing Sector Lead, or Carbon Black Production Sector Lead, as appropriate.
-
(2) Unless the Administrator has approved or agreed to a different schedule for submission of reports under § 63.10(a), “General Provisions,” you must prepare and submit each annual certification and compliance report according to the dates specified in paragraphs (b)(2)(i) through (iii) of this section. Note that the information reported for each of the months in the reporting period will be based on the last 12 months of data prior to the date of each monthly calculation.(i) The first annual certification and compliance report must cover the first annual reporting period which begins the day after the compliance date and ends on December 31.(ii) Each subsequent annual certification and compliance report must cover the subsequent semiannual reporting period from January 1 through December 31.(iii) Each annual certification and compliance report must be prepared and submitted no later than January 31 and kept in a readily-accessible location for inspector review. If an exceedence has occurred during the year, each annual certification and compliance report must be submitted along with the exceedence reports, and postmarked or delivered no later than January 31.
-
(4) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report specified in paragraph (b) of this section according to the following dates:(i) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.11560 and ending on June 30 or December 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for your source in § 63.11560.(ii) The first compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date follows the end of the first calendar half after the compliance date that is specified for your affected source in § 63.11560.(iii) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(iv) Each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.
-
(2) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each compliance report specified in Table 5 of this subpart according to the following dates:(i) If deviations occur, then:(A) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.11580 and ending on June 30 or December 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for your source in § 63.11580 (i.e., December 31 for a source that is existing with a compliance date of December 30, 2010).(B) The first compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date follows the end of the first calendar half after the compliance date that is specified for your affected source in § 63.11580 (i.e., January 31 for a source that is existing with a compliance date of December 30, 2010).(C) Each subsequent compliance report for a period in which deviations occur must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(D) Each subsequent compliance report for a period in which deviations occur must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(ii) If no deviations occur, then:(A) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.11580 and ending on December 31 following the end of the first calendar year after the compliance date that is specified for your source in § 63.11580.(B) The first compliance report must be postmarked or delivered no later than January 31 following the end of the first calendar year after the compliance date that is specified for your affected source in § 63.11580.(C) Each subsequent compliance report for a period in which deviations occur must cover the annual reporting period from January 1 through December 31.(D) Each subsequent compliance report for a period in which no deviations occur must be postmarked or delivered no later than January 31 immediately following the previous calendar year.
-
(6) For existing and new affected sources, the owner or operator shall submit Periodic Reports as specified in paragraphs (e)(6)(i) through (x) of this section. In addition, for equipment leaks subject to § 63.1434, the owner or operator shall submit the information specified in the HON periodic reporting requirements in § 63.182(d) as part of the Periodic Report required by this paragraph (e)(6), and for heat exchange systems subject to § 63.1434, the owner or operator shall submit the information specified in the HON heat exchange system reporting requirements in § 63.104(f)(2) as part of the Periodic Report required by this paragraph (e)(6). On and after March 18, 2029 or once the reporting template for this subpart has been available on the CEDRI website for 1 year, whichever date is later, owners and operators shall submit all subsequent reports following the procedure specified in § 63.9(k). Owners and operators shall use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports under §§ 63.9(i) and 63.10(a), the report shall be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted.(i) Except as specified in paragraphs (e)(6)(viii) of this section, a report containing the information in paragraph (e)(6)(ii) of this section or paragraphs (e)(6)(iii) through (vii) of this section, as appropriate, shall be submitted semiannually no later than 60 days after the end of each 180-day period. The first report shall be submitted no later than 240 days after the date the Notification of Compliance Status is due and shall cover the 6-month period beginning on the date the Notification of Compliance Status is due. Subsequent reports shall cover each preceding 6-month period. All periodic reports shall contain the company name and address (including county), as well as the beginning and ending dates of the reporting period.(ii) If none of the compliance exceptions in paragraphs (e)(6)(iii) through (vii) of this section occurred during the 6-month period, the Periodic Report required by paragraph (e)(6)(i) of this section shall be a statement that there were no compliance exceptions, as described in this paragraph, for the 6-month period covered by that report and that none of the activities specified in paragraphs (e)(6)(iii) through (vii) of this section occurred during the period covered by that report.(iii) For an owner or operator of an affected source complying with the provisions of §§ 63.1432, 63.1433, and 63.1434(i) for any emission point, Periodic Reports shall include:(A) All information specified in the HON periodic reporting requirements in § 63.122(a)(4) for storage vessels and in § 63.146(c) through (f) for process wastewater. In addition, if you comply with § 63.1433(a)(23)(iii)(D) and annual sampling shows that the combined ethylene oxide load of the excluded wastewater streams prior to treatment is 1.0 megagram per year or greater, you must document this in the Periodic Report and also include the actual combined ethylene oxide load prior to treatment, how the combined load was determined, and sampling dates and results for each wastewater stream contributing to the combined load. Beginning no later than the compliance dates specified in § 63.1422(h), include all information specified in § 63.130(d) for transfer racks. Beginning no later than the compliance dates specified in § 63.1422(h), for storage vessels in ethylene oxide service subject to the requirements of § 63.124, the Periodic Report must include the information specified in § 63.123(k)(2). Indicate the start date, start time, and duration in hours for each period.(B) The daily average values or, for parameters used to comply with § 63.1425(g) or 63.1432(s)(3), the 1-hour block average values of monitored parameters for all excursions, as defined in § 63.1438(f). Beginning no later than the compliance dates specified in § 63.1422(h), for each excursion, report the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, a description of the method used to estimate the emissions, actions taken to minimize emissions, and any corrective action taken to return the affected unit to its normal or usual manner of operation.(C) The periods when monitoring data were not collected shall be specified and, beginning no later than the compliance dates specified in § 63.1422(h), including start date, start time, and duration in hours; and(D) The information in paragraphs (e)(6)(iii)(D)(1) through (3) of this section, as applicable:(1) Notification if a process change is made such that the group status of any emission point changes from Group 2 to Group 1. The owner or operator is not required to submit a notification of a process change if that process change caused the group status of an emission point to change from Group 1 to Group 2. However, until the owner or operator notifies the Administrator that the group status of an emission point has changed from Group 1 to Group 2, the owner or operator is required to continue to comply with the Group 1 requirements for that emission point. This notification may be submitted at any time.(2) Notification if one or more emission points (other than equipment leak components subject to § 63.1434), or one or more PMPU is added to an affected source. The owner or operator shall submit the information contained in paragraphs (e)(6)(iii)(D)(2)(i) and (ii) of this section.(i) A description of the addition to the affected source.(ii) Notification of the group status or control requirement for the additional emission point or all emission points in the PMPU.(3) For gas streams sent for disposal pursuant to § 63.113(i) or for process wastewater streams sent for treatment pursuant to § 63.132(g), reports of changes in the identity of the treatment facility or transferee.(E) Before March 18, 2029, the information in paragraph (b)(1)(ii) of this section for reports of malfunctions.(iv) If any performance tests are reported in a Periodic Report, the following information shall be included:(A) One complete test report shall be submitted for each test method used for a particular kind of emission point tested. A complete test report shall contain the information specified in paragraph (e)(5)(i)(B) of this section.(B) For additional tests performed for the same kind of emission point using the same method, results and any other information required by the test method to be in the test report shall be submitted, but a complete test report is not required.(C) If the performance test results have been submitted electronically through CEDRI in accordance with paragraph (e)(9) of this section, the process unit(s) tested, the pollutant(s) tested, and the date that such performance test was conducted must be submitted in the Period Report in lieu of the information required in paragraphs (e)(6)(iv)(A) and (B) of this section. The performance test results must be submitted to CEDRI by the date the Periodic Report is submitted.(v) The results for each change made to a primary product determination for a PMPU made under § 63.1420(e)(3) or (10).(vi) The results for each reevaluation of the applicability of this subpart to a storage vessel that begins receiving material from (or sending material to) a process unit that was not included in the initial determination, or a storage vessel that ceases to receive material from (or send material to) a process unit that was included in the initial determination, in accordance with § 63.1420(f)(8).(vii) The Periodic Report required by the equipment leak provisions in § 63.1434(f) shall be submitted as part of the Periodic Report required by paragraph (e)(6) of this section. Additionally, for equipment in ethylene oxide service, you must include the information in paragraphs (e)(6)(vii)(A) through (E) of this section in the Periodic Report. If there are more than five pieces of equipment in ethylene oxide service on delay of repair during the reporting period, include the total number of pieces of equipment in ethylene oxide service in the Periodic Report.(C) An indication of whether the equipment has been successfully repaired, and if so, the date of successful repair (remonitoring date).(D) An indication of whether the equipment has been isolated from the process such that it is no longer in ethylene oxide service, and if so, the date that the equipment was successfully isolated from the process.(E) An indication of whether any monthly monitoring event resulted in an instrument reading of 1,000 parts per million or greater, and if so, the date of the monitoring event.(viii) The owner or operator of an affected source shall submit quarterly reports for particular emission points and process sections as specified in paragraphs (e)(6)(viii)(A) through (D) of this section.(A) The owner or operator of an affected source shall submit quarterly reports for a period of 1 year for an emission point or process section if the emission point or process section meets the conditions in paragraph (e)(6)(viii)(A)(1) or (2) of this section.(1) A combustion, recovery, or recapture device for a particular emission point or process section has one or more excursions, as defined in § 63.1438(f), in two consecutive semiannual reporting periods; or(2) The Administrator requests the owner or operator to submit quarterly reports for that emission point or process section.(B) The quarterly reports shall include all information specified in paragraphs (e)(6)(iii) through (vii) of this section, as applicable to the emission point or process section for which quarterly reporting is required under paragraph (e)(6)(viii)(A) of this section. Information applicable to other emission points within the affected source shall be submitted in the semiannual reports required under paragraph (e)(6)(i) of this section.(C) Quarterly reports shall be submitted no later than 60 days after the end of each quarter.(D) After quarterly reports have been submitted for an emission point for 1 year without one or more excursions occurring (during that year), the owner or operator may return to semiannual reporting for the emission point or process section.(ix) For pressure relief devices in organic HAP service, Periodic Reports must include the information specified in paragraphs (e)(6)(ix)(A) through (C) of this section.(A) For pressure relief devices in organic HAP service subject to § 63.1434(c), report confirmation that all monitoring to show compliance was conducted within the reporting period.(B) For pressure relief devices in organic HAP gas or vapor service subject to § 63.1434(c)(2), report any instrument reading of 500 ppm above background or greater, more than 5 calendar days after the pressure release.(C) For pressure relief devices in organic HAP service subject to § 63.1434(c)(3), report each pressure release to the atmosphere, including the following information:(1) The source, nature, and cause of the pressure release.(2) The start date, start time, and duration in minutes of the pressure release.(3) The quantity of total HAP emitted during the pressure release and the method used for determining this quantity.(4) The actions taken to prevent this pressure release.(5) The measures adopted to prevent future such pressure releases.(x) The information specified in § 63.108(l)(2) according to § 63.1436(b).
-
(b) Unless the Administrator has approved a different schedule under § 63.10(a), you must submit each compliance report required in paragraph (a) of this section according to the applicable requirements in paragraphs (b)(1) through (5) of this section following the procedures in § 63.9(k).(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.1443 and ending on June 30 or December 31, whichever date comes first after the compliance date that is specified for your source in § 63.1443.(2) The first compliance report must be delivered no later than July 31 or January 31, whichever date comes first after your first compliance report is due.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be delivered no later than July 31 or January 31, whichever date comes first after the end of the semiannual reporting period.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 71, and if the delegated authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the delegated authority has established instead of according to the dates in paragraphs (b)(1) through (4) of this section.
-
(c) The owner or operator of a source subject to this subpart shall submit Periodic Reports. On and after July 15, 2027 or once the reporting template for this subpart has been available on the CEDRI website for 1 year, whichever date is later, owners and operators must submit all subsequent reports following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Hazardous Organic Chemical Manufacturing Sector Lead. Owners and operators must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports under § 63.9(i) and § 63.10(a), the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted.(1) Except as specified under paragraphs (c)(5) and (c)(6) of this section, a report containing the information in paragraphs (c)(2), (c)(3), (c)(4), and (c)(7) of this section shall be submitted semiannually no later than 60 calendar days after the end of each 6-month period. The first report shall be submitted no later than 8 months after the date the Notification of Compliance Status is due and shall cover the 6-month period beginning on the date the Notification of Compliance Status is due. All periodic reports must contain the company name and address (including county), as well as the beginning and ending dates of the reporting period.(2) Except as provided in paragraph (c)(2)(iv) of this section, for an owner or operator of a source complying with the provisions of §§ 63.113 through 63.147 for any emission points, Periodic Reports shall include all information specified in §§ 63.117 and 63.118 for process vents, § 63.122 for storage vessels, §§ 63.129 and 63.130 for transfer operations, and § 63.146 for process wastewater, including reports of each excursion (i.e., each period when a monitored parameter is outside the established range and periods of insufficient monitoring data) using the procedures described in paragraphs (c)(2)(i) through (c)(2)(iv) of this section.(i) Report the affected sources or equipment, the monitored parameter that was exceeded and the date of each excursion.(ii) The parameter monitoring data for Group 1 emission points and emission points included in emissions averages that are required to perform continuous monitoring shall be used to determine compliance with the required operating conditions for the monitored control devices or recovery devices. For each excursion as specified in paragraphs (c)(2)(ii)(A) through (c)(2)(ii)(E) of this section, or paragraph (g)(2)(iv) of this section, except for excused excursions described therein, the owner or operator shall be deemed to have failed to have applied the control in a manner that achieves the required operating conditions and must report the information specified in paragraph (c)(2)(ii)(F) of this section.(A) An excursion means any of the three cases listed in paragraph (c)(2)(ii)(A)(1), (c)(2)(ii)(A)(2), or (c)(2)(ii)(A)(3) of this section. For a control device or recovery device where multiple parameters are monitored, if one or more of the parameters meets the excursion criteria in paragraph (c)(2)(ii)(A)(1), (c)(2)(ii)(A)(2), or (c)(2)(ii)(A)(3) of this section, this is considered a single excursion for the control device or recovery device.(1) When the daily average value of one or more monitored parameters is outside the permitted range.(2) When the period of control device or recovery device operation is 4 hours or greater in an operating day and monitoring data are insufficient to constitute a valid hour of data for at least 75 percent of the operating hours.(3) When the period of control device or recovery device operation is less than 4 hours in an operating day and more than one of the hours during the period of operation does not constitute a valid hour of data due to insufficient monitoring data.(4) Monitoring data are insufficient to constitute a valid hour of data, as used in paragraphs (c)(2)(ii)(A)(2) and (c)(2)(ii)(A)(3) of this section, if measured values are unavailable for any of the 15-minute periods within the hour. For data compression systems approved under § 63.151(g)(4), monitoring data are insufficient to calculate a valid hour of data if there are less than 4 data values recorded during the hour.(B) The number of excused excursions for each control device or recovery device for each semiannual period is specified in paragraphs (c)(2)(ii)(B)(1) through (c)(2)(ii)(B)(6) of this section. This paragraph applies to sources required to submit Periodic Reports semiannually or quarterly. The first semiannual period is the 6-month period starting the date the Notification of Compliance Status is due.(1) For the first semiannual period—six excused excursions.(2) For the second semiannual period—five excused excursions.(3) For the third semiannual period—four excused excursions.(4) For the fourth semiannual period—three excused excursions.(5) For the fifth semiannual period—two excused excursions.(6) For the sixth and all subsequent semiannual periods—one excused excursion.(C) A monitored parameter that is outside its established range or monitoring data that are not collected are excursions. However, if the conditions in paragraph (c)(2)(ii)(C)(1) or (c)(2)(ii)(C)(2) of this section are met, these excursions are not violations and do not count toward the number of excused excursions for determining compliance.(1) Periods of startup, shutdown, or malfunction. During periods of startup, shutdown, or malfunction when the source is operated during such periods in accordance with § 63.102(a)(4). For each source as defined in § 63.101, on and after July 15, 2027, this paragraph no longer applies.(2) Periods of nonoperation. During periods of nonoperation of the chemical manufacturing process unit, or portion thereof, that results in cessation of the emissions to which the monitoring applies.(D) Nothing in paragraph (c)(2)(ii) of this section shall be construed to allow or excuse a monitoring parameter excursion caused by any activity that violates other applicable provisions of subpart A, F, or G of this part.(E) Paragraph (c)(2)(ii) of this section, except paragraph (c)(2)(ii)(C) of this section, shall apply only to emission points and control devices or recovery devices for which continuous monitoring is required by §§ 63.113 through 63.150.(F) For each source as defined in § 63.101, beginning no later than the compliance dates specified in § 63.100(k)(10), for each excursion that is not an excused excursion, the report must include a list of the affected sources or equipment, the monitored parameter for which there was an excursion, the date of the excursion, an estimate of the quantity in pounds of each regulated pollutant emitted over any emission limit, a description of the method used to estimate the emissions, the cause of the excursion (including unknown cause, if applicable), as applicable, and the corrective action taken.(iii) Periodic Reports shall include the daily average values of monitored parameters for both excused and unexcused excursions, as defined in paragraph (c)(2)(ii)(A) of this section. For excursions caused by lack of monitoring data, the affected equipment or source, the monitored parameter, the start date and duration in hours of periods when monitoring data were not collected shall be specified.(iv) The provisions of paragraphs (c)(2) of this section, and (c)(2)(i) through (iii) of this section, do not apply to any storage vessel for which the owner or operator is not required, by the applicable monitoring plan established under § 63.120(d)(2), to keep continuous records. If continuous records are required, the owner or operator shall specify, in the monitoring plan, whether the provisions of paragraphs (c)(2) of this section, and (c)(2)(i) through (iii) of this section apply.(3) Except as specified in paragraph (c)(3)(iii) of this section, if any performance tests are reported in a Periodic Report, the following information shall be included:(i) One complete test report shall be submitted for each test method used for a particular kind of emission point tested. A complete test report shall contain the information specified in paragraph (b)(1)(ii) of this section.(ii) For additional tests performed for the same kind of emission point using the same method, results and any other information required in § 63.117 for process vents, § 63.129 for transfer, and § 63.146 for process wastewater shall be submitted, but a complete test report is not required.(iii) If the performance test report is submitted electronically through the EPA's CEDRI in accordance with paragraph (h) of this section, the process unit(s) tested, the pollutant(s) tested, and the date that such performance test was conducted may be submitted in the Periodic Report in lieu of the performance test results. The performance test results must be submitted to CEDRI by the date the Periodic Report is submitted.(4) Periodic Reports shall include the information in paragraphs (c)(4)(i) through (iv) of this section, as applicable:(iii) Notification if any Group 2 emission point becomes a Group 1 emission point, including a compliance schedule as required in § 63.100, and(iv) For gas streams sent for disposal pursuant to § 63.113(i) or for process wastewater streams sent for treatment pursuant to § 63.132(g), reports of changes in the identity of the transferee.(5) The owner or operator of a source shall submit quarterly reports for all emission points included in an emissions average.(i) The quarterly reports shall be submitted no later than 60 calendar days after the end of each quarter. The first report shall be submitted with the Notification of Compliance Status no later than 5 months after the compliance date specified in § 63.100.(ii) The quarterly reports shall include the information specified in this paragraph for all emission points included in an emissions average.(A) The credits and debits calculated each month during the quarter;(B) A demonstration that debits calculated for the quarter are not more than 1.30 times the credits calculated for the quarter, as required under § 63.150(e)(4).(C) The values of any inputs to the credit and debit equations in § 63.150(g) and (h) that change from month to month during the quarter or that have changed since the previous quarter;(D) Results of any performance tests conducted during the reporting period including one complete report for each test method used for a particular kind of emission point as described in paragraph (c)(3) of this section. If the performance test report is submitted electronically through the EPA's CEDRI in accordance with paragraph (h) of this section, the process unit(s) tested, the pollutant(s) tested, and the date that such performance test was conducted may be submitted in the Periodic Report in lieu of the performance test results. The performance test results must be submitted to CEDRI by the date the Periodic Report is submitted.;(E) Reports of daily average values of monitored parameters for both excused and unexcused excursions as defined in paragraph (c)(2)(ii)(A) of this section. For excursions caused by lack of monitoring data, the duration of periods when monitoring data were not collected shall be specified. Include the affected sources or equipment, monitored parameter, and the date for each excursion.(iii) Paragraphs (c)(2)(i) through (iii) of this section shall govern the use of monitoring data to determine compliance for Group 1 and Group 2 points included in emissions averages. For storage vessels to which the provisions of paragraphs (c)(2)(i) through (iii) of this section do not apply (as specified in paragraph (c)(2)(iv) of this section), the owner or operator is required to comply with the provisions of the applicable monitoring plan, and monitoring records may be used to determine compliance.(iv) Every fourth quarterly report shall include the following:(A) A demonstration that annual credits are greater than or equal to annual debits as required by § 63.150(e)(3); and(B) A certification of compliance with all the emissions averaging provisions in § 63.150.(6) The owner or operator of a source shall submit reports quarterly for particular emission points not included in an emissions average under the circumstances described in paragraphs (c)(6)(i) through (v) of this section.(i) The owner or operator of a source subject to this subpart shall submit quarterly reports for a period of one year for an emission point that is not included in an emissions average if:(A) The emission point has more excursions, as defined in paragraph (c)(2)(ii) of this section, than the number of excused excursions allowed under paragraph (c)(2)(ii)(B) of this section for a semiannual reporting period; and(ii) The quarterly reports shall include all information in paragraphs (c)(2), (3), and (4) of this section applicable to the emission point(s) for which quarterly reporting is required under paragraph (c)(6)(i) of this section. Information applicable to other emission points within the source shall be submitted in the semiannual reports required under paragraph (c)(1) of this section.(iii) Quarterly reports shall be submitted no later than 60 calendar days after the end of each quarter.(iv) After quarterly reports have been submitted for an emission point for one year, the owner or operator may return to semiannual reporting for the emission point unless the Administrator requests the owner or operator to continue to submit quarterly reports.(v) Paragraphs (c)(2)(i) through (iii) of this section shall govern the use of monitoring data to determine compliance for Group 1 emission points. For storage vessels to which the provisions of paragraphs (c)(2)(i) through (iii) of this section do not apply (as specified in paragraph (c)(2)(iv) of this section), the owner or operator is required to comply with the provisions of the applicable monitoring plan, and monitoring records may be used to determine compliance.(7) The information specified in § 63.108(l)(2) of subpart F of this part.
-
(d) The owner or operator of a source subject to this subpart shall submit Periodic Reports. On and after July 15, 2027 or once the reporting template for this subpart has been available on the CEDRI website for 1 year, whichever date is later, owners and operators must submit all subsequent reports following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Hazardous Organic Chemical Manufacturing Sector Lead. Owners and operators must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports under § 63.9(i) and § 63.10(a), the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. All Periodic Reports must include the following general information: company name, address (including county), and beginning and ending dates of the reporting period.(1) A report containing the information in paragraphs (d)(2), (d)(3), and (d)(4) of this section shall be submitted semiannually starting 6 months after the Notification of Compliance Status, as required in paragraph (c) of this section. The first periodic report shall cover the first 6 months after the compliance date specified in § 63.100(k)(3) of subpart F. Each subsequent periodic report shall cover the 6 month period following the preceding period.(2) For each process unit complying with the provisions of § 63.163 through § 63.174, the summary information listed in paragraphs (d)(2)(i) through (xix) of this paragraph for each monitoring period during the 6-month period.(i) The number of valves for which leaks were detected as described in § 63.168(b) of this subpart, the percent leakers, and the total number of valves monitored;(ii) The number of valves for which leaks were not repaired as required in § 63.168(f) of this subpart, identifying the number of those that are determined nonrepairable;(iii) The number of pumps for which leaks were detected as described in § 63.163(b) of this subpart, the percent leakers, and the total number of pumps monitored;(iv) The number of pumps for which leaks were not repaired as required in § 63.163(c) of this subpart;(v) The number of compressors for which leaks were detected as described in § 63.164(f) of this subpart;(vi) The number of compressors for which leaks were not repaired as required in § 63.164(g) of this subpart;(vii) The number of agitators for which leaks were detected as described in § 63.173(a) and (b) of this subpart;(viii) The number of agitators for which leaks were not repaired as required in § 63.173(c) of this subpart;(ix) The number of connectors for which leaks were detected as described in § 63.174(a) of this subpart, the percent of connectors leaking, and the total number of connectors monitored;(x) [Reserved](xi) The number of connectors for which leaks were not repaired as required in § 63.174(d) of this subpart, identifying the number of those that are determined nonrepairable;(xii) [Reserved](xiii) The facts that explain any delay of repairs and, where appropriate, why a process unit shutdown was technically infeasible.(xiv) The results of all monitoring to show compliance with §§ 63.164(i), 63.165(a), and 63.172(f) of this subpart conducted within the semiannual reporting period.(xv) If applicable, the initiation of a monthly monitoring program under § 63.168(d)(1)(i) of this subpart, or a quality improvement program under either §§ 63.175 or 63.176 of this subpart.(xvi) If applicable, notification of a change in connector monitoring alternatives as described in § 63.174(c)(1) of this subpart.(xvii) If applicable, the compliance option that has been selected under § 63.172(n).(xviii) Compliance reports for pressure relief devices subject to the requirements § 63.165(e) must include the information specified in paragraphs (d)(2)(xviii)(A) through (C) of this section.(A) For pressure relief devices in organic HAP gas or vapor service, pursuant to § 63.165(e)(1), report the instrument readings and dates for all readings of 500 ppm or greater.(B) For pressure relief devices in organic HAP gas or vapor service subject to § 63.165(e)(2), report the instrument readings and dates of instrument monitoring conducted.(C) For pressure relief devices in organic HAP service subject to § 63.165(e)(3), report each pressure release to the atmosphere, including pressure relief device identification name or number, the start date, start time, and duration (in minutes) of the pressure release; an estimate of the mass quantity in pounds of each organic HAP released; the results of any root cause analysis and corrective action analysis completed during the reporting period, including the corrective actions implemented during the reporting period; and, if applicable, the implementation schedule for planned corrective actions to be implemented subsequent to the reporting period.(xix) For each source as defined in § 63.101, and for each source as defined in § 63.191, beginning no later than the compliance dates specified in § 63.100(k)(10), the owner or operator must comply with this paragraph in addition to the requirements in paragraphs (d)(2)(i) through (d)(2)(xviii) of this section. For bypass lines subject to the requirements in § 63.172(j), the Periodic Report must include the start date, start time, duration in hours, estimate of the volume of gas in standard cubic feet, the concentration of organic HAP in the gas in parts per million by volume and the resulting mass emissions of organic HAP in pounds that bypass a control device. For periods when the flow indicator is not operating, report the start date, start time, and duration in hours.(3) For owners or operators electing to meet the requirements of § 63.178(b) of this subpart, the report shall include the information listed in paragraphs (i) through (v) of this paragraph for each process unit.(i) Batch product process equipment train identification;(ii) The number of pressure tests conducted;(iii) The number of pressure tests where the equipment train failed the pressure test;(iv) The facts that explain any delay of repairs; and(v) The results of all monitoring to determine compliance with § 63.172(f) of this subpart.(4) The information listed in paragraph (c) of this section for the Notification of Compliance Status for process units with later compliance dates. Any revisions to items reported in earlier Notification of Compliance Status, if the method of compliance has changed since the last report.
-
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report according to the schedule in Table 5 to this subpart and according to paragraphs (b)(1) through (5) of this section.(1) The first compliance report must include the information specified in paragraph (c) of this section. If you are demonstrating compliance with an emission limitation using a 12-month calculation period (e.g., the Average Option), then the first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.2133 and ending on either June 30 or December 31 (use whichever date is the first date following the end of the first 12 calendar months after the compliance date that is specified for your affected source in § 63.2133). If you are demonstrating compliance with an emission limitation using the Batch Option, then the first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.2133 and ending on either June 30 or December 31 (use whichever date is the first date following the compliance date that is specified for your affected source in § 63.2133).(2) The first compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date follows the end of the first compliance reporting period specified in paragraph (b)(1) of this section.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31. Each subsequent compliance report must include the information specified in paragraph (c) of this section.(4) Each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) through (4) of this section.
-
(b) Unless the EPA Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the date in table 9 to this subpart and as specified in paragraphs (b)(1) through (6) of this section.(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.2233 ending on June 30 or December 31, and lasting at least 6 months, but less than 12 months. For example, if your compliance date is March 1, then the first semiannual reporting period would begin on March 1 and end on December 31.(2) The first compliance report must be postmarked or delivered no later than July 31 or January 31 for compliance periods ending on June 30 and December 31, respectively.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31 for the semiannual reporting period ending on June 30 and December 31, respectively.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to § 70.6(a)(3)(iii)(A) or § 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) through (4) of this section.(6) Submit all reports following the procedure specified in § 63.9(k) except the CBI should be submitted according to paragraph (k) of this section.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report according to Table 11 to this subpart and by the dates shown in paragraphs (b)(1) through (3) of this section, by the dates shown in subpart SS of this part, and by the dates shown in Table 12 to this subpart, whichever are applicable.(i) The first Compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.2342 and ending on June 30 or December 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for your affected source in § 63.2342.(ii) The first Compliance report must be postmarked no later than July 31 or January 31, whichever date follows the end of the first calendar half after the compliance date that is specified for your affected source in § 63.2342.(i) Each subsequent Compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(ii) Each subsequent Compliance report must be postmarked no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(3) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent Compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) and (2) of this section.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the date in table 11 to this subpart and according to paragraphs (b)(1) through (5) of this section.(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.2445 and ending on June 30 or December 31, whichever date is the first date following the end of the first 6 months after the compliance date that is specified for your affected source in § 63.2445.(2) The first compliance report must be postmarked or delivered no later than August 31 or February 28, whichever date is the first date following the end of the first reporting period specified in paragraph (b)(1) of this section.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be postmarked or delivered no later than August 31 or February 28, whichever date is the first date following the end of the semiannual reporting period.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) through (4) of this section.
-
(1) Unless the Administrator has agreed to a different schedule for submitting reports under § 63.10(a), you must deliver or postmark each semiannual compliance report no later than 30 days following the end of each semiannual reporting period. The first semiannual reporting period begins on the compliance date for your affected source and ends on June 30 or December 31, whichever date immediately follows your compliance date. Each subsequent semiannual reporting period for which you must submit a semiannual compliance report begins on July 1 or January 1 and ends 6 calendar months later. Before March 1, 2019, as required by § 63.10(e)(3), you must begin submitting quarterly compliance reports if you deviate from the emission limits in § 63.2983 or the operating limits in § 63.2984. After February 28, 2019, you are not required to submit quarterly compliance reports. If you deviate from the emission limits in § 63.2983 or the operating limits in § 63.2984 in the quarter prior to February 28, 2019, you must include this information in the report for the first full semiannual reporting period following February 28, 2019.
-
(1) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must prepare and submit each semiannual compliance report according to the dates specified in paragraphs (a)(1)(i) through (iv) of this section.(i) The first semiannual compliance report must cover the first semiannual reporting period which begins the day after the end of the initial compliance period described in § 63.3160 that applies to your affected source and ends on June 30 or December 31, whichever occurs first following the end of the initial compliance period.(ii) Each subsequent semiannual compliance report must cover the subsequent semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(iii) Each semiannual compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(iv) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the date specified in paragraph (a)(1)(iii) of this section.
-
(1) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must prepare and submit each semiannual compliance report according to the dates specified in paragraphs (a)(1)(i) through (iv) of this section. Note that the information reported for each of the months in the reporting period will be based on the last 12 months of data prior to the date of each monthly calculation.(i) The first semiannual compliance report must cover the first semiannual reporting period which begins the day after the end of the initial compliance period described in § 63.3520, § 63.3530, § 63.3540, or § 63.3550 that applies to your affected source and ends on June 30 or December 31, whichever occurs first following the end of the initial compliance period.(ii) Each subsequent semiannual compliance report must cover the subsequent semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(iii) Each semiannual compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(iv) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of the date specified in paragraph (a)(1)(iii) of this section.
-
(a) The owner or operator of an affected source subject to the emissions standards in § 63.362 must fulfill all reporting requirements in § 63.10(a), (d), (e), and (f), according to the applicability in table 6 to this subpart. These reports will be made to the Administrator at the appropriate address identified in § 63.13 or submitted electronically.
-
(a) If you own or operate an affected source subject to § 63.362, you must comply with the recordkeeping requirements in § 63.10(a) through (c), according to the applicability in table 6 to this subpart, and in this section. All records required to be maintained by this subpart or a subpart referenced by this subpart shall be maintained in such a manner that they can be readily accessed and are suitable for inspection.
-
(1) Unless the Administrator has approved or agreed to a different schedule for submission of reports under § 63.10(a), you must prepare and submit each semiannual compliance report according to the dates specified in paragraphs (a)(1)(i) through (iv) of this section. Note that the information reported for each of the months in the reporting period will be based on the last 12 months of data prior to the date of each monthly calculation.(i) The first semiannual compliance report must cover the first semiannual reporting period which begins the day after the end of the initial compliance period described in § 63.3940, § 63.3950, or § 63.3960 that applies to your affected source and ends on June 30 or December 31, whichever date is the first date following the end of the initial compliance period.(ii) Each subsequent semiannual compliance report must cover the subsequent semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(iii) Each semiannual compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(iv) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the date specified in paragraph (a)(1)(iii) of this section.
-
(a) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must prepare and submit each semiannual compliance report according to the dates specified in paragraphs (a)(1) through (4) of this section.(1) The first semiannual compliance report must cover the first semiannual reporting period which begins the day after the end of the initial compliance period described in § 63.4140, § 63.4150, or § 63.4160 that applies to your affected source and ends on June 30 or December 31, whichever date is the first date following the end of the initial compliance period.(2) Each subsequent semiannual compliance report must cover the subsequent semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(3) Each semiannual compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(4) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent semiannual compliance reports according to the dates the permitting authority has established instead of the date specified in paragraph (a)(3) of this section.(5) Each affected source that has obtained a title V operating permit pursuant to 40 CFR part 70 or 40 CFR part 71 must report all deviations as defined in this subpart in the semiannual monitoring report required by 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A). If an affected source submits a semiannual compliance report pursuant to this section along with, or as part of, the semiannual monitoring report required by 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), and the semiannual compliance report includes all required information concerning deviations from any emission limitation in this subpart, its submission shall be deemed to satisfy any obligation to report the same deviations in the semiannual monitoring report. However, submission of a semiannual compliance report shall not otherwise affect any obligation the affected source may have to report deviations from permit requirements to the permitting authority.
-
(1) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must prepare and submit each semiannual compliance report according to the dates specified in paragraphs (a)(1)(i) through (iv) of this section.(i) The first semiannual compliance report must cover the first semiannual reporting period which begins the day after the end of the initial compliance period described in § 63.4320, § 63.4330, § 63.4340, or § 63.4350 that applies to your affected source and ends on June 30 or December 31, whichever date is the first date at least 6 months after the end of the initial compliance period.(ii) Each subsequent semiannual compliance report must cover the subsequent semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(iii) Each semiannual compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(iv) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the date specified in paragraph (a)(1)(iii) of this section.
-
(1) Unless the Administrator has approved or agreed to a different schedule for submission of reports under § 63.10(a), you must prepare and submit each semiannual compliance report according to the dates specified in paragraphs (a)(1)(i) through (iv) of this section. Note that the information reported for each of the months in the reporting period will be based on the last 12 months of data prior to the date of each monthly calculation.(i) The first semiannual compliance report must cover the first semiannual reporting period which begins the day after the end of the initial compliance period described in § 63.4540, § 63.4550, or § 63.4560 that applies to your affected source and ends on June 30 or December 31, whichever date is the first date following the end of the initial compliance period.(ii) Each subsequent semiannual compliance report must cover the subsequent semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(iii) Each semiannual compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(iv) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the date specified in paragraph (a)(1)(iii) of this section.
-
(1) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must prepare and submit each semiannual compliance report according to the dates specified in paragraphs (a)(1)(i) through (iv) of this section. Note that the information reported for each of the months in the reporting period will be based on the last 12 months of data prior to the date of each monthly calculation.(i) The first semiannual compliance report must cover the first semiannual reporting period which begins the day after the end of the initial compliance period described in § 63.4740, § 63.4750, or § 63.4760 that applies to your affected source and ends on June 30 or December 31, whichever occurs first following the end of the initial compliance period.(ii) Each subsequent semiannual compliance report must cover the subsequent semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(iii) Each semiannual compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(iv) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the date specified in paragraph (a)(1)(iii) of this section.
-
(1) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must prepare and submit each semiannual compliance report according to the dates specified in paragraphs (a)(1)(i) through (iv) of this section.(i) The first semiannual compliance report must cover the first semiannual reporting period which begins the day after the end of the initial compliance period described in § 63.4940, § 63.4950, or § 63.4960 that applies to your affected source and ends on June 30 or December 31, whichever occurs first following the end of the initial compliance period.(ii) Each subsequent semiannual compliance report must cover the subsequent semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(iii) Each semiannual compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(iv) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting 6-month monitoring reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent semiannual compliance reports according to the dates the permitting authority has established for the 40 CFR part 70 or 40 CFR part 71 6-month monitoring reports instead of according to the dates specified in paragraph (a)(1)(iii) of this section. However, under no circumstances shall the semiannual compliance report be submitted more than 30 days after the end of the semiannual reporting period established in paragraphs (a)(1)(i) and (ii) of this section.
-
(6) For existing and new affected sources, the owner or operator shall submit Periodic Reports as specified in paragraphs (e)(6)(i) through (xiii) of this section. In addition, for equipment leaks subject to § 63.502, the owner or operator shall submit the information specified in § 63.182(d) under the conditions listed in § 63.182(d) as part of the Periodic Report required by this paragraph (e)(6), and for heat exchange systems subject to § 63.502(n), the owner or operator shall submit the information specified in § 63.104(f)(2) as part of the Periodic Report required by this paragraph (e)(6). Section § 63.505 shall govern the use of monitoring data to determine compliance for Group 1 emission points and for Group 1 and Group 2 emission points included in emissions averages with the following exception: As discussed in § 63.484(k), for storage vessels to which the provisions of § 63.505 do not apply, as specified in the monitoring plan required by § 63.120(d)(2), the owner or operator is required to comply with the requirements set out in the monitoring plan, and monitoring records may be used to determine compliance. On and after July 15, 2027 or once the reporting template for this subpart has been available on the CEDRI website for 1 year, whichever date is later, owners and operators must submit all subsequent reports following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Polymers and Resins Sector Lead. Owners and operators must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports under § 63.9(i) and § 63.10(a), the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted.(i) Except as specified in paragraphs (e)(6)(xi) and (xii) of this section, a report containing the information in paragraph (e)(6)(ii) of this section or paragraphs (e)(6)(iii) through (x) and (xiii) of this section, as appropriate, shall be submitted semiannually no later than 60 days after the end of each 6-month period. The first report shall be submitted no later than 240 days after the date the Notification of Compliance Status is due and shall cover the 6-month period beginning on the date the Notification of Compliance Status is due. All periodic reports must contain the company name and address (including county), as well as the beginning and ending dates of the reporting period.(ii) If none of the compliance exceptions in paragraphs (e)(6)(iii) through (ix) or (xiii) of this section occurred during the 6-month period, the Periodic Report required by paragraph (e)(6)(i) of this section shall be a statement that there were no compliance exceptions as described in this paragraph for the 6-month period covered by that report and that none of the activities specified in paragraphs (e)(6)(iii) through (ix) or (xiii) of this section occurred during the 6-month period covered by that report.(iii) For an owner or operator of an affected source complying with the provisions of §§ 63.484 through 63.501 for any emission point, Periodic Reports shall include:(A) All information specified in § 63.122(a)(4) for storage vessels, §§ 63.117(a)(3) and 63.118(f) and 63.485(s)(5) for continuous front-end process vents, § 63.492 for batch front-end process vents and aggregate batch vent streams, § 63.499 for back-end process operations, § 63.104(f)(2) for heat exchange systems, and § 63.146(c) through (g) for process wastewater.(B) The daily average values or batch cycle daily average values of monitored parameters for all excursions, as defined in § 63.505(g) and (h). For excursions caused by lack of monitoring data, the start date and time and duration (in hours) of periods when monitoring data were not collected shall be specified.(C) For each affected source as described in § 63.480, beginning no later than the compliance dates specified in § 63.481(n), for each excursion that is not an excused excursion, the report must include the date of the excursion, a list of the affected sources or equipment, an estimate of the quantity in pounds of each regulated pollutant emitted over any emission limit, a description of the method used to estimate the emissions, the cause of the excursion (including unknown cause, if applicable), as applicable, and the corrective action taken.(D) (1) Any supplements to the Emissions Averaging Plan, as required in paragraph (e)(4)(iii) of this section;(2) Notification if a process change is made such that the group status of any emission point changes from Group 2 to Group 1. The owner or operator is not required to submit a notification of a process change if that process change caused the group status of an emission point to change from Group 1 to Group 2. However, until the owner or operator notifies the Administrator that the group status of an emission point has changed from Group 1 to Group 2, the owner or operator is required to continue to comply with the Group 1 requirements for that emission point. This notification may be submitted at any time.(3) Notification if one or more emission points (other than equipment leaks) or one or more EPPU is added to an affected source. The owner or operator shall submit the information contained in paragraphs (e)(6)(iii)(D)(3)(i) through (ii) of this section.(i) A description of the addition to the affected source; and(ii) Notification of the group status of the additional emission point or all emission points in the EPPU.(4) Notification if a standard operating procedure, as defined in § 63.500(a)(2), is changed and the change has the potential for increasing the concentration of carbon disulfide in the crumb dryer exhaust. This notification shall also include a summary of the test results of the carbon disulfide concentration resulting from the new standard operating procedure. The results of the performance test must be submitted according to paragraph (i) of this section by the date the Periodic Report is submitted.(5) For process wastewater streams sent for treatment pursuant to § 63.132(g), reports of changes in the identity of the treatment facility or transferee.(E) The start date, start time, duration in hours, and a brief description for each type of malfunction which occurred during the reporting period and which caused or may have caused any applicable emission limitation to be exceeded. The report must also include a description of actions taken by an owner or operator during a malfunction of an affected source to minimize emissions in accordance with § 63.483(a), including actions taken to correct a malfunction.(iv) For each batch front-end process vent with a batch mass input limitation, every second Periodic Report shall include the mass of HAP or material input to the batch unit operation during the 12-month period covered by the preceding and current Periodic Reports, and a statement of whether the batch front-end process vent was in or out of compliance with the batch mass input limitation.(v) Except as specified in paragraph (i) of this section, if any performance tests are reported in a Periodic Report, the following information shall be included:(A) One complete test report shall be submitted for each test method used for a particular kind of emission point tested. A complete test report shall contain the information specified in paragraph (e)(5)(i)(B) of this section.(B) For additional tests performed for the same kind of emission point using the same method, results and any other information, pertaining to the performance test, that is requested on a case-by-case basis by the Administrator shall be submitted, but a complete test report is not required.(vi) Notification of a change in the primary product of an EPPU, in accordance with the provisions in § 63.480(f). This includes a change in primary product from one elastomer product to either another elastomer product or to a non-elastomer product.(vii) The results for each change made to a predominant use determination made under § 63.480(g) for a storage vessel that is assigned to an affected source subject to this subpart after the change.(viii) The results for each change made to a predominant use determination made under § 63.480(h) for recovery operations equipment assigned to an affected source subject to this subpart after the change.(ix) An owner or operator complying with paragraph (h)(1) of this section shall notify the Administrator of the election to comply with paragraph (h)(1) of this section as part of the Periodic Report or as part of the Notification of Compliance Status as specified in paragraph (e)(5)(xi) of this section.(x) An owner or operator electing not to retain daily average or batch cycle daily average values under paragraph (h)(2) of this section shall notify the Administrator as specified in paragraph (h)(2)(i) of this section.(xi) The owner or operator of an affected source shall submit quarterly reports for all emission points included in an emissions average as specified in paragraphs (e)(6)(xi)(A) through (C) of this section.(A) The quarterly reports shall be submitted no later than 60 days after the end of each quarter. The first report shall be submitted with the Notification of Compliance Status no later than 150 days after the compliance date.(B) The quarterly reports shall include the information specified in paragraphs (e)(6)(xi)(B)(1) through (e)(6)(xi)(B)(7) of this section for all emission points included in an emissions average.(1) The credits and debits calculated each month during the quarter;(2) A demonstration that debits calculated for the quarter are not more than 1.30 times the credits calculated for the quarter, as required under § 63.503(e)(4);(3) The values of any inputs to the debit and credit equations in § 63.503(g) and (h) that change from month to month during the quarter or that have changed since the previous quarter;(4) Except as specified in paragraph (i) of this section, results of any performance tests conducted during the reporting period including one complete report for each test method used for a particular kind of emission point as described in paragraph (e)(6)(v) of this section. If the performance test was submitted to CEDRI, include the unit(s) tested, the pollutant(s) tested, and the date of the performance test(s) in the quarterly report. The performance test results must be submitted to CEDRI by the date the quarterly report is due;(5) Reports of daily average values or batch cycle daily averages of monitored parameters for excursions as defined in § 63.505(g) or (h) and the date of the excursion;(6) For excursions caused by lack of monitoring data, the start date and time and duration in hours of periods when monitoring data were not collected shall be specified; and(7) Any other information the affected source is required to report under the operating permit or Emissions Averaging Plan for the affected source.(C) Every fourth quarterly report shall include the following:(1) A demonstration that annual credits are greater than or equal to annual debits as required by § 63.503(e)(3); and(2) A certification of compliance with all the emissions averaging provisions in § 63.503.(xii) The owner or operator of an affected source shall submit quarterly reports for particular emission points and process sections not included in an emissions average as specified in paragraphs (e)(6)(xii)(A) through (D) of this section.(A) The owner or operator of an affected source shall submit quarterly reports for a period of 1 year for an emission point or process section that is not included in an emissions average if:(1) A control or recovery device for a particular emission point or process section has more excursions, as defined in § 63.505(g) or (h), than the number of excused excursions allowed under § 63.505(i) for a semiannual reporting period; or(2) The Administrator requests that the owner or operator submit quarterly reports for the emission point or process section.(B) The quarterly reports shall include all information specified in paragraphs (e)(6)(iii) through (ix) of this section, as applicable to the emission point or process section for which quarterly reporting is required under paragraph (e)(6)(xii)(A) of this section. Information applicable to other emission points within the affected source shall be submitted in the semiannual reports required under paragraph (e)(6)(i) of this section.(C) Quarterly reports shall be submitted no later than 60 days after the end of each quarter.(D) After quarterly reports have been submitted for an emission point for 1 year without more excursions occurring (during that year) than the number of excused excursions allowed under § 63.505(i), the owner or operator may return to semiannual reporting for the emission point or process section.(xiii) The information specified in § 63.108(l)(2).
-
(a) The owner or operator of any affected BLR source, as well as the owner or operator of any affected WSR source that is subject to the emission limit for process vents, storage tanks, and wastewater systems and/or is subject to the dioxins and furans emission limit for process vents, shall comply with the reporting requirements of applicable paragraphs of § 63.10, as specified in the General Provisions applicability table in this subpart. The owner or operator shall also submit to the Administrator, as part of the quarterly excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e)(3), the following recorded information. On and after July 15, 2027 or once the reporting template for this subpart has been available on the CEDRI website for 1 year, whichever date is later, owners and operators must submit all subsequent reports following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Polymers and Resins Sector Lead. Owners and operators must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports under § 63.9(i) and § 63.10(a), the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. If a report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirements in § 63.10(e)(3)(v), § 63.10(e)(3)(vi)(L), and § 63.10(e)(3)(vi)(M) to submit the date of the report and the name, title, and signature of the responsible official who is certifying the accuracy of the report.(1) Reports of monitoring data, including 15-minute monitoring values as well as daily average values or per-unit operation average values, as applicable, of monitored parameters for all operating days or unit operations when the average values were outside the ranges established in the Notification of Compliance Status or operating permit, including reports specified in paragraph (a)(4) of this section.(2) Reports of the duration of periods when monitoring data is not collected for each excursion caused by insufficient monitoring data, including reports specified in paragraph (a)(4) of this section. An excursion means any of the three cases listed in paragraph (a)(2)(i) or (a)(2)(ii) of this section. For a control device where multiple parameters are monitored, if one or more of the parameters meets the excursion criteria in paragraph (a)(2)(i) or (a)(2)(ii) of this section, this is considered a single excursion for the control device. In the report, include the identification of the source, start date, start time, duration in hours, and monitored parameter(s) meeting the excursion criteria.(i) When the period of control device operation is 4 hours or greater in an operating day and monitoring data are insufficient to constitute a valid hour of data, as defined in paragraph (a)(2)(iii) of this section, for at least 75 percent of the operating hours.(ii) When the period of control device operation is less than 4 hours in an operating day and more than one of the hours during the period of operation does not constitute a valid hour of data due to insufficient monitoring data.(iii) Monitoring data are insufficient to constitute a valid hour of data, as used in paragraphs (a)(2)(i) and (ii) of this section, if measured values are unavailable for any of the 15-minute periods within the hour.(3) Whenever a process change, as defined in § 63.115(e), is made that causes the emission rate from a de minimis emission point to become a process vent with an emission rate of one pound per year or greater, the owner or operator shall submit a report within 180 calendar days after the process change. The report may be submitted as part of the next summary report required under § 63.10(e)(3). The report shall include:(i) A description of the process change; and(4) For each existing, new, or reconstructed affected BLR and WSR source, beginning no later than the compliance dates specified in § 63.521(c), for each excursion that is not an excused excursion, the report must include a list of the affected sources or equipment, the monitored parameter, an estimate of the quantity in pounds of each regulated pollutant emitted over any emission limit, a description of the method used to estimate the emissions, the cause of the excursion (including unknown cause, if applicable), as applicable, and the corrective action taken. Include the start date, start time, and duration in hours of each excursion.(5) For pressure relief device subject to § 63.527(f), report each pressure release to the atmosphere, including pressure relief device identification name or number, the start date, start time, and duration (in minutes) of the pressure release; and an estimate of the mass quantity in pounds of each organic HAP released.(6) For heat exchangers subject to § 63.104 of subpart F of this part, the information specified in § 63.104(f)(2) of subpart F of this part.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the dates in paragraphs (b)(1) through (5) of this section.(1) If your source is not controlled by an add-on control device (i.e., you are complying with organic HAP content limits, application equipment requirements, or MACT model point value averaging provisions), the first compliance report must cover the period beginning 12 months after the compliance date specified for your source in § 63.5695 and ending on June 30 or December 31, whichever date is the first date following the end of the first 12-month period after the compliance date that is specified for your source in § 63.5695. If your source is controlled by an add-on control device, the first compliance report must cover the period beginning on the compliance date specified for your source in § 63.5695 and ending on June 30 or December 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for your source in § 63.5695.(2) The first compliance report must be postmarked or delivered no later than 60 calendar days after the end of the compliance reporting period specified in paragraph (b)(1) of this section.(3) Each subsequent compliance report must cover the applicable semiannual reporting period from January 1 through June 30 or from July 1 through December 31.(4) Each subsequent compliance report must be postmarked or delivered no later than 60 calendar days after the end of the semiannual reporting period.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) through (4) of this section.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the date specified in Table 14 to this subpart and according to paragraphs (b)(1) through (5) of this section.(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.5800 and ending on June 30 or December 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for your source in § 63.5800.(2) The first compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date follows the end of the first calendar half after the compliance date that is specified for your affected source in § 63.5800.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(5) For each affected source that is subject to permitting requirements pursuant to 40 CFR part 70 or 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to § 70.6 (a)(3)(iii)(A) or § 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) through (4) of this section.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the date in table 15 to this subpart and according to the requirements in paragraphs (b)(1) through (5) of this section.(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.5983 and ending on June 30 or December 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for your source in § 63.5983.(2) Before January 21, 2021, the first semiannual compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date follows the end of the first calendar half after the compliance date that is specified for your affected source in § 63.5983. After January 20, 2021, the first semiannual compliance report must be submitted electronically via CEDRI no later than July 31 or January 31, whichever date follows the end of the first calendar half after the compliance date that is specified for your affected source in § 63.5983.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Before January 21, 2021, each subsequent semiannual compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period. After January 20, 2021, each subsequent semiannual compliance report must be submitted electronically via CEDRI no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(5) For each affected source that is subject to permitting subparts pursuant to 40 CFR part 70 or 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) through (4) of this section.
-
(g) The owner or operator of a source subject to this subpart shall submit Periodic Reports no later than 60 days after the end of each 6-month period when any of the information specified in paragraphs (g)(1) through (7) of this section or paragraphs (g)(9) through (14) of this section is collected. The first 6-month period shall begin on the date the Notification of Compliance Status report is required to be submitted. A Periodic Report is not required if none of the events identified in paragraphs (g)(1) through (7) of this section or paragraphs (g)(9) through (14) of this section occurred during the 6-month period unless emissions averaging is utilized. Quarterly reports must be submitted for emission points included in emission averages, as provided in paragraph (g)(8) of this section. An owner or operator may submit reports required by other regulations in place of or as part of the Periodic Report required by this paragraph (g) if the reports contain the information required by paragraphs (g)(1) through (14) of this section. The Periodic Report must contain company identifier information (including the company name and address), the beginning and ending dates of the time period covered by the report, and the information specified in paragraphs (g)(1) through (14) of this section, and it must be submitted in accordance with § 63.10(a) of this part. On or after April 4, 2024, upon initial startup, or once the form has been available on the CEDRI website for six months, whichever date is later, owners or operators must submit all subsequent Periodic Reports in accordance with § 63.10(a) of this part except for the items in paragraphs (g)(10)(iv) and (11)(iv) of this section. The items in paragraphs (g)(10)(iv) and (11)(iv) of this section must be submitted using the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart and following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Refinery Sector lead. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports, the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted.(1) For storage vessels, Periodic Reports shall include the information specified for Periodic Reports in paragraphs (g)(2) through (5) of this section. Information related to gaskets, slotted membranes, and sleeve seals is not required for storage vessels that are part of an existing source complying with § 63.646.(i) An owner or operator who elects to comply with § 63.646 by using a fixed roof and an internal floating roof or by using an external floating roof converted to an internal floating roof shall submit the results of each inspection conducted in accordance with § 63.120(a) of subpart G in which a failure is detected in the control equipment.(A) For vessels for which annual inspections are required under § 63.120(a)(2)(i) or (a)(3)(ii) of subpart G, the specifications and requirements listed in paragraphs (g)(2)(i)(A)(1) through (3) of this section apply.(1) A failure is defined as any time in which the internal floating roof is not resting on the surface of the liquid inside the storage vessel and is not resting on the leg supports; or there is liquid on the floating roof; or the seal is detached from the internal floating roof; or there are holes, tears, or other openings in the seal or seal fabric; or there are visible gaps between the seal and the wall of the storage vessel.(2) Except as provided in paragraph (g)(2)(i)(A)(3) of this section, each Periodic Report shall include the date of the inspection, identification of each storage vessel in which a failure was detected, and a description of the failure. The Periodic Report shall also describe the nature of and date the repair was made or the date the storage vessel was emptied.(3) If an extension is utilized in accordance with § 63.120(a)(4) of subpart G, the owner or operator shall, in the next Periodic Report, identify the vessel; include the documentation specified in § 63.120(a)(4) of subpart G; and describe the date the storage vessel was emptied and the nature of and date the repair was made.(B) For vessels for which inspections are required under § 63.120(a)(2)(ii), (a)(3)(i), or (a)(3)(iii) of subpart G (i.e., internal inspections), the specifications and requirements listed in paragraphs (g)(2)(i)(B)(1) and (2) of this section apply.(1) A failure is defined as any time in which the internal floating roof has defects; or the primary seal has holes, tears, or other openings in the seal or the seal fabric; or the secondary seal (if one has been installed) has holes, tears, or other openings in the seal or the seal fabric; or, for a storage vessel that is part of a new source, the gaskets no longer close off the liquid surface from the atmosphere; or, for a storage vessel that is part of a new source, the slotted membrane has more than a 10 percent open area.(2) Each Periodic Report shall include the date of the inspection, identification of each storage vessel in which a failure was detected, and a description of the failure. The Periodic Report shall also describe the nature of and date the repair was made.(ii) An owner or operator who elects to comply with § 63.660 by using a fixed roof and an internal floating roof shall submit the results of each inspection conducted in accordance with § 63.1063(c)(1), (d)(1), and (d)(2) of subpart WW in which a failure is detected in the control equipment. For vessels for which inspections are required under § 63.1063(c) and (d), the specifications and requirements listed in paragraphs (g)(2)(ii)(A) through (C) of this section apply.(A) A failure is defined in § 63.1063(d)(1) of subpart WW.(B) Each Periodic Report shall include a copy of the inspection record required by § 63.1065(b) of subpart WW when a failure occurs.(C) An owner or operator who elects to use an extension in accordance with § 63.1063(e)(2) of subpart WW shall, in the next Periodic Report, submit the documentation required by § 63.1063(e)(2).(i) An owner or operator who elects to comply with § 63.646 by using an external floating roof shall meet the periodic reporting requirements specified in paragraphs (g)(3)(i)(A) through (C) of this section.(A) The owner or operator shall submit, as part of the Periodic Report, documentation of the results of each seal gap measurement made in accordance with § 63.120(b) of subpart G in which the seal and seal gap requirements of § 63.120(b)(3), (4), (5), or (6) of subpart G are not met. This documentation shall include the information specified in paragraphs (g)(3)(i)(A)(1) through (4) of this section.(1) The date of the seal gap measurement.(2) The raw data obtained in the seal gap measurement and the calculations described in § 63.120(b)(3) and (4) of subpart G.(3) A description of any seal condition specified in § 63.120(b)(5) or (6) of subpart G that is not met.(4) A description of the nature of and date the repair was made, or the date the storage vessel was emptied.(B) If an extension is utilized in accordance with § 63.120(b)(7)(ii) or (b)(8) of subpart G, the owner or operator shall, in the next Periodic Report, identify the vessel; include the documentation specified in § 63.120(b)(7)(ii) or (b)(8) of subpart G, as applicable; and describe the date the vessel was emptied and the nature of and date the repair was made.(C) The owner or operator shall submit, as part of the Periodic Report, documentation of any failures that are identified during visual inspections required by § 63.120(b)(10) of subpart G. This documentation shall meet the specifications and requirements in paragraphs (g)(3)(i)(C)(1) and (2) of this section.(1) A failure is defined as any time in which the external floating roof has defects; or the primary seal has holes or other openings in the seal or the seal fabric; or the secondary seal has holes, tears, or other openings in the seal or the seal fabric; or, for a storage vessel that is part of a new source, the gaskets no longer close off the liquid surface from the atmosphere; or, for a storage vessel that is part of a new source, the slotted membrane has more than 10 percent open area.(2) Each Periodic Report shall include the date of the inspection, identification of each storage vessel in which a failure was detected, and a description of the failure. The Periodic Report shall also describe the nature of and date the repair was made.(ii) An owner or operator who elects to comply with § 63.660 by using an external floating roof shall meet the periodic reporting requirements specified in paragraphs (g)(3)(ii)(A) and (B) of this section.(A) For vessels for which inspections are required under § 63.1063(c)(2), (d)(1), and (d)(3) of subpart WW, the owner or operator shall submit, as part of the Periodic Report, a copy of the inspection record required by § 63.1065(b) of subpart WW when a failure occurs. A failure is defined in § 63.1063(d)(1).(B) An owner or operator who elects to use an extension in accordance with § 63.1063(e)(2) or (c)(2)(iv)(B) of subpart WW shall, in the next Periodic Report, submit the documentation required by those paragraphs.(4) [Reserved](5) An owner or operator who elects to comply with § 63.646 or § 63.660 by installing a closed vent system and control device shall submit, as part of the next Periodic Report, the information specified in paragraphs (g)(5)(i) through (v) of this section, as applicable.(i) The Periodic Report shall include the information specified in paragraphs (g)(5)(i)(A) and (B) of this section for those planned routine maintenance operations that would require the control device not to meet the requirements of either § 63.119(e)(1) or (2) of subpart G, § 63.985(a) and (b) of subpart SS, or § 63.670, as applicable.(A) A description of the planned routine maintenance that is anticipated to be performed for the control device during the next 6 months. This description shall include the type of maintenance necessary, planned frequency of maintenance, and lengths of maintenance periods.(B) A description of the planned routine maintenance that was performed for the control device during the previous 6 months. This description shall include the type of maintenance performed and the total number of hours during those 6 months that the control device did not meet the requirements of either § 63.119(e)(1) or (2) of subpart G, § 63.985(a) and (b) of subpart SS, or § 63.670, as applicable, due to planned routine maintenance.(ii) If a control device other than a flare is used, the Periodic Report shall describe each occurrence when the monitored parameters were outside of the parameter ranges documented in the Notification of Compliance Status report. The description shall include: Identification of the control device for which the measured parameters were outside of the established ranges, and causes for the measured parameters to be outside of the established ranges.(iii) If a flare is used prior to January 30, 2019 and prior to electing to comply with the requirements in § 63.670, the Periodic Report shall describe each occurrence when the flare does not meet the general control device requirements specified in § 63.11(b) of subpart A and shall include: Identification of the flare that does not meet the general requirements specified in § 63.11(b) of subpart A, and reasons the flare did not meet the general requirements specified in § 63.11(b) of subpart A.(iv) If a flare is used on or after the date for which compliance with the requirements in § 63.670 is elected, which can be no later than January 30, 2019, the Periodic Report shall include the items specified in paragraph (g)(11) of this section.(v) An owner or operator who elects to comply with § 63.660 by installing an alternate control device as described in § 63.1064 of subpart WW shall submit, as part of the next Periodic Report, a written application as described in § 63.1066(b)(3) of subpart WW.(6) For miscellaneous process vents for which continuous parameter monitors are required by this subpart, periods of excess emissions shall be identified in the Periodic Reports and shall be used to determine compliance with the emission standards.(i) Period of excess emission means any of the following conditions:(A) An operating day when the daily average value of a monitored parameter, except presence of a flare pilot flame, is outside the range specified in the Notification of Compliance Status report. Monitoring data recorded during periods of monitoring system breakdown, repairs, calibration checks and zero (low-level) and high-level adjustments shall not be used in computing daily average values of monitored parameters.(C) An operating day when monitoring data required to be recorded in paragraphs (i)(3) (i) and (ii) of this section are available for less than 75 percent of the operating hours.(D) For data compression systems under paragraph (h)(5)(iii) of this section, an operating day when the monitor operated for less than 75 percent of the operating hours or a day when less than 18 monitoring values were recorded.(ii) For miscellaneous process vents, excess emissions shall be reported for the operating parameters specified in table 10 of this subpart unless other site-specific parameter(s) have been approved by the operating permit authority.(iii) For periods in closed vent systems when a Group 1 miscellaneous process vent stream was detected in the bypass line or diverted from the control device and either directly to the atmosphere or to a control device that does not comply with the requirements in § 63.643(a), report the date, time, duration, estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting mass emissions of organic HAP that bypassed the control device. For periods when the flow indicator is not operating, report the date, time, and duration.(7) If a performance test for determination of compliance for a new emission point subject to this subpart or for an emission point that has changed from Group 2 to Group 1 is conducted during the period covered by a Periodic Report, the results of the performance test shall be included in the Periodic Report.(i) Results of the performance test shall include the identification of the source tested, the date of the test, the percentage of emissions reduction or outlet pollutant concentration reduction (whichever is needed to determine compliance) for each run and for the average of all runs, and the values of the monitored operating parameters.(ii) The complete test report shall be maintained onsite.(8) The owner or operator of a source shall submit quarterly reports for all emission points included in an emissions average.(i) The quarterly reports shall be submitted no later than 60 calendar days after the end of each quarter. The first report shall be submitted with the Notification of Compliance Status report no later than 150 days after the compliance date specified in § 63.640.(ii) The quarterly reports shall include:(A) The information specified in this paragraph and in paragraphs (g)(2) through (g)(7) of this section for all storage vessels and miscellaneous process vents included in an emissions average;(B) The information required to be reported by § 63.428 (h)(1), (h)(2), and (h)(3) for each gasoline loading rack included in an emissions average, unless this information has already been submitted in a separate report;(C) The information required to be reported by § 63.567(e)(4) and (j)(3) of subpart Y for each marine tank vessel loading operation included in an emissions average, unless the information has already been submitted in a separate report;(D) Any information pertaining to each wastewater stream included in an emissions average that the source is required to report under the Implementation Plan for the source;(E) The credits and debits calculated each month during the quarter;(F) A demonstration that debits calculated for the quarter are not more than 1.30 times the credits calculated for the quarter, as required under §§ 63.652(e)(4);(G) The values of any inputs to the credit and debit equations in § 63.652 (g) and (h) that change from month to month during the quarter or that have changed since the previous quarter; and(iii) Every fourth quarterly report shall include the following:(A) A demonstration that annual credits are greater than or equal to annual debits as required by § 63.652(e)(3); and(B) A certification of compliance with all the emissions averaging provisions in § 63.652 of this subpart.(9) For heat exchange systems, Periodic Reports must include the following information:(i) The number of heat exchange systems at the plant site subject to the monitoring requirements in § 63.654.(iii) For each monitoring location where the total strippable hydrocarbon concentration was determined to be equal to or greater than the applicable leak definitions specified in § 63.654(c)(6), identification of the monitoring location (e.g., unique monitoring location or heat exchange system ID number), the measured total strippable hydrocarbon concentration, the date the leak was first identified, and, if applicable, the date the source of the leak was identified;(iv) For leaks that were repaired during the reporting period (including delayed repairs), identification of the monitoring location associated with the repaired leak, the total strippable hydrocarbon concentration measured during re-monitoring to verify repair, and the re-monitoring date (i.e., the effective date of repair); and(v) For each delayed repair, identification of the monitoring location associated with the leak for which repair is delayed, the date when the delay of repair began, the date the repair is expected to be completed (if the leak is not repaired during the reporting period), the total strippable hydrocarbon concentration and date of each monitoring event conducted on the delayed repair during the reporting period, and an estimate of the potential strippable hydrocarbon emissions over the reporting period associated with the delayed repair.(10) For pressure relief devices subject to the requirements § 63.648(j), Periodic Reports must include the information specified in paragraphs (g)(10)(i) through (iv) of this section. Owners or operators must submit the Periodic Report in accordance with § 63.10(a) of this part. On or after April 4, 2024 or once the report template for this subpart has been available on the CEDRI website for six months, whichever date is later, owners or operators must submit subsequent Periodic Reports in accordance with § 63.10(a) of this part except for the items in paragraph (iv) of this section. The items in paragraph (iv) of this section must be submitted using the appropriate electronic report template on the CEDRI website for this subpart and following the procedures specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Refinery Sector lead. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports, the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted.(i) For pressure relief devices in organic HAP gas or vapor service, pursuant to § 63.648(j)(1), report any instrument reading of 500 ppm or greater.(ii) For pressure relief devices in organic HAP gas or vapor service subject to § 63.648(j)(2), report confirmation that any monitoring required to be done during the reporting period to show compliance was conducted.(iii) For pilot-operated pressure relief devices in organic HAP service, report each pressure release to the atmosphere through the pilot vent that equals or exceeds 72 pounds of VOC per day, including duration of the pressure release through the pilot vent and estimate of the mass quantity of each organic HAP released.(iv) For each pressure release to the atmosphere during the reporting period from a pressure relief device in organic HAP service subject to § 63.648(j)(3), report the following information:(E) The results of any root cause analysis and corrective action analysis completed during the reporting period, including the corrective actions implemented during the reporting period and, if applicable, the implementation schedule for planned corrective actions to be implemented subsequent to the reporting period.(11) For flares subject to § 63.670, Periodic Reports must include the information specified in paragraphs (g)(11)(i) through (iv) of this section. Owners or operators must submit the Periodic Report in accordance with § 63.10(a) of this part. On or after April 4, 2024 or once the report template for this subpart has been available on the CEDRI website for six months, whichever date is later, owners or operators must submit subsequent Periodic Reports in accordance with § 63.10(a) of this part except for the items in paragraph (iv) of this section. The items in paragraph (iv) of this section must be submitted using the appropriate electronic report template on the CEDRI website and following the procedures specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Refinery Sector lead. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated State agency or other authority has approved a different schedule for submission of reports, the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted.(i) Records as specified in paragraph (i)(9)(i) of this section for each 15-minute block during which there was at least one minute when regulated material is routed to a flare and no pilot flame is present.(ii) Visible emission records as specified in paragraph (i)(9)(ii)(C) of this section for each period of 2 consecutive hours during which visible emissions exceeded a total of 5 minutes.(iii) The 15-minute block periods for which the applicable operating limits specified in § 63.670(d) through (f) are not met. Indicate the date and time for the period, the type of deviation (e.g., flare tip velocity, valve position for pressure-assisted flares, combustion zone net heating value, or net heating value dilution parameter) and the flare tip velocity, if applicable, and the net heating value operating parameter(s) determined following the methods in § 63.670(k) through (n) as applicable.(iv) An indication whether there were any flaring events meeting the criteria in § 63.670(o)(3) that occurred during the reporting period. If there were flaring events meeting the criteria in § 63.670(o)(3), report the following information for each such flaring event:(E) The periods of time that the flare tip velocity exceeds the maximum flare tip velocity determined using the methods in § 63.670(d)(2) and the maximum 15-minute block average flare tip velocity recorded during the event.(F) Results of the root cause and corrective actions analysis completed during the reporting period, including the corrective actions implemented during the reporting period and, if applicable, the implementation schedule for planned corrective actions to be implemented subsequent to the reporting period.(12) For delayed coking units, the Periodic Report must include the information specified in paragraphs (g)(12)(i) through (iv) of this section.(i) For existing source delayed coking units, any 60-cycle average exceeding the applicable limit in § 63.657(a)(1).(ii) For new source delayed coking units, any direct venting event exceeding the applicable limit in § 63.657(a)(2).(iv) For each double quenching draining event when the drain water temperature exceeded 210 °F, report the drum, date, time, the coke drum vessel pressure or temperature, as applicable, when pre-vent draining was initiated, and the maximum drain water temperature during the pre-vent draining period.(13) For maintenance vents subject to the requirements in § 63.643(c), Periodic Reports must include the information specified in paragraphs (g)(13)(i) through (iv) of this section for any release exceeding the applicable limits in § 63.643(c)(1). For the purposes of this reporting requirement, owners or operators complying with § 63.643(c)(1)(iv) must report each venting event for which the lower explosive limit is 20 percent or greater; owners or operators complying with § 63.643(c)(1)(v) must report each venting event conducted under those provisions and include an explanation for each event as to why utilization of this alternative was required.(iii) The lower explosive limit, vessel pressure, or mass of VOC in the equipment, as applicable, at the start of atmospheric venting. If the 5 psig vessel pressure option in § 63.643(c)(1)(ii) was used and active purging was initiated while the concentration of the vapors was 10 percent or greater of its LEL, also include the concentration of the vapors at the time active purging was initiated.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the date in Table 7 of this subpart and according to the requirements in paragraphs (b)(1) through (b)(9) of this section.(1) For semiannual Compliance reports, the first Compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.6595 and ending on June 30 or December 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for your source in § 63.6595.(2) For semiannual Compliance reports, the first Compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date follows the end of the first calendar half after the compliance date that is specified for your affected source in § 63.6595.(3) For semiannual Compliance reports, each subsequent Compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) For semiannual Compliance reports, each subsequent Compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(5) For each stationary RICE that is subject to permitting regulations pursuant to 40 CFR part 70 or 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6 (a)(3)(iii)(A), you may submit the first and subsequent Compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) through (b)(4) of this section.(6) For annual Compliance reports, the first Compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.6595 and ending on December 31.(7) For annual Compliance reports, the first Compliance report must be postmarked or delivered no later than January 31 following the end of the first calendar year after the compliance date that is specified for your affected source in § 63.6595.(8) For annual Compliance reports, each subsequent Compliance report must cover the annual reporting period from January 1 through December 31.(9) For annual Compliance reports, each subsequent Compliance report must be postmarked or delivered no later than January 31.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the date specified in Table 8 to this subpart and according to the requirements in paragraphs (b)(1) through (6) of this section:(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.7083 and ending on June 30 or December 31, whichever date is the first date following the end of the first half calendar year after the compliance date that is specified for your source in § 63.7083.(2) The first compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date follows the end of the first half calendar year after the compliance date that is specified for your affected source in § 63.7083.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(5) For each affected source that is subject to permitting regulations pursuant to part 70 or part 71 of this chapter, if the permitting authority has established dates for submitting semiannual reports pursuant to §§ 70.6(a)(3)(iii)(A) or 71.6(a)(3)(iii)(A) of this chapter, you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates specified in paragraphs (b)(1) through (4) of this section.(6) Beginning on the relevant compliance date for your source as specified in § 63.7083(g), submit all subsequent compliance reports following the procedure specified in paragraph (h) of this section.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the date according to paragraphs (b)(1) through (5) of this section.(1) The first periodic compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.7183 and ending on June 30 or December 31, whichever date is the first date following the end of the first 12 calendar months after the compliance date that is specified for your source in § 63.7183.(2) The first periodic compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date follows the end of the first 12 calendar months after the compliance date that is specified for your affected source in § 63.7183.(3) Each subsequent periodic compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent periodic compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent periodic compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) through (4) of this section.
-
(a) . Each owner or operator of a source subject to this subpart shall fulfill all recordkeeping requirements specified in § 63.10(a), (b), (d), and (f), except § 63.10(b)(2)(i), (iv) and (v). Each owner or operator must also record and maintain according to § 63.10(b)(1) the information specified in paragraph (a)(1) through (3) of this section.(1) In the event that an affected unit fails to meet an applicable standard, record the number of failures. For each failure record the date, time, and duration of each failure.(2) For each failure to meet an applicable standard, record and retain a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(3) Record actions taken to minimize emissions in accordance with § 63.743(e), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(1) Except as provided in paragraphs (a)(2) through (5) of this section, each owner or operator subject to this subpart shall fulfill the requirements contained in § 63.9(a) through (e) and (h) through (j), Notification requirements, and § 63.10(a), (b), (d), and (f), Recordkeeping and reporting requirements, of the General Provisions, 40 CFR part 63, subpart A, and that the initial notification for existing sources required in § 63.9(b)(2) shall be submitted not later than September 1, 1997, or as specified in § 63.9(b)(2). In addition to the requirements of § 63.9(h), the notification of compliance status shall include:(i) Information detailing whether the source has operated within the specified ranges of its designated operating parameters.(ii) For each coating line, where averaging will be used along with the types of quantities of coatings the facility expects to use in the first year of operation. Averaging scheme shall be approved by the Administrator or delegated State authority and shall be included as part of the facility's title V or part 70 permit.
-
(b) Unless the EPA Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report, according to paragraph (h) of this section, by the date in Table 9 to this subpart and according to the requirements in paragraphs (b)(1) through (4) of this section. For units that are subject only to a requirement to conduct subsequent annual, biennial, or 5-year tune-up according to § 63.7540(a)(10), (11), or (12), respectively, and not subject to emission limits or Table 4 operating limits, you may submit only an annual, biennial, or 5-year compliance report, as applicable, as specified in paragraphs (b)(1) through (4) of this section, instead of a semi-annual compliance report.(1) The first semi-annual compliance report must cover the period beginning on the compliance date that is specified for each boiler or process heater in § 63.7495 and ending on June 30 or December 31, whichever date is the first date that occurs at least 180 days after the compliance date that is specified for your source in § 63.7495. If submitting an annual, biennial, or 5-year compliance report, the first compliance report must cover the period beginning on the compliance date that is specified for each boiler or process heater in § 63.7495 and ending on December 31 within 1, 2, or 5 years, as applicable, after the compliance date that is specified for your source in § 63.7495.(2) The first semi-annual compliance report must be postmarked or submitted no later than July 31 or January 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for each boiler or process heater in § 63.7495. The first annual, biennial, or 5-year compliance report must be postmarked or submitted no later than January 31.(3) Each subsequent semi-annual compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31. Annual, biennial, and 5-year compliance reports must cover the applicable 1-, 2-, or 5-year periods from January 1 to December 31.(4) Each subsequent semi-annual compliance report must be postmarked or submitted no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period. Annual, biennial, and 5-year compliance reports must be postmarked or submitted no later than January 31.(5) For each affected source that is subject to permitting regulations pursuant to part 70 or part 71 of this chapter, and if the permitting authority has established dates for submitting semiannual reports pursuant to 70.6(a)(3)(iii)(A) or 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established in the permit instead of according to the dates in paragraphs (b)(1) through (4) of this section.
-
(12) For existing sources and for new or reconstructed sources which commenced construction or reconstruction on or before August 16, 2019, before January 11, 2021, for each startup, shutdown, or malfunction during the reporting period that is not consistent with your startup, shutdown, and malfunction plan you must submit an immediate startup, shutdown and malfunction report. Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report according to paragraphs (f)(1) and (2) of this section. An immediate startup, shutdown, and malfunction report is not required after January 11, 2021.
-
(a) Each owner or operator of an affected source shall comply with the applicable recordkeeping and reporting requirements in § 63.10 (a), (b), (d), and (f). Any owner that receives approval pursuant to § 63.783(c) to use an add-on control system to control coating emissions shall also comply with the applicable requirements of § 63.10 (c) and (e). A summary of recordkeeping and reporting requirements is provided in Table 3 of this subpart.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report as specified in Table 9 to this subpart and paragraphs (b)(1) and (2) of this section.(1) The compliance reports must be submitted semiannually. The first report must be submitted no later than 240 days after the applicable compliance date and shall cover the 6-month period beginning on the compliance date. Each subsequent compliance report must cover the 6-month period following the preceding period.(2) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in Table 9.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the date in Table 9 to this subpart and as specified in paragraphs (b)(1) through (5) of this section.(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.8395 and ending on either June 30 or December 31. The first reporting period must be at least 6 months, but less than 12 months. For example, if your compliance date is March 1, then the first semiannual reporting period would begin on March 1 and end on December 31.(2) The first compliance report must be postmarked or delivered no later than July 31 or January 31 for compliance periods ending on June 30 and December 31, respectively.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31 for compliance periods ending on June 30 and December 31, respectively.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of the dates in paragraphs (b)(1) through (4) of this section.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the date in Table 10 to this subpart and as specified in paragraphs (b)(1) through (5) of this section.(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.8545 and ending on either June 30 or December 31. This reporting period must be at least 6 months, but less than 12 months. For example, if your compliance date is March 1, then the first semiannual reporting period would begin on March 1 and end on December 31.(2) The first compliance report must be postmarked or delivered no later than July 31 or January 31 for compliance periods ending on June 30 and December 31, respectively.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31 for compliance periods ending on June 30 and December 31, respectively.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of the dates in paragraphs (b)(1) through (4) of this section.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the date in Table 6 to this subpart and according to the following dates:(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.8683 and ending on June 30 or December 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for your source in § 63.8683.(2) The first compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date follows the end of the first calendar half after the compliance date that is specified for your affected source in § 63.8683.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of the dates in paragraphs (b)(1) through (4) of this section.(6) On and after September 9, 2020, you must submit all compliance reports to EPA via the CEDRI, which can be accessed through EPA's CDX (https://cdx.epa.gov/). You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/compliance-and-emissions-data-reporting-interface-cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. If you claim some of the information required to be submitted via CEDRI is CBI, submit a complete report, including information claimed to be CBI, to EPA. The report must be generated using the appropriate form on the CEDRI website or an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website. Submit the file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Group Leader, Measurement Policy Group, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to EPA via EPA's CDX as described earlier in this paragraph (b)(6). You may assert a claim of EPA system outage or force majeure for failure to timely comply with the reporting requirement in this paragraph (b)(6) provided you meet the requirements outlined in § 63.8693(h) or (i), as applicable.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each compliance report for flame lamination affected sources semiannually according to paragraphs (b)(1) through (4) of this section.(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.8786 and ending on June 30 or December 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for your source in § 63.8786.(2) The first compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date follows the end of the first calendar half after the compliance date that is specified for your affected source in § 63.8786.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report according to paragraphs (b)(1) through (5) of this section.(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.8995 and ending on June 30 or December 31, whichever date is the first date following the end of the first calendar half after the compliance date that is specified for your source in § 63.8995 (i.e., June 30, 2006, for sources existing on April 17, 2006).(2) The first compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date follows the end of the first calendar half after the compliance date that is specified for your affected source in § 63.8995 (i.e., July 31, 2006, for sources existing on April 17, 2006).(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date is the first date following the end of the semiannual reporting period.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6 (a)(3)(iii)(A) or 71.6 (a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) through (4) of this section.
-
(b) Unless the Administrator has approved a different schedule for submission of reports under § 63.10(a), you must submit each report by the date in Table 10 to this subpart and as specified in paragraphs (b)(1) through (5) of this section.(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.9786 and ending on June 30 or December 31 and lasting at least 6 months but less than 12 months. For example, if your compliance date is March 1, then the first semiannual reporting period would begin on March 1 and end on December 31.(2) The first compliance report must be postmarked or delivered no later than July 31 or January 31 for compliance periods ending on June 30 and December 31, respectively.(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.(4) Each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31 for compliance periods ending on June 30 and December 31, respectively.(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71 and, if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (b)(1) through (4) of this section. In such cases, you must notify the Administrator of this change.
Citations to §63.10(a)(3)
-
(b) In addition to the information required under § 63.10, reports required under paragraph (a) of this section must include the information specified in paragraphs (b)(1) through (b)(5) of this section. As allowed by § 63.10(a)(3), if any State requires a report that contains all of the information required in a report listed in this section, an owner or operator may send the Administrator a copy of the report sent to the State to satisfy the requirements of this section for that report.(1) The owner or operator must submit reports that summarize the records maintained as part of the practices described in the maintenance plan for air pollution control devices required under § 63.1655(b), including an explanation of the periods when the procedures were not followed and the corrective actions taken.(2) In addition to the information required to be submitted in paragraph (b)(1) of this section, the owner or operator must submit reports that identify the periods when the average hourly pressure drop of venturi scrubbers used to control particulate emissions dropped below the levels established in § 63.1656(c)(4), and an explanation of the corrective actions taken.(3) The owner or operator must submit reports that explain the periods when the procedures outlined in the fugitive dust control plan pursuant to § 63.1654(a) were not followed and the corrective actions taken.(4) The owner or operator must submit reports that summarize the monitoring parameter excursions measured pursuant to § 63.1657(c) and the corrective actions taken.(5) The owner or operator must submit reports including the following information:(iii) Calculation of the percent of time the alarm on the bag leak detection system sounded during the reporting period.(i) The owner or operator must submit reports pursuant to § 63.10(e)(3) that are associated with excess emissions events such as the excursion of the scrubber pressure drop limit per paragraph (b)(2) of this section. These reports are to be submitted on a quarterly basis, unless the owner or operator can satisfy the requirements in § 63.10(e)(3) to reduce the frequency to a semiannual basis.(ii) All other reports specified in paragraphs (b)(1) through (b)(5) of this section must be submitted semiannually.
Citations to §63.10(a)(4)(ii)
-
(c) Each owner or operator of a source subject to subparts F, G, and H of this part shall keep copies of all applicable reports and records required by subparts F, G, and H of this part for at least 5 years; except that, if subparts G or H require records to be maintained for a time period different than 5 years, those records shall be maintained for the time specified in subpart G or H of this part. If an owner or operator submits copies of reports to the applicable EPA Regional Office, the owner or operator is not required to maintain copies of reports. If the EPA Regional Office has waived the requirement of § 63.10(a)(4)(ii) for submittal of copies of reports, the owner or operator is not required to maintain copies of reports.(1) All applicable records shall be maintained in such a manner that they can be readily accessed. The most recent 6 months of records shall be retained on site or shall be accessible from a central location by computer or other means that provides access within 2 hours after a request. The remaining four and one-half years of records may be retained offsite. Records may be maintained in hard copy or computer-readable form including, but not limited to, on paper, microfilm, computer, floppy disk, magnetic tape, or microfiche.(2) The owner or operator subject to subparts F, G, and H of this part shall keep the records specified in this paragraph, as well as records specified in subparts G and H.(i) Records of the occurrence and duration of each start-up, shutdown, and malfunction of operation of process equipment or of air pollution control equipment or continuous monitoring systems used to comply with this subpart or subpart G or H of this part during which excess emissions (as defined in § 63.102(a)(4)) occur. For each source as defined in § 63.101, on and after July 15, 2027, this paragraph (c)(2)(i) no longer applies; however, for historical compliance purposes, a copy of these records must be retained and available on-site for at least five years after the date of occurrence.(ii) For each start-up, shutdown, and malfunction during which excess emissions (as defined in § 63.102(a)(4)) occur, records that the procedures specified in the source's start-up, shutdown, and malfunction plan were followed, and documentation of actions taken that are not consistent with the plan. For example, if a start-up, shutdown, and malfunction plan includes procedures for routing a control device to a backup control device (e.g., the incinerator for a halogenated stream could be routed to a flare during periods when the primary control device is out of service), records must be kept of whether the plan was followed. These records may take the form of a “checklist,” or other form of recordkeeping that confirms conformance with the start-up, shutdown, and malfunction plan for the event. For each source as defined in § 63.101, on and after July 15, 2027, this paragraph (c)(2)(ii) no longer applies; however, for historical compliance purposes, a copy of the plan and these records must be retained and available on-site for 5 years after July 15, 2027.(iii) For continuous monitoring systems used to comply with subpart G of this part, records documenting the completion of calibration checks and maintenance of continuous monitoring systems that are specified in the manufacturer's instructions or other written procedures that provide adequate assurance that the equipment would reasonably be expected to monitor accurately.inning no later than the compliance dates specified in § 63.100(k)(10), the manufacturer's specifications specified in paragraph (c)(2)(iii) of this section must include a schedule for calibrations, preventative maintenance procedures, a schedule for preventative maintenance, and corrective actions to be taken if a calibration fails. If a continuous monitoring system calibration fails, the continuous monitoring system is considered to be inoperative until the owner or operator takes corrective action and the system passes calibration. The owner or operator must record the nature and cause of instances when the continuous monitoring system is inoperative and the corrective action taken.(3) Records of start-up, shutdown and malfunction and continuous monitoring system calibration and maintenance are not required if they pertain solely to Group 2 emission points, as defined in § 63.101, that are not included in an emissions average. For each source as defined in § 63.101, on and after July 15, 2027, the phrase “start-up, shutdown and malfunction and” in this paragraph (c)(3) no longer applies.
-
(2) If an owner or operator submits copies of reports to the appropriate EPA Regional Office, the owner or operator is not required to maintain copies of reports. If the EPA Regional Office has waived the requirement of § 63.10(a)(4)(ii) for submittal of copies of reports, the owner or operator is not required to maintain copies of those reports.
-
(2) If an owner or operator submits copies of reports to the appropriate EPA Regional Office, the owner or operator is not required to maintain copies of reports. If the EPA Regional Office has waived the requirement of § 63.10(a)(4)(ii) for submittal of copies of reports, the owner or operator is not required to maintain copies of those reports.
-
(a) Unless otherwise specified in this subpart, the owner or operator of an affected source shall keep copies of all applicable records and reports required by this subpart for at least 5 years. All applicable records shall be maintained in such a manner that they can be readily accessed. The most recent 6 months of records shall be retained on site or shall be accessible from a central location by computer or other means that provide access within 2 hours after a request. The remaining 4 and one-half years of records may be retained offsite. Records may be maintained in hard copy or computer-readable form including, but not limited to, on microfilm, computer, floppy disk, magnetic tape, or microfiche. Before May 18, 2026, if an owner or operator submits copies of reports to the applicable EPA Regional Office, the owner or operator is not required to maintain copies of reports. Before May 18, 2026, if the EPA Regional Office has waived the requirement of § 63.10(a)(4)(ii) for submittal of copies of reports, the owner or operator is not required to maintain copies of reports.
-
(f) Each owner or operator of a source subject to subparts I and H of this part shall keep copies of all applicable reports and records required by subpart H for at least 2 years, except as otherwise specified in subpart H. If an owner or operator submits copies of reports to the applicable EPA Regional Office, the owner or operator is not required to maintain copies of reports. If the EPA Regional Office has waived the requirement of § 63.10(a)(4)(ii) for submittal of copies of reports, the owner or operator is not required to maintain copies of reports.(1) All applicable records shall be maintained in such a manner that they can be readily accessed. The most recent 6 months of records shall be retained on site or shall be accessible from a central location by computer or other means that provides access within 2 hours after a request.(2) The owner or operator subject to subparts I and H of this part shall keep the records specified in this paragraph, as well as records specified in subpart H of this part.(i) Records of the occurrence and duration of each start-up, shutdown, and malfunction of operation of a process subject to this subpart as specified in § 63.190(b). On and after July 15, 2027, this paragraph no longer applies; however, for historical compliance purposes, a copy of these records must be retained and available on-site for at least five years after the date of occurrence.(ii) Records of the occurrence and duration of each malfunction of air pollution control equipment or continuous monitoring systems used to comply with subparts I and H of this part.(iii) For each start-up, shutdown, and malfunction, records that the procedures specified in the source's start-up, shutdown, and malfunction plan were followed, and documentation of actions taken that are not consistent with the plan. These records may take the form of a “checklist,” or other form of recordkeeping that confirms conformance with the startup, shutdown, and malfunction plan for the event. On and after July 15, 2027, this paragraph no longer applies; however, for historical compliance purposes, a copy of the plan and these records must be retained and available on-site for at least five years after the date of occurrence.
-
(2) If an owner or operator submits copies of reports to the appropriate EPA Regional Office, the owner or operator is not required to maintain copies of reports. If the EPA Regional Office has waived the requirement of § 63.10(a)(4)(ii) for submittal of copies of reports, the owner or operator is not required to maintain copies of those reports.
Citations to §63.10(a)(5)
-
(1) As provided by § 63.10(a)(5), if the owner or operator is required to submit periodic reports to a State on an established time line, he or she may change the dates by which periodic reports submitted under this part may be submitted (without changing the frequency of reporting) to be consistent with the State's schedule by mutual agreement between the owner or operator and the State. This provision may be applied at any point after the source's compliance date.
Citations to §63.10(b)
-
(a) Maintain files of all information required by § 63.10(b) of the general provisions in subpart A of this part, including all notifications and reports.
-
(c) A report of each event as required by § 63.10(b) of the general provisions in subpart A of this part, including a report if an action taken during a startup, shutdown, or malfunction is inconsistent with the procedures in the plan as described in § 63.6(e)(3) of the general provisions in subpart A of this part.
-
(1) As required by § 63.10(b) of this part, the owner or operator shall maintain files of all information (including all reports and notifications) required by the general provisions and this subpart:(i) The owner or operator must retain each record for at least 5 years following the date of each occurrence, measurement, maintenance, corrective action, report, or record. The most recent 2 years of records must be retained at the facility. The remaining 3 years of records may be retained off site;(ii) The owner or operator may retain records on microfilm, on a computer, on computer disks, on magnetic tape, or on microfiche; and(iii) The owner or operator may report required information on paper or on a labeled computer disk using commonly available and EPA-compatible computer software.
-
(a) As required by § 63.10(b), the owner or operator shall maintain files of all information (including all reports and notifications) required by the general provisions and this subpart.(1) The owner or operator must retain each record for at least 5 years following the date of each occurrence, measurement, maintenance, corrective action, report, or record. The most recent 2 years of records must be retained at the facility. The remaining 3 years of records may be retained off site.(2) The owner or operator may retain records on microfilm, computer disks, magnetic tape, or microfiche; and(3) The owner or operator may report required information on paper or on a labeled computer disk using commonly available and EPA-compatible computer software.
-
(b) Each owner or operator of an affected source subject to this subpart must maintain records of all liquid-liquid material balances performed in accordance with the requirements of § 63.3370. The records must be maintained in accordance with the applicable requirements of § 63.10(b).
-
(a) If you own or operate an affected source subject to § 63.362, you must comply with the recordkeeping requirements in § 63.10(a) through (c), according to the applicability in table 6 to this subpart, and in this section. All records required to be maintained by this subpart or a subpart referenced by this subpart shall be maintained in such a manner that they can be readily accessed and are suitable for inspection.
-
(a) . Each owner or operator of a source subject to this subpart shall fulfill all recordkeeping requirements specified in § 63.10(a), (b), (d), and (f), except § 63.10(b)(2)(i), (iv) and (v). Each owner or operator must also record and maintain according to § 63.10(b)(1) the information specified in paragraph (a)(1) through (3) of this section.(1) In the event that an affected unit fails to meet an applicable standard, record the number of failures. For each failure record the date, time, and duration of each failure.(2) For each failure to meet an applicable standard, record and retain a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(3) Record actions taken to minimize emissions in accordance with § 63.743(e), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(1) Except as provided in paragraphs (a)(2) through (5) of this section, each owner or operator subject to this subpart shall fulfill the requirements contained in § 63.9(a) through (e) and (h) through (j), Notification requirements, and § 63.10(a), (b), (d), and (f), Recordkeeping and reporting requirements, of the General Provisions, 40 CFR part 63, subpart A, and that the initial notification for existing sources required in § 63.9(b)(2) shall be submitted not later than September 1, 1997, or as specified in § 63.9(b)(2). In addition to the requirements of § 63.9(h), the notification of compliance status shall include:(i) Information detailing whether the source has operated within the specified ranges of its designated operating parameters.(ii) For each coating line, where averaging will be used along with the types of quantities of coatings the facility expects to use in the first year of operation. Averaging scheme shall be approved by the Administrator or delegated State authority and shall be included as part of the facility's title V or part 70 permit.
-
(a) Each owner or operator of an affected source shall comply with the applicable recordkeeping and reporting requirements in § 63.10 (a), (b), (d), and (f). Any owner that receives approval pursuant to § 63.783(c) to use an add-on control system to control coating emissions shall also comply with the applicable requirements of § 63.10 (c) and (e). A summary of recordkeeping and reporting requirements is provided in Table 3 of this subpart.
-
(c) Each owner or operator of an affected source subject to this subpart shall maintain records of all liquid-liquid material balances performed in accordance with the requirements of §§ 63.824-63.825 of this subpart. The records shall be maintained in accordance with the requirements of § 63.10(b) of this part.
-
(e) The owner or operator shall maintain files of all information (including all reports and notifications) required by § 63.10(b) and by this subpart.(1) The owner or operator must retain each record for at least 5 years following the date of each occurrence, measurement, maintenance, corrective action, report, or record. The most recent 2 years of records must be retained at the facility. The remaining 3 years of records may be retained offsite;(2) The owner or operator may retain records on microfilm, on a computer, on computer disks, on magnetic tape, or on microfiche;(3) The owner or operator may report required information on paper or on a labeled computer disc using commonly available and compatible computer software; and(4) In addition to the general records required by § 63.10(b), the owner or operator shall maintain records of the following information:(i) Daily production rate of aluminum;(ii) Daily production rate of green anode material placed in the anode bake furnace;(iii) [Reserved](iv) Records of design information for paste production plant capture systems;(v) Records of design information for an alternative emission control device for a paste production plant;(vi) Records supporting the monitoring of similar potlines demonstrating that the performance of similar potlines is the same as or better than that of potlines sampled by manual methods;(vii) Records supporting a request for reduced sampling of potlines;(viii) Records supporting the correlation of emissions measured by a continuous emission monitoring system to emissions measured by manual methods and the derivation of the alternative emission limit derived from the measurements;(ix) The current implementation plan for emission averaging and any subsequent amendments;(x) Records, such as a checklist or the equivalent, demonstrating that the daily inspection of a potline with wet roof scrubbers for secondary emission control has been performed as required in § 63.848(f)(5)(ii), including the results of each inspection;(xi) Records, such as a checklist or the equivalent, demonstrating that the daily visual inspection of the exhaust stack for each control device has been performed as required in § 63.848(g), including the results of each inspection;(xii) For a potline equipped with an HF continuous emission monitor, records of information and data required by § 63.10(c);(xiii) Records documenting the corrective actions taken when the limit(s) for an operating parameter established under § 63.847(h) were exceeded, when visible emissions indicating abnormal operation were observed from a control device stack during a daily inspection required under § 63.848(g), or when a problem was detected during the daily inspection of a wet roof scrubber for potline secondary control required in § 63.848(f)(5)(ii);(xiv) Records documenting any POM data that are invalidated due to the installation and startup of a cathode;(xv) Records documenting the portion of TF that is measured as particulate matter and the portion that is measured as gaseous when the particulate and gaseous fractions are quantified separately using an approved test method;(xvi) Records of the occurrence and duration of each malfunction of operation (i.e. process equipment) or the air pollution control equipment and monitoring equipment; and
Citations to §63.10(b)(1)
-
(iii) The owner or operator shall follow the recordkeeping procedures outlined in § 63.10(b)(1) for the DCOT certification, compliance report, data sheets, and all raw unaltered JPEGs used for opacity and certification determination.
-
(C) The owner or operator shall follow the recordkeeping procedures outlined in § 63.10(b)(1) for the DCOT certification, compliance report, data sheets, and all raw unaltered JPEGs used for opacity and certification determination.
-
(iii) You must follow the record keeping procedures outlined in § 63.10(b)(1) for the DCOT certification, compliance report, data sheets, and all raw unaltered JPEGs used for opacity and certification determination.
-
(3) For NSPS, the Administrator of the EPA, an employee of the EPA, the Director of the state air pollution control agency, or employee of the state air pollution control agency to whom the authority has been delegated by the Administrator of the EPA to perform the specified task.Air curtain incinerator means an incinerator that operates by forcefully projecting a curtain of air across an open chamber or pit in which burning occurs. Incinerators of that type can be constructed above or below ground and with or without refractory walls and floor.Batch municipal waste combustor means a municipal waste combustor designed so it cannot combust municipal solid waste continuously 24 hours per day because the design does not allow waste to be fed to the unit or ash to be removed during combustion.Bubbling fluidized bed combustor means a fluidized bed combustor in which the majority of the bed material remains in a fluidized state in the primary combustion zone.Calendar quarter means a consecutive 3-month period (nonoverlapping) beginning on January 1, April 1, July 1, and October 1.Calendar year means the period including 365 days starting January 1 and ending on December 31.CEMS means continuous emissions monitoring system.CEMS data during warmup, startup, and shutdown means CEMS data collected during periods of operation defined within this subpart as warmup, startup or shutdown.Chief facility operator means the person in direct charge and control of the operation of a municipal waste combustor and who is responsible for daily onsite supervision, technical direction, management, and overall performance of the facility.Circulating fluidized bed combustor means a fluidized bed combustor in which the majority of the fluidized bed material is carried out of the primary combustion zone and is transported back to the primary zone through a recirculation loop.Clean wood means untreated wood or untreated wood products including clean or untreated lumber (as defined in this subpart), tree stumps (whole or chipped), and tree limbs (whole or chipped). Clean wood does not include yard waste, which is defined elsewhere in this section, wood products that have been painted, pigment-stained, or pressure-treated by compounds such as chromate copper arsenate, pentachlorophenol, and creosote, or construction, renovation, and demolition wastes (including but not limited to railroad ties and telephone poles), which are exempt from the definition of municipal solid waste in this section.Cofired combustor means a unit combusting municipal solid waste with nonmunicipal solid waste fuel (e.g., coal, industrial process waste) and subject to a federally enforceable permit limiting the unit to combusting a fuel feed stream, 30 percent or less of the weight of which is comprised, in aggregate, of municipal solid waste as measured on a calendar quarter basis.Continuous automated sampling system means the total equipment and procedures for automated sample collection and sample recovery/analysis to determine a pollutant concentration or emission rate by collecting a single or multiple integrated sample(s) of the pollutant (or diluent gas) for subsequent on-or off-site analysis; integrated sample(s) collected are representative of the emissions for the sample time as specified by the applicable requirement.Continuous emission monitoring system means a monitoring system that continuously measures the emissions of a pollutant from an affected facility.Digital camera opacity technique conditions mean the following four conditions that must be followed if ASTM D7520-16, “Standard Test Method for Determining the Opacity of a Plume in the Outdoor Ambient Atmosphere” is used as an alternative to EPA Method 9:
-
(3) For NSPS, the Administrator of the EPA, an employee of the EPA, the Director of the state air pollution control agency, or employee of the state air pollution control agency to whom the authority has been delegated by the Administrator of the EPA to perform the specified task.Air curtain incinerator means an incinerator that operates by forcefully projecting a curtain of air across an open chamber or pit in which burning occurs. Incinerators of that type can be constructed above or below ground and with or without refractory walls and floor.Batch municipal waste combustor means a municipal waste combustor designed so it cannot combust municipal solid waste continuously 24 hours per day because the design does not allow waste to be fed to the unit or ash to be removed during combustion.Bubbling fluidized bed combustor means a fluidized bed combustor in which the majority of the bed material remains in a fluidized state in the primary combustion zone.Calendar quarter means a consecutive 3-month period (nonoverlapping) beginning on January 1, April 1, July 1, and October 1.Calendar year means the period including 365 days starting January 1 and ending on December 31.CEMS means continuous emissions monitoring system.CEMS data during warmup, startup, and shutdown means CEMS data collected during periods of operation defined within this subpart as warmup, startup or shutdown.Chief facility operator means the person in direct charge and control of the operation of a municipal waste combustor and who is responsible for daily onsite supervision, technical direction, management, and overall performance of the facility.Circulating fluidized bed combustor means a fluidized bed combustor in which the majority of the fluidized bed material is carried out of the primary combustion zone and is transported back to the primary zone through a recirculation loop.Clean wood means untreated wood or untreated wood products including clean or untreated lumber (as defined in this subpart), tree stumps (whole or chipped), and tree limbs (whole or chipped). Clean wood does not include yard waste, which is defined elsewhere in this section, wood products that have been painted, pigment-stained, or pressure-treated by compounds such as chromate copper arsenate, pentachlorophenol, and creosote, or construction, renovation, and demolition wastes (including but not limited to railroad ties and telephone poles), which are exempt from the definition of municipal solid waste in this section.Cofired combustor means a unit combusting municipal solid waste with nonmunicipal solid waste fuel (e.g., coal, industrial process waste) and subject to a federally enforceable permit limiting the unit to combusting a fuel feed stream, 30 percent or less of the weight of which is comprised, in aggregate, of municipal solid waste as measured on a calendar quarter basis.Continuous automated sampling system means the total equipment and procedures for automated sample collection and sample recovery/analysis to determine a pollutant concentration or emission rate by collecting a single or multiple integrated sample(s) of the pollutant (or diluent gas) for subsequent on-or off-site analysis; integrated sample(s) collected are representative of the emissions for the sample time as specified by the applicable requirement.Continuous emission monitoring system means a monitoring system that continuously measures the emissions of a pollutant from an affected facility.Dioxins/furans mean tetra- through octa- chlorinated dibenzo-p-dioxins and dibenzofurans. For the purposes of this subpart, dioxins/furans emission limits are expressed on a total mass basis.Digital camera opacity technique conditions mean the following four conditions that must be followed if ASTM D7520-16, “Standard Test Method for Determining the Opacity of a Plume in the Outdoor Ambient Atmosphere” (incorporated by reference, see § 60.17), is used as an alternative to EPA Method 9:
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(d) As required by § 63.10(b)(1), you must maintain files of all information (including all reports and notifications) for at least 5 years following the date of each occurrence, measurement, maintenance, corrective action, report, or record. At a minimum, the most recent 2 years of data shall be retained on site. The remaining 3 years of data may be retained off site. Such files may be maintained on microfilm, on a computer, on computer floppy disks, on magnetic tape disks, or on microfiche. Any records required to be maintained by this part that are submitted electronically via the EPA's Compliance and Emissions Data Reporting Interface (CEDRI) may be maintained in electronic format. This ability to maintain electronic copies does not affect the requirement for facilities to make records, data, and reports available upon request to a delegated air agency or the EPA as part of an on-site compliance evaluation.
-
(a) As required by § 63.10(b)(1), you must maintain files of all information (including all reports and notifications) for at least 5 years following the date of each occurrence, measurement, maintenance, corrective action, report, or record. At a minimum, the most recent 2 years of data shall be retained on site. The remaining 3 years of data may be retained off site. Such files may be maintained on microfilm, on a computer, on computer floppy disks or flash drives, on magnetic tape disks, or on microfiche. Any records required to be maintained by this part that are submitted electronically via the EPA's CEDRI may be maintained in electronic format. This ability to maintain electronic copies does not affect the requirement for facilities to make records, data, and reports available upon request to a delegated air agency or the EPA as part of an on-site compliance evaluation.
-
(C) You must follow the recordkeeping procedures outlined in § 63.10(b)(1) for the DCOT certification, compliance report, data sheets, and all raw unaltered JPEGs used for opacity and certification determination.
-
(b) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(b) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(b) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(c) You must maintain files of all information required by this subpart for at least 5 years following the date of each occurrence according to the requirements in § 63.10(b)(1). If you are subject, you must comply with the recordkeeping and reporting requirements of § 63.10(b)(2)(iii) and (vi) through (xiv), and the applicable requirements specified in paragraphs (c)(1) through (11) of this section.(1) For each CMPU subject to this subpart, you must keep the records specified in paragraphs (c)(1)(i) through (viii) of this section.(i) Except as specified in paragraph (c)(9) of this section, records of management practice inspections, repairs, and reasons for any delay of repair, as specified in § 63.11495(a)(5).(ii) Except as specified in paragraph (c)(11) of this section, records of small heat exchange system inspections, demonstrations of indications of leaks that do not constitute leaks, repairs, and reasons for any delay in repair as specified in § 63.11495(b).(iii) If batch process vent emissions are less than 10,000 lb/yr for a CMPU, records of batch process vent emission calculations, as specified in § 63.11496(a)(1), the number of batches operated each month, as specified in § 63.11496(a)(3), and any updated emissions calculations, as specified in § 63.11496(a)(3). Alternatively, keep records of the worst-case processes or organic HAP usage, as specified in § 63.11496(a)(2) and (4), respectively.(iv) Records of all TRE calculations for continuous process vents as specified in § 63.11496(b)(2).(v) Records of metal HAP emission calculations as specified in § 63.11496(f)(1) and (2). If total uncontrolled metal HAP process vent emissions from a CMPU subject to this subpart are estimated to be less than 400 lb/yr, also keep records of either the number of batches per month or operating hours, as specified in § 63.11496(f)(2).(vi) Records identifying wastewater streams and the type of treatment they receive, as specified in table 6 to this subpart.(vii) Before April 1, 2029, records of the date, time, and duration of each malfunction of operation of process equipment, control devices, recovery devices, or continuous monitoring systems used to comply with this subpart that causes a failure to meet a standard. The record must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. After April 1, 2029, for any deviation, records of the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions.(viii) Before April 1, 2029, records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.11495(d), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. After April 1, 2029, for any deviation, records of actions taken to minimize emissions in accordance with § 63.11495(d), and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) For batch process vents subject to table 2 to this subpart and continuous process vents subject to table 3 to this subpart, you must keep records specified in paragraphs (c)(2)(i) or (ii) of this section, as applicable.(i) If you route emissions to a control device other than a flare, keep records of performance tests, if applicable, as specified in § 63.998(a)(2)(ii) and (4), keep records of the monitoring system and the monitored parameters, as specified in § 63.998(b) and (c), and keep records of the closed-vent system, as specified in § 63.998(d)(1). If you use a recovery device to maintain the TRE above 1.0 for a continuous process vent, keep records of monitoring parameters during the TRE index value determination, as specified in § 63.998(a)(3).(ii) If you route emissions to a flare, keep records of the flare compliance assessment, as specified in § 63.998(a)(1)(i), keep records of the pilot flame monitoring, as specified in § 63.998(a)(1)(ii) and (iii), and keep records of the closed-vent system, as specified in § 63.998(d)(1).(3) For metal HAP process vents subject to table 4 to this subpart, you must keep records specified in paragraph (c)(3)(i) or (ii) of this section, as applicable.(i) For a new source using a control device other than a baghouse and for any existing source, maintain a monitoring plan, as specified in § 63.11496(f)(3)(i), and keep records of monitoring results, as specified in § 63.11496(f)(3).(ii) For a new source using a baghouse to control metal HAP emissions, keep a site-specific monitoring plan, as specified in §§ 63.11496(f)(4) and 63.11410(g), and keep records of bag leak detection systems, as specified in §§ 63.11496(f)(4) and 63.11410(g)(4).(4) For each storage tank subject to table 5 to this subpart, you must keep records specified in paragraphs (c)(4)(i) through (vii) of this section, as applicable.(i) Keep records of the vessel dimensions, capacity, and liquid stored, as specified in § 63.1065(a).(ii) Keep records of each inspection of an internal floating roof, as specified in § 63.1065(b)(1).(iii) Keep records of each seal gap measurement for external floating roofs, as specified in § 63.1065(b)(2), and keep records of inspections of external floating roofs, as specified in § 63.1065(b)(1).(iv) If you vent emissions to a control device other than a flare, keep records of the operating plan and measured parameter values, as specified in §§ 63.985(c) and 63.998(d)(2).(v) If you vent emissions to a flare, keep records of all periods of operation during which the flare pilot flame is absent, as specified in §§ 63.987(c) and 63.998(a)(1), and keep records of closed-vent systems, as specified in § 63.998(d)(1).(vi) For periods of planned routine maintenance of a control device, keep records of the day and time at which each maintenance period begins and ends, and keep records of the type of maintenance performed, as specified in § 63.11497(b)(3).(vii) For each pressure vessel subject to the requirements of § 63.11497(f) you must keep records as specified in paragraphs (c)(4)(vii)(A) and (B) of this section.(A) The date of each performance test conducted according to § 63.11497(f)(2).(B) The record of each performance test conducted according to § 63.11497(f)(2), including the following:(1) Date each defect was detected and the instrument reading (in ppmv) during the performance test.(2) Date of the next performance test that shows the instrument reading is less than 500 ppmv and the instrument reading (in ppmv) during the performance test.(3) Start and end dates of each period after the date in paragraph (c)(4)(ix)(B)(1) of this section when the pressure vessel was completely empty.(4) Estimated emissions from each defect.(5) For each wastewater stream subject to item 2 in table 6 to this subpart, keep records of the wastewater stream identification and the disposition of the organic phase(s), as specified in item 2 to table 6 to this subpart.(6) Except as specified in paragraph (c)(11) of this section, for each large heat exchange system subject to table 8 to this subpart, you must keep records of detected leaks; the date the leak was detected; if demonstrated not to be a leak, the basis for that determination; the date of efforts to repair the leak; and the date the leak is repaired, as specified in table 8 to this subpart.(7) You must keep a record of all transferred liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) For continuous process vents subject to table 3 to this subpart, keep records of the occurrence and duration of each startup and shutdown of operation of process equipment, or of air pollution control and monitoring equipment.(9) If you are subject to the equipment leak requirements specified in § 63.11495(a)(6), then you must keep records as specified in paragraphs (c)(9)(i) through (vii) of this section instead of the records specified in paragraph (c)(1)(i) of this section.(i) Keep a list, summary description, or diagram(s) showing the location and identification number of all equipment in organic HAP service at the facility and the information in paragraphs (c)(9)(i)(A) through (D) of this section.(A) Identification of equipment designated as unsafe to monitor, difficult to monitor, unsafe to inspect, difficult to inspect, or unsafe to repair and the plan for monitoring or inspecting this equipment, as applicable.(B) Identification of the equipment in batch process units, for which you do not elect to pressure test the batch product process equipment train.(ii) For leak detection monitoring and inspections required by paragraphs § 63.11495(a)(6) (e.g., monitoring using Method 21 of appendix A-7 to part 60 of this chapter; visible, audible, or olfactory monitoring; closed vent system inspections; and batch process unit monitoring), record the date of the monitoring or inspection and include a statement of whether leaks were detected. If no leaks are detected, records of the monitoring and inspection results are not required.(iii) When each leak is detected as specified in § 63.11495(a)(6), the following information must be recorded:(A) The instrument and the equipment identification number and the operator name, initials, or identification number.(D) Maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A-7 of this chapter after it is successfully repaired or determined to be nonrepairable.(E) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(1) You may develop a written procedure that identifies the conditions that justify a delay of repair. In such cases, reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(2) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked on-site before depletion and the reason for depletion.(iv) For each pressure relief device subject to the provisions in § 63.165(e), you must keep the records specified in paragraphs (c)(9)(iv)(A) through (C) of this section.(A) Records of the prevention measures implemented as required in § 63.165(e)(3)(ii).(C) For each release to the atmosphere, you must keep the records specified in paragraphs (c)(9)(iv)(C)(1) through (4) of this section.(1) The start and end time and date of each pressure release to the atmosphere.(2) Records of any data, assumptions, and calculations used to estimate of the mass quantity of each organic HAP released during the event.(3) Records of the root cause analysis and corrective action analysis conducted as required in § 63.165(e)(3)(iii), including an identification of the affected facility, a statement noting whether the event resulted from the same root cause(s) identified in a previous analysis and either a description of the recommended corrective action(s) or an explanation of why corrective action is not necessary under § 63.165(e)(7)(i).(4) For any corrective action analysis for which implementation of corrective actions are required in § 63.165(e)(7), a description of the corrective action(s) completed within the first 45 days following the discharge and, for action(s) not already completed, a schedule for implementation, including proposed commencement and completion dates.(v) If you own or operate a batch product process and elect to pressure test the batch product process equipment train to demonstrate compliance with § 63.11495(a)(6), you are exempt from the requirements of paragraphs (c)(9)(i) through (iv) of this section. Instead, you must maintain records of the following information:(B) The dates of each pressure test required in § 63.178(b), the test pressure, and the pressure drop observed during the test.(C) When a batch product process equipment train does not pass two consecutive pressure tests, the following information must be recorded:(1) The date of each pressure test and the date of each leak repair attempt.(2) Repair methods applied in each attempt to repair the leak.(3) The reason for the delay of repair.(4) The expected date for delivery of the replacement equipment and the actual date of delivery of the replacement equipment.(5) The date of successful repair.(vi) You must maintain records of the information specified in paragraphs (c)(9)(vi)(A) through (C) of this section for closed vent systems and control devices subject to the provisions of § 63.172. The records specified in paragraph (c)(9)(vi)(A) of this section must be retained for the life of the equipment.(A) The design specifications and performance demonstrations specified in paragraphs (c)(9)(vi)(A)(1) through (4) of this section.(1) Detailed schematics, design specifications of the control device, and piping and instrumentation diagrams.(2) The dates and descriptions of any changes in the design specifications.(3) The flare design (i.e., steam-assisted, air-assisted, or non-assisted) and the results of the compliance demonstration required by subpart SS of this part.(4) A description of the parameter or parameters monitored, as required in § 63.172(e), to ensure that control devices are operated and maintained in conformance with their design and an explanation of why that parameter (or parameters) was selected for the monitoring.(B) Records of operation of closed vent systems and control devices, as specified in paragraphs (c)(9)(vi)(B)(1) through (3) of this section.(1) Dates and durations when the closed vent systems and control devices required in § 63.11495(a)(6) are not operated as designed as indicated by the monitored parameters, including periods when a flare pilot light system does not have a flame.(2) Dates and durations during which the monitoring system or monitoring device is inoperative.(3) Dates and durations of startups and shutdowns of control devices required in § 63.11495(a)(6).(C) Records of inspections of closed vent systems subject to the provisions of § 63.172, as specified in paragraphs (c)(9)(vi)(C)(1) and (2) of this section.(1) For each inspection conducted in accordance with the provisions of § 63.172(f)(1) or (2) during which leaks were detected, the information specified in paragraph (c)(9)(iii) of this section must be recorded.(2) For each flow event from a bypass line subject to the requirements in § 63.172(j), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements in § 63.11495(a)(6), you must include an estimate of the volume of gas, the concentration of organic HAP in the gas, and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(vii) If you choose to comply with the requirements of § 63.179, you must maintain the following records:(C) A description of the system used to create a negative pressure in the enclosure to ensure that all emissions are routed to the control device.(10) For each flow event from a bypass line subject to the requirements in § 63.11495(e), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements specified in §§ 63.11495 through 63.11499, you must include an estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must keep records as specified in § 63.104(f)(3) instead of the heat exchange system records specified in paragraphs (c)(1)(ii) and (6) of this section.
-
(f) You must keep each record for a minimum of 5 years following the date of each occurrence, measurement, maintenance, corrective action, report, or record. You must keep each record onsite for at least 2 years after the date of each occurrence, measurement, maintenance, corrective action, report, or record, according to § 63.10(b)(1) of the General Provisions to part 63. You may keep the records offsite for the remaining 3 years.
-
(i) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1), “General Provisions.” Where appropriate, the records may be maintained as electronic spreadsheets or as a database.
-
(e) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(d) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). As specified in § 63.10(b)(1), you must keep each record for 5 years following the date of each recorded action. For records of annual metal melt production, you must keep the records for 5 years from the end of the calendar year. You must keep each record onsite for at least 2 years after the date of each recorded action according to § 63.10(b)(1). You may keep the records offsite for the remaining 3 years.
-
(i) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(4) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(7) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(e) You must keep the records specified in paragraphs (e)(1) through (e)(3) of this section. The form and maintenance of records must be consistent with the requirements in section 63.10(b)(1) of the General Provisions.(1) As required in § 63.10(b)(2)(xiv), you must keep a copy of each notification that you submitted to comply with this subpart and all documentation supporting any Initial Notification, Notification of Compliance Status, and semiannual compliance certifications that you submitted.(2) You must keep the records of all performance tests, measurements, monitoring data, and corrective actions required by §§ 63.11646 and 63.11647, and the information identified in paragraphs (c)(2)(i) through (c)(2)(vi) of this section for each corrective action required by § 63.11647.(i) The date, place, and time of the monitoring event requiring corrective action;(ii) Technique or method used for monitoring;(iv) Operating conditions during the activity;(v) Results, including the date, time, and duration of the period from the time the monitoring indicated a problem to the time that monitoring indicated proper operation; and(3) You must keep records of operating hours for each process as required by § 63.11646(a)(5) and records of the monthly quantity of ore and concentrate processed or produced as required by § 63.11646(a)(10).
-
(a) You must keep records for 5 years in a form suitable and readily available for expeditious review, as specified in § 63.10(b)(1).
-
(1) Each owner or operator of an affected source shall keep copies of all records and reports required by this subpart for at least 5 years, as specified in § 63.10(b)(1).
-
(j) The owner or operator of any affected source implementing the LDAR program specified in § 63.1255 of this subpart shall implement the reporting requirements in § 63.1255 of this subpart. Copies of all reports shall be retained as records for a period of 5 years, in accordance with the requirements of § 63.10(b)(1).
-
(a) The owner or operator shall maintain files of all information (including all reports and notifications) required by this section recorded in a form suitable and readily available for inspection and review as required by § 63.10(b)(1). The files shall be retained for at least five years following the date of each occurrence, measurement, maintenance, corrective action, report, or record. At a minimum, the most recent two years of data shall be retained on site. The remaining three years of data may be retained off site. The files may be maintained on microfilm, on a computer, on floppy disks, on magnetic tape, or on microfiche.
-
(4) When each leak is detected as specified in paragraphs (c) and (e) of this section and §§ 63.164, 63.169, 63.172, and 63.174 of subpart H of this part, the owner or operator shall record the information specified in paragraphs (g)(4)(i) through (ix) of this section. All records shall be retained for 5 years, in accordance with the requirements of § 63.10(b)(1) of subpart A of this part.(i) The instrument and the equipment identification number and the operator name, initials, or identification number.(iv) If postrepair monitoring is required, maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A, after it is successfully repaired or determined to be nonrepairable.(v) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(A) The owner or operator may develop a written procedure that identifies the conditions that justify a delay of repair. The written procedures must be maintained at the plant site. Reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(B) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked onsite before depletion and the reason for depletion.(vi) If repairs were delayed, dates of process shutdowns that occur while the equipment is unrepaired.(A) If the alternative in § 63.174(c)(1)(ii) of subpart H of this part is not in use for the monitoring period, identification, either by list, location (area or grouping), or tagging of connectors disturbed since the last monitoring period required in § 63.174(b) of subpart H of this part, as described in § 63.174(c)(1) of subpart H of this part.(B) The date and results of follow-up monitoring as required in § 63.174(c) of subpart H of this part. If identification of disturbed connectors is made by location, then all connectors within the designated location shall be monitored.(viii) The date and results of the monitoring required in § 63.178(c)(3)(i) of subpart H of this part for equipment added to a batch process since the last monitoring period required in § 63.178(c)(3)(ii) and (iii) of subpart H of this part. If no leaking equipment is found in this monitoring, the owner or operator shall record that the inspection was performed. Records of the actual monitoring results are not required.(ix) Copies of the periodic reports as specified in paragraph (h)(3) of this section, if records are not maintained on a computerized data base capable of generating summary reports from the records.
-
(1) Each owner or operator of an affected source shall keep copies of all records and reports required by this subpart for at least 5 years, as specified in § 63.10(b)(1) of subpart A of this part.
-
(j) The owner or operator of an affected source subject to the standards in § 63.1363, shall implement the reporting requirements specified in § 63.1363(h). Copies of all reports shall be retained as records for a period of 5 years, in accordance with the requirements of § 63.10(b)(1) of subpart A of this part.
-
(C) You must follow the record keeping procedures outlined in § 63.10(b)(1) for the DCOT certification, compliance report, data sheets, and all raw unaltered JPEGs used for opacity and certification determination.
-
(b) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(iii) The owner or operator must follow the recordkeeping procedures outlined in § 63.10(b)(1) for DCOT certification, compliance report, data sheets and all raw unaltered JPEGs used for opacity and certification determination.
-
(g) Your records must be in a form suitable and readily available for expeditious review according to § 63.10(b)(1).
-
(iii) You must follow the recordkeeping procedures outlined in § 63.10(b)(1) for the DCOT certification, compliance report, data sheets and all raw unaltered JPEGs used for opacity and certification determination.
-
(1) Records must be maintained in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). However, electronic recordkeeping and reporting is encouraged and required for some records and reports.
-
(iii) The owner or operator must follow the recordkeeping procedures outlined in § 63.10(b)(1) for the DCOT certification, compliance report, data sheets and all raw unaltered JPEGs used for opacity and certification determination.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious review as specified in § 63.10(b)(1).
-
(a) For each storage tank subject to this subpart having a capacity of less than 18.9 cubic meters (5,000 gallons) and for each transfer rack subject to this subpart that only unloads organic liquids (i.e., no organic liquids are loaded at any of the transfer racks), you must keep documentation that verifies that each storage tank and transfer rack identified in this paragraph (a) is not required to be controlled. The documentation must be kept up-to-date (i.e., all such emission sources at a facility are identified in the documentation regardless of when the documentation was last compiled) and must be in a form suitable and readily available for expeditious inspection and review according to § 63.10(b)(1), including records stored in electronic form in a separate location. The documentation may consist of identification of the tanks and transfer racks identified in this paragraph (a) on a plant site plan or process and instrumentation diagram (P&ID).
-
(a) Your records must be in a form suitable and readily available for expeditious inspection and review according to § 63.10(b)(1), including records stored in electronic form at a separate location.
-
(l) Beginning no later than the compliance dates specified in § 63.2445(g), paragraph (h) of this section no longer applies. Instead, for each deviation from an emission limit, operating limit, or work practice standard, you must keep a record of the information specified in paragraph (l)(1) through (3) of this section. The records shall be maintained as specified in § 63.10(b)(1) of subpart A.(1) In the event that an affected unit does not meet an applicable standard, record the number of deviations. For each deviation record the date, time, and duration of each deviation.(2) For each deviation from an applicable standard, record and retain a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(3) Record actions taken to minimize emissions in accordance with § 63.2450(u) and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(a) Your records must be in a form suitable and readily available for review in accordance with § 63.10(b)(1).
-
(C) The owner or operator must follow the recordkeeping procedures outlined in § 63.10(b)(1) for the DCOT certification, compliance report, data sheets, and all raw unaltered JPEGs used for opacity and certification determination.
-
(a) Your records must be in a form suitable and readily available for expeditious review according to § 63.10(b)(1). Where appropriate, the records may be maintained as electronic spreadsheets or as a database. On and after January 5, 2021, any records required to be maintained by this subpart that are submitted electronically via the EPA's CEDRI may be maintained in electronic format. This ability to maintain electronic copies does not affect the requirement for facilities to make records, data, and reports available upon request to a delegated air agency or the EPA as part of an on-site compliance evaluation.
-
(a) Each owner or operator of an affected source subject to this subpart must maintain the records specified in paragraphs (a)(1) and (2) of this section on a monthly basis in accordance with the requirements of § 63.10(b)(1):(1) Records specified in § 63.10(b)(2) of all measurements needed to demonstrate compliance with this standard as indicated in Table 2 to subpart JJJJ of part 63, including:(i) Continuous emission monitor data in accordance with the requirements of § 63.3350(d);(ii) Control device and capture system operating parameter data in accordance with the requirements of § 63.3350(c), (e), and (f);(iii) Organic HAP content data for the purpose of demonstrating compliance in accordance with the requirements of § 63.3360(c);(iv) Volatile matter and coating solids content data for the purpose of demonstrating compliance in accordance with the requirements of § 63.3360(d);(v) Overall control efficiency determination using capture efficiency and control device destruction or removal efficiency test results in accordance with the requirements of § 63.3360(e) and (f);(vi) Material usage, organic HAP usage, volatile matter usage, and coating solids usage and compliance demonstrations using these data in accordance with the requirements of § 63.3370(b), (c), and (d); and(vii) Emission factor development calculations and HAP content for coating materials used to develop the emission factor as needed for § 63.3360(g).(2) Records specified in § 63.10(c) for each CMS operated by the owner or operator in accordance with the requirements of § 63.3350(b), as indicated in Table 2 to subpart JJJJ of part 63.
-
(c) All records shall be maintained for a period of 5 years in accordance with § 63.10(b)(1).
-
(a) Your records must be kept in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). Where appropriate, the records may be maintained as electronic spreadsheets or as a database. On and after August 24, 2020, any records required to be maintained by this subpart that are in reports that were submitted electronically via the EPA's CEDRI may be maintained in electronic format. This ability to maintain electronic copies does not affect the requirement for facilities to make records, data, and reports available upon request to a delegated air agency or the EPA as part of an on-site compliance evaluation.
-
(f) For each deviation from an emission limit, operating limit, or best management practice, you must keep a record of the information specified in paragraph (g)(1) through (4) of this section. The records shall be maintained as specified in § 63.10(b)(1).(1) The occurrence and duration of each startup, shutdown, or malfunction of process, air pollution control, and monitoring equipment.(2) In the event that an affected unit does not meet an applicable standard, record the number of deviations. For each deviation, record the date, time, cause, and duration of each deviation.(3) For each failure to meet an applicable standard, record and retain a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(4) Record actions taken to minimize emissions in accordance with § 63.362(k) and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). Where appropriate, the records may be maintained as electronic spreadsheets or as a database. On and after January 5, 2021, any records required to be maintained by this subpart that are in reports that were submitted electronically via the EPA's CEDRI may be maintained in electronic format. This ability to maintain electronic copies does not affect the requirement for facilities to make records, data, and reports available upon request to a delegated air agency or the EPA as part of an on-site compliance evaluation.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). Where appropriate, the records may be maintained as electronic spreadsheets or as a data base. Any records required to be maintained by this subpart that are in reports that were submitted electronically via the EPA's CEDRI may be maintained in electronic format. This ability to maintain electronic copies does not affect the requirement for facilities to make records, data, and reports available upon request to a delegated air agency or the EPA as part of an on-site compliance evaluation.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). Where appropriate, the records may be maintained as electronic spreadsheets or as a database. Any records required to be maintained by this subpart that are in reports that were submitted electronically via the EPA's CEDRI may be maintained in electronic format. This ability to maintain electronic copies does not affect the requirement for facilities to make records, data, and reports available upon request to a delegated air agency or the EPA as part of an on-site compliance evaluation.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). Where appropriate, the records may be maintained as electronic spreadsheets or as a database. On and after January 5, 2021, any records required to be maintained by this subpart that are in reports that were submitted electronically via the EPA's CEDRI may be maintained in electronic format. This ability to maintain electronic copies does not affect the requirement for facilities to make records, data, and reports available upon request to a delegated air agency or the EPA as part of an on-site compliance evaluation.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). Where appropriate, the records may be maintained as electronic spreadsheets or as a database.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). Where appropriate, the records may be maintained as electronic spreadsheets or as a database. Any records required to be maintained by this subpart that are in reports that were submitted electronically via the EPA's CEDRI may be maintained in electronic format. This ability to maintain electronic copies does not affect the requirement for facilities to make records, data, and reports available upon request to a delegated air agency or the EPA as part of an on-site compliance evaluation.
-
(a) You must maintain the records specified in paragraphs (a) and (b) of this section in accordance with § 63.10(b)(1):(1) Records of the coating lines on which you used each compliance option and the time periods (beginning and ending dates and times) you used each option.(2) Records specified in § 63.10(b)(2) of all measurements needed to demonstrate compliance with this subpart, including:(i) Continuous emission monitor data in accordance with § 63.5150(a)(2);(ii) Control device and capture system operating parameter data in accordance with § 63.5150(a)(1), (3), and (4);(iii) Organic HAP content data for the purpose of demonstrating compliance in accordance with § 63.5160(b);(iv) Volatile matter and solids content data for the purpose of demonstrating compliance in accordance with § 63.5160(c);(v) Overall control efficiency determination or alternative outlet HAP concentration using capture efficiency tests and control device destruction or removal efficiency tests in accordance with § 63.5160(d), (e), and (f); and(vi) Material usage, HAP usage, volatile matter usage, and solids usage and compliance demonstrations using these data in accordance with § 63.5170(a), (b), and (d);(3) Records specified in § 63.10(b)(3); and(4) Additional records specified in § 63.10(c) for each continuous monitoring system operated by the owner or operator in accordance with § 63.5150(a)(2).(5) On and after August 24, 2020, for each deviation from an emission limitation reported under § 63.5180(h) or (i), a record of the information specified in paragraphs (a)(5)(i) through (iv) of this section, as applicable.(i) The date, time, and duration of the deviation, as reported under § 63.5180(h) and (i).(ii) A list of the affected sources or equipment for which the deviation occurred and the cause of the deviation, as reported under § 63.5180(h) and (i).(iii) An estimate of the quantity of each regulated pollutant emitted over any applicable emission limit in § 63.5120 to this subpart or any applicable operating limit established according to § 63.5121 to this subpart, and a description of the method used to calculate the estimate, as reported under § 63.5180(h) and (i).(iv) A record of actions taken to minimize emissions in accordance with § 63.5140(b) and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(d) The owner or operator of any affected BLR source, as well as the owner or operator of any affected WSR source subject to the leak detection and repair program specified in subpart H of this part, shall implement the recordkeeping requirements outlined therein. All records shall be retained for a period of 5 years, in accordance with the requirements of 40 CFR 63.10(b)(1).
-
(b) The owner or operator of any affected BLR source, as well as the owner or operator of any affected WSR source who is subject to the leak detection and repair program specified in subpart H of this part, shall implement the reporting requirements outlined therein. Copies of all reports shall be retained as records for a period of 5 years, in accordance with the requirements of 40 CFR 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious review according to § 63.10(b)(1).
-
(1) Records must be maintained in a form suitable and readily available for expeditious review, according to § 63.10(b)(1). However, electronic recordkeeping and reporting if suitable for the specific case (e.g., by electronic media such as Excel spreadsheet, on CD or hard copy), and when required by this subpart.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) You must maintain all applicable records in such a manner that they can be readily accessed and are suitable for inspection according to § 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(1) You must comply with the general recordkeeping requirements in § 63.10(b)(1).
-
(a) You must maintain all applicable records in such a manner that they can be readily accessed and are suitable for inspection according to § 63.10(b)(1).
-
(1) You must comply with the general recordkeeping requirements in § 63.10(b)(1); and
-
(a) Your records must be in a form suitable and readily available for expeditious review according to § 63.10(b)(1).
-
(h) In accordance with § 63.10(b)(1) of subpart A, the owner or operator of an affected source subject to the provisions of this subpart shall retain all records required by this subpart and subpart A for at least 5 years following their collection.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(iii) The owner or operator must follow the recordkeeping procedures outlined in § 63.10(b)(1) for the DCOT certification, compliance report, data sheets, and all raw unaltered JPEGs used for opacity and certification determination.
-
(a) You must keep your records in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) . Each owner or operator of a source subject to this subpart shall fulfill all recordkeeping requirements specified in § 63.10(a), (b), (d), and (f), except § 63.10(b)(2)(i), (iv) and (v). Each owner or operator must also record and maintain according to § 63.10(b)(1) the information specified in paragraph (a)(1) through (3) of this section.(1) In the event that an affected unit fails to meet an applicable standard, record the number of failures. For each failure record the date, time, and duration of each failure.(2) For each failure to meet an applicable standard, record and retain a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(3) Record actions taken to minimize emissions in accordance with § 63.743(e), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) You must keep your records in a form suitable and readily available for expeditious review, according to the requirements of § 63.10(b)(1).
-
(iii) The owner or operator must follow the recordkeeping procedures outlined in § 63.10(b)(1) for the DCOT certification, compliance report, data sheets, and all raw unaltered JPEGs used for opacity and certification determination.
-
(iii) The owner or operator must follow the recordkeeping procedures outlined in § 63.10(b)(1) for the DCOT certification, compliance report, data sheets, and all raw unaltered JPEGs used for opacity and certification determination.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(1) and (b)(2)(xiv).
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(d) The reference to § 63.103(c)(1) in § 63.104(f)(1) does not apply. For the purposes of this subpart, records must be retained as specified in § 63.10(b)(1).
-
(j) The owner or operator of an affected source shall maintain all records in accordance with the requirements of § 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious inspection and review, according to § 63.10(b)(1).
-
(b) Each owner or operator of an affected source subject to this subpart shall maintain the records specified in paragraphs (b)(1) through (b)(3) of this section on a monthly basis in accordance with the requirements of § 63.10(b)(1) of this part:(1) Records specified in § 63.10(b)(2) of this part, of all measurements needed to demonstrate compliance with this standard, such as continuous emission monitor data, control device and capture system operating parameter data, material usage, HAP usage, volatile matter usage, and solids usage that support data that the source is required to report.(2) Records specified in § 63.10(b)(3) of this part for each applicability determination performed by the owner or operator in accordance with the requirements of § 63.820(a) of this subpart, and(3) Records specified in § 63.10(c) of this part for each continuous monitoring system operated by the owner or operator in accordance with the requirements of § 63.828(a) of this subpart.
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious inspection and review, according to § 63.10(b)(1).
-
(a) You must maintain all applicable records in such a manner that they can be readily accessed and are suitable for inspection according to § 63.10(b)(1).
-
(a) You must keep your records in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
-
(a) Your records must be in a form suitable and readily available for expeditious review, according to § 63.10(b)(1).
Citations to §63.10(b)(2)
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(a) As required by § 63.10(b)(2) of subpart A of this part, the owner or operator shall maintain records for 5 years from the date of each record of:(1) The occurrence and duration of each malfunction of operation (i.e., process equipment);(2) The occurrence and duration of each malfunction of the air pollution control equipment;(3) All maintenance performed on the air pollution control equipment;(4) Actions taken during periods of malfunction to minimize emissions in accordance with § 63.1259(c) and the dates of such actions (including corrective actions to restore malfunctioning process and air pollution control equipment to its normal or usual manner of operation);(5) All required measurements needed to demonstrate compliance with the standard and to support data that the source is required to report, including, but not limited to, performance test measurements (including initial and any subsequent performance tests) and measurements as may be necessary to determine the conditions of the initial test or subsequent tests;(6) All results of initial or subsequent performance tests;(7) If the owner or operator has been granted a waiver from recordkeeping or reporting requirements under § 63.10(f) of subpart A of this part, any information demonstrating whether a source is meeting the requirements for a waiver of recordkeeping or reporting requirements;
-
(2) Records specified in § 63.10(b)(2);
-
(b) The owner or operator shall maintain records for each affected source as required by § 63.10(b)(2) and (b)(3) of this part; and(1) All documentation supporting initial notifications and notifications of compliance status under § 63.9;(2) All records of applicability determination, including supporting analyses; and(3) If the owner or operator has been granted a waiver under § 63.8(f)(6), any information demonstrating whether a source is meeting the requirements for a waiver of recordkeeping or reporting requirements.
-
(2) In addition to the general records required by § 63.10(b)(2) of this part, the owner or operator shall maintain records of the following information:(i) Any bag leak detection system alarms, including the date and time of the alarm, when corrective actions were initiated, the cause of the alarm, an explanation of the corrective actions taken, and when the cause of the alarm was corrected;(ii) ESP parameter value(s) used to monitor ESP performance, including any period when the value(s) deviated from the established limit(s), the date and time of the deviation, when corrective actions were initiated, the cause of the deviation, an explanation of the corrective actions taken, and when the cause of the deviation was corrected;(iii) Air temperature above the molten glass in an uncontrolled cold top electric furnace, including any period when the temperature exceeded 120 °C (250 °F) at a location 46 to 61 centimeters (18 to 24 inches) above the molten glass surface, the date and time of the exceedance, when corrective actions were initiated, the cause of the exceedance, an explanation of the corrective actions taken, and when the cause of the exceedance was corrected;(iv) Uncontrolled glass-melting furnace (that is not a cold top electric furnace) parameter value(s) used to monitor furnace performance, including any period when the value(s) exceeded the established limit(s), the date and time of the exceedance, when corrective actions were initiated, the cause of the exceedance, an explanation of the corrective actions taken, and when the cause of the exceedance was corrected;(v) The formulation of each binder batch and the LOI and density for each product manufactured on a rotary spin manufacturing line or flame attenuation manufacturing line subject to the provisions of this subpart, and the free-formaldehyde and free-phenol contents of each resin shipment received and of each resin used in the binder formulation;(vi) Process parameter level(s) for RS and FA manufacturing lines that use process modifications to comply with the emission limits, including any period when the parameter level(s) deviated from the established limit(s), the date and time of the deviation, when corrective actions were initiated, the cause of the deviation, an explanation of the corrective actions taken, and when the cause of the deviation was corrected;(vii) Scrubber pressure drop, scrubbing liquid flow rate, and any chemical additive (including chemical feed rate to the scrubber), including any period when a parameter level(s) deviated from the established limit(s), the date and time of the deviation, when corrective actions were initiated, the cause of the deviation, an explanation of the corrective actions taken, and when the cause of the deviation was corrected;(viii) Incinerator operating temperature and results of periodic inspection of incinerator components, including any period when the temperature fell below the established average or the inspection identified problems with the incinerator, the date and time of the problem, when corrective actions were initiated, the cause of the problem, an explanation of the corrective actions taken, and when the cause of the problem was corrected;(ix) Glass pull rate, including any period when the pull rate exceeded the average pull rate established during the performance test by more than 20 percent, the date and time of the exceedance, when corrective actions were initiated, the cause of the exceedance, an explanation of the corrective actions taken, and when the cause of the exceedance was corrected.(xi) For each gas-fired glass-melting furnace that uses cullet, records of the daily average cullet percentage, and the 30-day rolling average percent cullet in the materials mix charged to the furnace. The initial daily average should be recorded on the compliance date and the first 30-day rolling average should be calculated 30 days after the compliance date.
-
(2) As required by § 63.10(b)(2), the owner or operator must maintain records for 5 years from the date of each record of:(i) Records of the occurrence and duration of each malfunction of operation (i.e., process equipment) or the air pollution control equipment and monitoring equipment;(ii) Records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.1652(f), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation;(iii) All maintenance performed on the air pollution control equipment;(iv) -(v) [Reserved](vi) All required measurements needed to demonstrate compliance with the standard and to support data that the source is required to report, including, but not limited to, performance test measurements (including initial and any subsequent performance tests) and measurements as may be necessary to determine the conditions of the initial test or subsequent tests;(vii) All results of initial or subsequent performance tests;(viii) If the owner or operator has been granted a waiver from recordkeeping or reporting requirements under § 63.10(f), any information demonstrating whether a source is meeting the requirements for a waiver of recordkeeping or reporting requirements;(ix) If the owner or operator has been granted a waiver from the initial performance test under § 63.7(h), a copy of the full request and the Administrator's approval or disapproval;(x) All documentation supporting initial notifications and notifications of compliance status required by § 63.9; and(xi) As required by § 63.10(b)(3), records of any applicability determination, including supporting analyses.
-
(1) Records specified in § 63.10(b)(2) of all measurements needed to demonstrate compliance with this standard as indicated in Table 2 to subpart JJJJ of part 63, including:(i) Continuous emission monitor data in accordance with the requirements of § 63.3350(d);(ii) Control device and capture system operating parameter data in accordance with the requirements of § 63.3350(c), (e), and (f);(iii) Organic HAP content data for the purpose of demonstrating compliance in accordance with the requirements of § 63.3360(c);(iv) Volatile matter and coating solids content data for the purpose of demonstrating compliance in accordance with the requirements of § 63.3360(d);(v) Overall control efficiency determination using capture efficiency and control device destruction or removal efficiency test results in accordance with the requirements of § 63.3360(e) and (f);(vi) Material usage, organic HAP usage, volatile matter usage, and coating solids usage and compliance demonstrations using these data in accordance with the requirements of § 63.3370(b), (c), and (d); and(vii) Emission factor development calculations and HAP content for coating materials used to develop the emission factor as needed for § 63.3360(g).
-
(2) Records specified in § 63.10(b)(2) of all measurements needed to demonstrate compliance with this subpart, including:(i) Continuous emission monitor data in accordance with § 63.5150(a)(2);(ii) Control device and capture system operating parameter data in accordance with § 63.5150(a)(1), (3), and (4);(iii) Organic HAP content data for the purpose of demonstrating compliance in accordance with § 63.5160(b);(iv) Volatile matter and solids content data for the purpose of demonstrating compliance in accordance with § 63.5160(c);(v) Overall control efficiency determination or alternative outlet HAP concentration using capture efficiency tests and control device destruction or removal efficiency tests in accordance with § 63.5160(d), (e), and (f); and(vi) Material usage, HAP usage, volatile matter usage, and solids usage and compliance demonstrations using these data in accordance with § 63.5170(a), (b), and (d);
-
(3) Records of performance tests, design, and performance evaluations as required in § 63.10(b)(2).
-
(1) Magnetic tape manufacturing operations that are subject to § 63.703(b) and are not at major sources are not subject to §§ 63.6(e), 63.6(f), 63.6(g), 63.6(i)(4), 63.7, 63.8, 63.9 (c) through (h), 63.10(b)(2), 63.10(c), 63.10(d) (2) through (5), 63.10(e), and 63.11 of subpart A.
-
(2) Records specified in § 63.10(b)(2);
-
(1) Records specified in § 63.10(b)(2) of this part, of all measurements needed to demonstrate compliance with this standard, such as continuous emission monitor data, control device and capture system operating parameter data, material usage, HAP usage, volatile matter usage, and solids usage that support data that the source is required to report.
Citations to §63.10(b)(2)(d)(5)
-
(4) Each owner or operator subject to this subpart is not required to comply with § 63.10(b)(2)(i), (b)(2)(iv), (b)(2)(v), and (d)(5).
Citations to §63.10(b)(2)(i)
-
(2) The records specified in § 63.10(b)(2)(i) through (iii) and (xiv) of the General Provisions of this part.
-
(3) Before September 8, 2020, records of the occurrence and duration of each startup, shutdown, or malfunction as required in § 63.10(b)(2)(i).
-
(a) . Each owner or operator of a source subject to this subpart shall fulfill all recordkeeping requirements specified in § 63.10(a), (b), (d), and (f), except § 63.10(b)(2)(i), (iv) and (v). Each owner or operator must also record and maintain according to § 63.10(b)(1) the information specified in paragraph (a)(1) through (3) of this section.(1) In the event that an affected unit fails to meet an applicable standard, record the number of failures. For each failure record the date, time, and duration of each failure.(2) For each failure to meet an applicable standard, record and retain a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(3) Record actions taken to minimize emissions in accordance with § 63.743(e), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(4) Each owner or operator subject to this subpart is not required to comply with § 63.10(b)(2)(i), (b)(2)(iv), (b)(2)(v), and (d)(5).
Citations to §63.10(b)(2)(ii)
-
(2) The records specified in § 63.10(b)(2)(i) through (iii) and (xiv) of the General Provisions of this part.
-
(4) Before September 8, 2020, records of the occurrence and duration of each malfunction of the air pollution control equipment, if applicable, as required in § 63.10(b)(2)(ii).
Citations to §63.10(b)(2)(iii)
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(c) You must maintain files of all information required by this subpart for at least 5 years following the date of each occurrence according to the requirements in § 63.10(b)(1). If you are subject, you must comply with the recordkeeping and reporting requirements of § 63.10(b)(2)(iii) and (vi) through (xiv), and the applicable requirements specified in paragraphs (c)(1) through (11) of this section.(1) For each CMPU subject to this subpart, you must keep the records specified in paragraphs (c)(1)(i) through (viii) of this section.(i) Except as specified in paragraph (c)(9) of this section, records of management practice inspections, repairs, and reasons for any delay of repair, as specified in § 63.11495(a)(5).(ii) Except as specified in paragraph (c)(11) of this section, records of small heat exchange system inspections, demonstrations of indications of leaks that do not constitute leaks, repairs, and reasons for any delay in repair as specified in § 63.11495(b).(iii) If batch process vent emissions are less than 10,000 lb/yr for a CMPU, records of batch process vent emission calculations, as specified in § 63.11496(a)(1), the number of batches operated each month, as specified in § 63.11496(a)(3), and any updated emissions calculations, as specified in § 63.11496(a)(3). Alternatively, keep records of the worst-case processes or organic HAP usage, as specified in § 63.11496(a)(2) and (4), respectively.(iv) Records of all TRE calculations for continuous process vents as specified in § 63.11496(b)(2).(v) Records of metal HAP emission calculations as specified in § 63.11496(f)(1) and (2). If total uncontrolled metal HAP process vent emissions from a CMPU subject to this subpart are estimated to be less than 400 lb/yr, also keep records of either the number of batches per month or operating hours, as specified in § 63.11496(f)(2).(vi) Records identifying wastewater streams and the type of treatment they receive, as specified in table 6 to this subpart.(vii) Before April 1, 2029, records of the date, time, and duration of each malfunction of operation of process equipment, control devices, recovery devices, or continuous monitoring systems used to comply with this subpart that causes a failure to meet a standard. The record must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. After April 1, 2029, for any deviation, records of the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions.(viii) Before April 1, 2029, records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.11495(d), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. After April 1, 2029, for any deviation, records of actions taken to minimize emissions in accordance with § 63.11495(d), and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) For batch process vents subject to table 2 to this subpart and continuous process vents subject to table 3 to this subpart, you must keep records specified in paragraphs (c)(2)(i) or (ii) of this section, as applicable.(i) If you route emissions to a control device other than a flare, keep records of performance tests, if applicable, as specified in § 63.998(a)(2)(ii) and (4), keep records of the monitoring system and the monitored parameters, as specified in § 63.998(b) and (c), and keep records of the closed-vent system, as specified in § 63.998(d)(1). If you use a recovery device to maintain the TRE above 1.0 for a continuous process vent, keep records of monitoring parameters during the TRE index value determination, as specified in § 63.998(a)(3).(ii) If you route emissions to a flare, keep records of the flare compliance assessment, as specified in § 63.998(a)(1)(i), keep records of the pilot flame monitoring, as specified in § 63.998(a)(1)(ii) and (iii), and keep records of the closed-vent system, as specified in § 63.998(d)(1).(3) For metal HAP process vents subject to table 4 to this subpart, you must keep records specified in paragraph (c)(3)(i) or (ii) of this section, as applicable.(i) For a new source using a control device other than a baghouse and for any existing source, maintain a monitoring plan, as specified in § 63.11496(f)(3)(i), and keep records of monitoring results, as specified in § 63.11496(f)(3).(ii) For a new source using a baghouse to control metal HAP emissions, keep a site-specific monitoring plan, as specified in §§ 63.11496(f)(4) and 63.11410(g), and keep records of bag leak detection systems, as specified in §§ 63.11496(f)(4) and 63.11410(g)(4).(4) For each storage tank subject to table 5 to this subpart, you must keep records specified in paragraphs (c)(4)(i) through (vii) of this section, as applicable.(i) Keep records of the vessel dimensions, capacity, and liquid stored, as specified in § 63.1065(a).(ii) Keep records of each inspection of an internal floating roof, as specified in § 63.1065(b)(1).(iii) Keep records of each seal gap measurement for external floating roofs, as specified in § 63.1065(b)(2), and keep records of inspections of external floating roofs, as specified in § 63.1065(b)(1).(iv) If you vent emissions to a control device other than a flare, keep records of the operating plan and measured parameter values, as specified in §§ 63.985(c) and 63.998(d)(2).(v) If you vent emissions to a flare, keep records of all periods of operation during which the flare pilot flame is absent, as specified in §§ 63.987(c) and 63.998(a)(1), and keep records of closed-vent systems, as specified in § 63.998(d)(1).(vi) For periods of planned routine maintenance of a control device, keep records of the day and time at which each maintenance period begins and ends, and keep records of the type of maintenance performed, as specified in § 63.11497(b)(3).(vii) For each pressure vessel subject to the requirements of § 63.11497(f) you must keep records as specified in paragraphs (c)(4)(vii)(A) and (B) of this section.(A) The date of each performance test conducted according to § 63.11497(f)(2).(B) The record of each performance test conducted according to § 63.11497(f)(2), including the following:(1) Date each defect was detected and the instrument reading (in ppmv) during the performance test.(2) Date of the next performance test that shows the instrument reading is less than 500 ppmv and the instrument reading (in ppmv) during the performance test.(3) Start and end dates of each period after the date in paragraph (c)(4)(ix)(B)(1) of this section when the pressure vessel was completely empty.(4) Estimated emissions from each defect.(5) For each wastewater stream subject to item 2 in table 6 to this subpart, keep records of the wastewater stream identification and the disposition of the organic phase(s), as specified in item 2 to table 6 to this subpart.(6) Except as specified in paragraph (c)(11) of this section, for each large heat exchange system subject to table 8 to this subpart, you must keep records of detected leaks; the date the leak was detected; if demonstrated not to be a leak, the basis for that determination; the date of efforts to repair the leak; and the date the leak is repaired, as specified in table 8 to this subpart.(7) You must keep a record of all transferred liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) For continuous process vents subject to table 3 to this subpart, keep records of the occurrence and duration of each startup and shutdown of operation of process equipment, or of air pollution control and monitoring equipment.(9) If you are subject to the equipment leak requirements specified in § 63.11495(a)(6), then you must keep records as specified in paragraphs (c)(9)(i) through (vii) of this section instead of the records specified in paragraph (c)(1)(i) of this section.(i) Keep a list, summary description, or diagram(s) showing the location and identification number of all equipment in organic HAP service at the facility and the information in paragraphs (c)(9)(i)(A) through (D) of this section.(A) Identification of equipment designated as unsafe to monitor, difficult to monitor, unsafe to inspect, difficult to inspect, or unsafe to repair and the plan for monitoring or inspecting this equipment, as applicable.(B) Identification of the equipment in batch process units, for which you do not elect to pressure test the batch product process equipment train.(ii) For leak detection monitoring and inspections required by paragraphs § 63.11495(a)(6) (e.g., monitoring using Method 21 of appendix A-7 to part 60 of this chapter; visible, audible, or olfactory monitoring; closed vent system inspections; and batch process unit monitoring), record the date of the monitoring or inspection and include a statement of whether leaks were detected. If no leaks are detected, records of the monitoring and inspection results are not required.(iii) When each leak is detected as specified in § 63.11495(a)(6), the following information must be recorded:(A) The instrument and the equipment identification number and the operator name, initials, or identification number.(D) Maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A-7 of this chapter after it is successfully repaired or determined to be nonrepairable.(E) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(1) You may develop a written procedure that identifies the conditions that justify a delay of repair. In such cases, reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(2) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked on-site before depletion and the reason for depletion.(iv) For each pressure relief device subject to the provisions in § 63.165(e), you must keep the records specified in paragraphs (c)(9)(iv)(A) through (C) of this section.(A) Records of the prevention measures implemented as required in § 63.165(e)(3)(ii).(C) For each release to the atmosphere, you must keep the records specified in paragraphs (c)(9)(iv)(C)(1) through (4) of this section.(1) The start and end time and date of each pressure release to the atmosphere.(2) Records of any data, assumptions, and calculations used to estimate of the mass quantity of each organic HAP released during the event.(3) Records of the root cause analysis and corrective action analysis conducted as required in § 63.165(e)(3)(iii), including an identification of the affected facility, a statement noting whether the event resulted from the same root cause(s) identified in a previous analysis and either a description of the recommended corrective action(s) or an explanation of why corrective action is not necessary under § 63.165(e)(7)(i).(4) For any corrective action analysis for which implementation of corrective actions are required in § 63.165(e)(7), a description of the corrective action(s) completed within the first 45 days following the discharge and, for action(s) not already completed, a schedule for implementation, including proposed commencement and completion dates.(v) If you own or operate a batch product process and elect to pressure test the batch product process equipment train to demonstrate compliance with § 63.11495(a)(6), you are exempt from the requirements of paragraphs (c)(9)(i) through (iv) of this section. Instead, you must maintain records of the following information:(B) The dates of each pressure test required in § 63.178(b), the test pressure, and the pressure drop observed during the test.(C) When a batch product process equipment train does not pass two consecutive pressure tests, the following information must be recorded:(1) The date of each pressure test and the date of each leak repair attempt.(2) Repair methods applied in each attempt to repair the leak.(3) The reason for the delay of repair.(4) The expected date for delivery of the replacement equipment and the actual date of delivery of the replacement equipment.(5) The date of successful repair.(vi) You must maintain records of the information specified in paragraphs (c)(9)(vi)(A) through (C) of this section for closed vent systems and control devices subject to the provisions of § 63.172. The records specified in paragraph (c)(9)(vi)(A) of this section must be retained for the life of the equipment.(A) The design specifications and performance demonstrations specified in paragraphs (c)(9)(vi)(A)(1) through (4) of this section.(1) Detailed schematics, design specifications of the control device, and piping and instrumentation diagrams.(2) The dates and descriptions of any changes in the design specifications.(3) The flare design (i.e., steam-assisted, air-assisted, or non-assisted) and the results of the compliance demonstration required by subpart SS of this part.(4) A description of the parameter or parameters monitored, as required in § 63.172(e), to ensure that control devices are operated and maintained in conformance with their design and an explanation of why that parameter (or parameters) was selected for the monitoring.(B) Records of operation of closed vent systems and control devices, as specified in paragraphs (c)(9)(vi)(B)(1) through (3) of this section.(1) Dates and durations when the closed vent systems and control devices required in § 63.11495(a)(6) are not operated as designed as indicated by the monitored parameters, including periods when a flare pilot light system does not have a flame.(2) Dates and durations during which the monitoring system or monitoring device is inoperative.(3) Dates and durations of startups and shutdowns of control devices required in § 63.11495(a)(6).(C) Records of inspections of closed vent systems subject to the provisions of § 63.172, as specified in paragraphs (c)(9)(vi)(C)(1) and (2) of this section.(1) For each inspection conducted in accordance with the provisions of § 63.172(f)(1) or (2) during which leaks were detected, the information specified in paragraph (c)(9)(iii) of this section must be recorded.(2) For each flow event from a bypass line subject to the requirements in § 63.172(j), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements in § 63.11495(a)(6), you must include an estimate of the volume of gas, the concentration of organic HAP in the gas, and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(vii) If you choose to comply with the requirements of § 63.179, you must maintain the following records:(C) A description of the system used to create a negative pressure in the enclosure to ensure that all emissions are routed to the control device.(10) For each flow event from a bypass line subject to the requirements in § 63.11495(e), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements specified in §§ 63.11495 through 63.11499, you must include an estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must keep records as specified in § 63.104(f)(3) instead of the heat exchange system records specified in paragraphs (c)(1)(ii) and (6) of this section.
-
(2) The records specified in § 63.10(b)(2)(i) through (iii) and (xiv) of the General Provisions of this part.
-
(5) Records of all maintenance on the air pollution control equipment as required in § 63.10(b)(2)(iii).
-
(2) Records of required maintenance performed on the air pollution control and monitoring equipment as required by § 63.10(b)(2)(iii).
-
(c) In addition to the general records required by § 63.10(b)(2)(iii) and (vi) through (xiv), the owner or operator must maintain records of the information in paragraphs (c)(1) through (8) of this section:(1) Records of black liquor solids firing rates in units of Mg/d or ton/d for all recovery furnaces and semichemical combustion units;(2) Records of CaO production rates in units of Mg/d or ton/d for all lime kilns;(3) Records of parameter monitoring data required under § 63.864, including any period when the operating parameter levels were inconsistent with the levels established during the performance test, with a brief explanation of the cause of the monitoring exceedance, the time the monitoring exceedance occurred, the time corrective action was initiated and completed, and the corrective action taken;(4) Records and documentation of supporting calculations for compliance determinations made under § 63.865(a) through (d);(5) Records of parameter operating limits established for each affected source or process unit;(6) Records certifying that an NDCE recovery furnace equipped with a dry ESP system is used to comply with the gaseous organic HAP standard in § 63.862(c)(1);(7) For the bag leak detection system on the hog fuel dryer fabric filter at Cosmo Specialty Fibers' Cosmopolis, Washington facility (Emission Unit no. HD-14), records of each alarm, the time of the alarm, the time corrective action was initiated and completed, and a brief description of the cause of the alarm and the corrective action taken; and(8) Records demonstrating compliance with the requirement in § 63.864(e)(1) to maintain proper operation of an ESP's AVC.
Citations to §63.10(b)(2)(iv)
-
(a) . Each owner or operator of a source subject to this subpart shall fulfill all recordkeeping requirements specified in § 63.10(a), (b), (d), and (f), except § 63.10(b)(2)(i), (iv) and (v). Each owner or operator must also record and maintain according to § 63.10(b)(1) the information specified in paragraph (a)(1) through (3) of this section.(1) In the event that an affected unit fails to meet an applicable standard, record the number of failures. For each failure record the date, time, and duration of each failure.(2) For each failure to meet an applicable standard, record and retain a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(3) Record actions taken to minimize emissions in accordance with § 63.743(e), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(4) Each owner or operator subject to this subpart is not required to comply with § 63.10(b)(2)(i), (b)(2)(iv), (b)(2)(v), and (d)(5).
Citations to §63.10(b)(2)(ix)
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(c) You must maintain files of all information required by this subpart for at least 5 years following the date of each occurrence according to the requirements in § 63.10(b)(1). If you are subject, you must comply with the recordkeeping and reporting requirements of § 63.10(b)(2)(iii) and (vi) through (xiv), and the applicable requirements specified in paragraphs (c)(1) through (11) of this section.(1) For each CMPU subject to this subpart, you must keep the records specified in paragraphs (c)(1)(i) through (viii) of this section.(i) Except as specified in paragraph (c)(9) of this section, records of management practice inspections, repairs, and reasons for any delay of repair, as specified in § 63.11495(a)(5).(ii) Except as specified in paragraph (c)(11) of this section, records of small heat exchange system inspections, demonstrations of indications of leaks that do not constitute leaks, repairs, and reasons for any delay in repair as specified in § 63.11495(b).(iii) If batch process vent emissions are less than 10,000 lb/yr for a CMPU, records of batch process vent emission calculations, as specified in § 63.11496(a)(1), the number of batches operated each month, as specified in § 63.11496(a)(3), and any updated emissions calculations, as specified in § 63.11496(a)(3). Alternatively, keep records of the worst-case processes or organic HAP usage, as specified in § 63.11496(a)(2) and (4), respectively.(iv) Records of all TRE calculations for continuous process vents as specified in § 63.11496(b)(2).(v) Records of metal HAP emission calculations as specified in § 63.11496(f)(1) and (2). If total uncontrolled metal HAP process vent emissions from a CMPU subject to this subpart are estimated to be less than 400 lb/yr, also keep records of either the number of batches per month or operating hours, as specified in § 63.11496(f)(2).(vi) Records identifying wastewater streams and the type of treatment they receive, as specified in table 6 to this subpart.(vii) Before April 1, 2029, records of the date, time, and duration of each malfunction of operation of process equipment, control devices, recovery devices, or continuous monitoring systems used to comply with this subpart that causes a failure to meet a standard. The record must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. After April 1, 2029, for any deviation, records of the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions.(viii) Before April 1, 2029, records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.11495(d), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. After April 1, 2029, for any deviation, records of actions taken to minimize emissions in accordance with § 63.11495(d), and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) For batch process vents subject to table 2 to this subpart and continuous process vents subject to table 3 to this subpart, you must keep records specified in paragraphs (c)(2)(i) or (ii) of this section, as applicable.(i) If you route emissions to a control device other than a flare, keep records of performance tests, if applicable, as specified in § 63.998(a)(2)(ii) and (4), keep records of the monitoring system and the monitored parameters, as specified in § 63.998(b) and (c), and keep records of the closed-vent system, as specified in § 63.998(d)(1). If you use a recovery device to maintain the TRE above 1.0 for a continuous process vent, keep records of monitoring parameters during the TRE index value determination, as specified in § 63.998(a)(3).(ii) If you route emissions to a flare, keep records of the flare compliance assessment, as specified in § 63.998(a)(1)(i), keep records of the pilot flame monitoring, as specified in § 63.998(a)(1)(ii) and (iii), and keep records of the closed-vent system, as specified in § 63.998(d)(1).(3) For metal HAP process vents subject to table 4 to this subpart, you must keep records specified in paragraph (c)(3)(i) or (ii) of this section, as applicable.(i) For a new source using a control device other than a baghouse and for any existing source, maintain a monitoring plan, as specified in § 63.11496(f)(3)(i), and keep records of monitoring results, as specified in § 63.11496(f)(3).(ii) For a new source using a baghouse to control metal HAP emissions, keep a site-specific monitoring plan, as specified in §§ 63.11496(f)(4) and 63.11410(g), and keep records of bag leak detection systems, as specified in §§ 63.11496(f)(4) and 63.11410(g)(4).(4) For each storage tank subject to table 5 to this subpart, you must keep records specified in paragraphs (c)(4)(i) through (vii) of this section, as applicable.(i) Keep records of the vessel dimensions, capacity, and liquid stored, as specified in § 63.1065(a).(ii) Keep records of each inspection of an internal floating roof, as specified in § 63.1065(b)(1).(iii) Keep records of each seal gap measurement for external floating roofs, as specified in § 63.1065(b)(2), and keep records of inspections of external floating roofs, as specified in § 63.1065(b)(1).(iv) If you vent emissions to a control device other than a flare, keep records of the operating plan and measured parameter values, as specified in §§ 63.985(c) and 63.998(d)(2).(v) If you vent emissions to a flare, keep records of all periods of operation during which the flare pilot flame is absent, as specified in §§ 63.987(c) and 63.998(a)(1), and keep records of closed-vent systems, as specified in § 63.998(d)(1).(vi) For periods of planned routine maintenance of a control device, keep records of the day and time at which each maintenance period begins and ends, and keep records of the type of maintenance performed, as specified in § 63.11497(b)(3).(vii) For each pressure vessel subject to the requirements of § 63.11497(f) you must keep records as specified in paragraphs (c)(4)(vii)(A) and (B) of this section.(A) The date of each performance test conducted according to § 63.11497(f)(2).(B) The record of each performance test conducted according to § 63.11497(f)(2), including the following:(1) Date each defect was detected and the instrument reading (in ppmv) during the performance test.(2) Date of the next performance test that shows the instrument reading is less than 500 ppmv and the instrument reading (in ppmv) during the performance test.(3) Start and end dates of each period after the date in paragraph (c)(4)(ix)(B)(1) of this section when the pressure vessel was completely empty.(4) Estimated emissions from each defect.(5) For each wastewater stream subject to item 2 in table 6 to this subpart, keep records of the wastewater stream identification and the disposition of the organic phase(s), as specified in item 2 to table 6 to this subpart.(6) Except as specified in paragraph (c)(11) of this section, for each large heat exchange system subject to table 8 to this subpart, you must keep records of detected leaks; the date the leak was detected; if demonstrated not to be a leak, the basis for that determination; the date of efforts to repair the leak; and the date the leak is repaired, as specified in table 8 to this subpart.(7) You must keep a record of all transferred liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) For continuous process vents subject to table 3 to this subpart, keep records of the occurrence and duration of each startup and shutdown of operation of process equipment, or of air pollution control and monitoring equipment.(9) If you are subject to the equipment leak requirements specified in § 63.11495(a)(6), then you must keep records as specified in paragraphs (c)(9)(i) through (vii) of this section instead of the records specified in paragraph (c)(1)(i) of this section.(i) Keep a list, summary description, or diagram(s) showing the location and identification number of all equipment in organic HAP service at the facility and the information in paragraphs (c)(9)(i)(A) through (D) of this section.(A) Identification of equipment designated as unsafe to monitor, difficult to monitor, unsafe to inspect, difficult to inspect, or unsafe to repair and the plan for monitoring or inspecting this equipment, as applicable.(B) Identification of the equipment in batch process units, for which you do not elect to pressure test the batch product process equipment train.(ii) For leak detection monitoring and inspections required by paragraphs § 63.11495(a)(6) (e.g., monitoring using Method 21 of appendix A-7 to part 60 of this chapter; visible, audible, or olfactory monitoring; closed vent system inspections; and batch process unit monitoring), record the date of the monitoring or inspection and include a statement of whether leaks were detected. If no leaks are detected, records of the monitoring and inspection results are not required.(iii) When each leak is detected as specified in § 63.11495(a)(6), the following information must be recorded:(A) The instrument and the equipment identification number and the operator name, initials, or identification number.(D) Maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A-7 of this chapter after it is successfully repaired or determined to be nonrepairable.(E) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(1) You may develop a written procedure that identifies the conditions that justify a delay of repair. In such cases, reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(2) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked on-site before depletion and the reason for depletion.(iv) For each pressure relief device subject to the provisions in § 63.165(e), you must keep the records specified in paragraphs (c)(9)(iv)(A) through (C) of this section.(A) Records of the prevention measures implemented as required in § 63.165(e)(3)(ii).(C) For each release to the atmosphere, you must keep the records specified in paragraphs (c)(9)(iv)(C)(1) through (4) of this section.(1) The start and end time and date of each pressure release to the atmosphere.(2) Records of any data, assumptions, and calculations used to estimate of the mass quantity of each organic HAP released during the event.(3) Records of the root cause analysis and corrective action analysis conducted as required in § 63.165(e)(3)(iii), including an identification of the affected facility, a statement noting whether the event resulted from the same root cause(s) identified in a previous analysis and either a description of the recommended corrective action(s) or an explanation of why corrective action is not necessary under § 63.165(e)(7)(i).(4) For any corrective action analysis for which implementation of corrective actions are required in § 63.165(e)(7), a description of the corrective action(s) completed within the first 45 days following the discharge and, for action(s) not already completed, a schedule for implementation, including proposed commencement and completion dates.(v) If you own or operate a batch product process and elect to pressure test the batch product process equipment train to demonstrate compliance with § 63.11495(a)(6), you are exempt from the requirements of paragraphs (c)(9)(i) through (iv) of this section. Instead, you must maintain records of the following information:(B) The dates of each pressure test required in § 63.178(b), the test pressure, and the pressure drop observed during the test.(C) When a batch product process equipment train does not pass two consecutive pressure tests, the following information must be recorded:(1) The date of each pressure test and the date of each leak repair attempt.(2) Repair methods applied in each attempt to repair the leak.(3) The reason for the delay of repair.(4) The expected date for delivery of the replacement equipment and the actual date of delivery of the replacement equipment.(5) The date of successful repair.(vi) You must maintain records of the information specified in paragraphs (c)(9)(vi)(A) through (C) of this section for closed vent systems and control devices subject to the provisions of § 63.172. The records specified in paragraph (c)(9)(vi)(A) of this section must be retained for the life of the equipment.(A) The design specifications and performance demonstrations specified in paragraphs (c)(9)(vi)(A)(1) through (4) of this section.(1) Detailed schematics, design specifications of the control device, and piping and instrumentation diagrams.(2) The dates and descriptions of any changes in the design specifications.(3) The flare design (i.e., steam-assisted, air-assisted, or non-assisted) and the results of the compliance demonstration required by subpart SS of this part.(4) A description of the parameter or parameters monitored, as required in § 63.172(e), to ensure that control devices are operated and maintained in conformance with their design and an explanation of why that parameter (or parameters) was selected for the monitoring.(B) Records of operation of closed vent systems and control devices, as specified in paragraphs (c)(9)(vi)(B)(1) through (3) of this section.(1) Dates and durations when the closed vent systems and control devices required in § 63.11495(a)(6) are not operated as designed as indicated by the monitored parameters, including periods when a flare pilot light system does not have a flame.(2) Dates and durations during which the monitoring system or monitoring device is inoperative.(3) Dates and durations of startups and shutdowns of control devices required in § 63.11495(a)(6).(C) Records of inspections of closed vent systems subject to the provisions of § 63.172, as specified in paragraphs (c)(9)(vi)(C)(1) and (2) of this section.(1) For each inspection conducted in accordance with the provisions of § 63.172(f)(1) or (2) during which leaks were detected, the information specified in paragraph (c)(9)(iii) of this section must be recorded.(2) For each flow event from a bypass line subject to the requirements in § 63.172(j), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements in § 63.11495(a)(6), you must include an estimate of the volume of gas, the concentration of organic HAP in the gas, and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(vii) If you choose to comply with the requirements of § 63.179, you must maintain the following records:(C) A description of the system used to create a negative pressure in the enclosure to ensure that all emissions are routed to the control device.(10) For each flow event from a bypass line subject to the requirements in § 63.11495(e), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements specified in §§ 63.11495 through 63.11499, you must include an estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must keep records as specified in § 63.104(f)(3) instead of the heat exchange system records specified in paragraphs (c)(1)(ii) and (6) of this section.
-
(i) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(3) Records of performance tests and performance evaluations as required in § 63.10(b)(2)(viii) and (ix).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vii) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi) that apply to your continuous monitoring system.
-
(c) In addition to the general records required by § 63.10(b)(2)(iii) and (vi) through (xiv), the owner or operator must maintain records of the information in paragraphs (c)(1) through (8) of this section:(1) Records of black liquor solids firing rates in units of Mg/d or ton/d for all recovery furnaces and semichemical combustion units;(2) Records of CaO production rates in units of Mg/d or ton/d for all lime kilns;(3) Records of parameter monitoring data required under § 63.864, including any period when the operating parameter levels were inconsistent with the levels established during the performance test, with a brief explanation of the cause of the monitoring exceedance, the time the monitoring exceedance occurred, the time corrective action was initiated and completed, and the corrective action taken;(4) Records and documentation of supporting calculations for compliance determinations made under § 63.865(a) through (d);(5) Records of parameter operating limits established for each affected source or process unit;(6) Records certifying that an NDCE recovery furnace equipped with a dry ESP system is used to comply with the gaseous organic HAP standard in § 63.862(c)(1);(7) For the bag leak detection system on the hog fuel dryer fabric filter at Cosmo Specialty Fibers' Cosmopolis, Washington facility (Emission Unit no. HD-14), records of each alarm, the time of the alarm, the time corrective action was initiated and completed, and a brief description of the cause of the alarm and the corrective action taken; and(8) Records demonstrating compliance with the requirement in § 63.864(e)(1) to maintain proper operation of an ESP's AVC.
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
Citations to §63.10(b)(2)(v)
-
(a) . Each owner or operator of a source subject to this subpart shall fulfill all recordkeeping requirements specified in § 63.10(a), (b), (d), and (f), except § 63.10(b)(2)(i), (iv) and (v). Each owner or operator must also record and maintain according to § 63.10(b)(1) the information specified in paragraph (a)(1) through (3) of this section.(1) In the event that an affected unit fails to meet an applicable standard, record the number of failures. For each failure record the date, time, and duration of each failure.(2) For each failure to meet an applicable standard, record and retain a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(3) Record actions taken to minimize emissions in accordance with § 63.743(e), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(4) Each owner or operator subject to this subpart is not required to comply with § 63.10(b)(2)(i), (b)(2)(iv), (b)(2)(v), and (d)(5).
Citations to §63.10(b)(2)(vi)
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(b) The following provisions of subpart A of this part (General Provisions), §§ 63.1 through 63.5, and §§ 63.12 through 63.15, apply to owners or operators of affected sources subject to this subpart. For sources that reclassify from major source to area source status, the applicable provisions of § 63.9(j) and (k) apply. Beginning no later than the compliance dates specified in § 63.1102(c), for ethylene production affected sources, §§ 63.7(a)(4), (c), (e)(4), and (g)(2), 63.9(k), and 63.10(b)(2)(vi) also apply.
-
(15) Records described in § 63.10(b)(2)(vi).
-
(c) You must maintain files of all information required by this subpart for at least 5 years following the date of each occurrence according to the requirements in § 63.10(b)(1). If you are subject, you must comply with the recordkeeping and reporting requirements of § 63.10(b)(2)(iii) and (vi) through (xiv), and the applicable requirements specified in paragraphs (c)(1) through (11) of this section.(1) For each CMPU subject to this subpart, you must keep the records specified in paragraphs (c)(1)(i) through (viii) of this section.(i) Except as specified in paragraph (c)(9) of this section, records of management practice inspections, repairs, and reasons for any delay of repair, as specified in § 63.11495(a)(5).(ii) Except as specified in paragraph (c)(11) of this section, records of small heat exchange system inspections, demonstrations of indications of leaks that do not constitute leaks, repairs, and reasons for any delay in repair as specified in § 63.11495(b).(iii) If batch process vent emissions are less than 10,000 lb/yr for a CMPU, records of batch process vent emission calculations, as specified in § 63.11496(a)(1), the number of batches operated each month, as specified in § 63.11496(a)(3), and any updated emissions calculations, as specified in § 63.11496(a)(3). Alternatively, keep records of the worst-case processes or organic HAP usage, as specified in § 63.11496(a)(2) and (4), respectively.(iv) Records of all TRE calculations for continuous process vents as specified in § 63.11496(b)(2).(v) Records of metal HAP emission calculations as specified in § 63.11496(f)(1) and (2). If total uncontrolled metal HAP process vent emissions from a CMPU subject to this subpart are estimated to be less than 400 lb/yr, also keep records of either the number of batches per month or operating hours, as specified in § 63.11496(f)(2).(vi) Records identifying wastewater streams and the type of treatment they receive, as specified in table 6 to this subpart.(vii) Before April 1, 2029, records of the date, time, and duration of each malfunction of operation of process equipment, control devices, recovery devices, or continuous monitoring systems used to comply with this subpart that causes a failure to meet a standard. The record must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. After April 1, 2029, for any deviation, records of the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions.(viii) Before April 1, 2029, records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.11495(d), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. After April 1, 2029, for any deviation, records of actions taken to minimize emissions in accordance with § 63.11495(d), and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) For batch process vents subject to table 2 to this subpart and continuous process vents subject to table 3 to this subpart, you must keep records specified in paragraphs (c)(2)(i) or (ii) of this section, as applicable.(i) If you route emissions to a control device other than a flare, keep records of performance tests, if applicable, as specified in § 63.998(a)(2)(ii) and (4), keep records of the monitoring system and the monitored parameters, as specified in § 63.998(b) and (c), and keep records of the closed-vent system, as specified in § 63.998(d)(1). If you use a recovery device to maintain the TRE above 1.0 for a continuous process vent, keep records of monitoring parameters during the TRE index value determination, as specified in § 63.998(a)(3).(ii) If you route emissions to a flare, keep records of the flare compliance assessment, as specified in § 63.998(a)(1)(i), keep records of the pilot flame monitoring, as specified in § 63.998(a)(1)(ii) and (iii), and keep records of the closed-vent system, as specified in § 63.998(d)(1).(3) For metal HAP process vents subject to table 4 to this subpart, you must keep records specified in paragraph (c)(3)(i) or (ii) of this section, as applicable.(i) For a new source using a control device other than a baghouse and for any existing source, maintain a monitoring plan, as specified in § 63.11496(f)(3)(i), and keep records of monitoring results, as specified in § 63.11496(f)(3).(ii) For a new source using a baghouse to control metal HAP emissions, keep a site-specific monitoring plan, as specified in §§ 63.11496(f)(4) and 63.11410(g), and keep records of bag leak detection systems, as specified in §§ 63.11496(f)(4) and 63.11410(g)(4).(4) For each storage tank subject to table 5 to this subpart, you must keep records specified in paragraphs (c)(4)(i) through (vii) of this section, as applicable.(i) Keep records of the vessel dimensions, capacity, and liquid stored, as specified in § 63.1065(a).(ii) Keep records of each inspection of an internal floating roof, as specified in § 63.1065(b)(1).(iii) Keep records of each seal gap measurement for external floating roofs, as specified in § 63.1065(b)(2), and keep records of inspections of external floating roofs, as specified in § 63.1065(b)(1).(iv) If you vent emissions to a control device other than a flare, keep records of the operating plan and measured parameter values, as specified in §§ 63.985(c) and 63.998(d)(2).(v) If you vent emissions to a flare, keep records of all periods of operation during which the flare pilot flame is absent, as specified in §§ 63.987(c) and 63.998(a)(1), and keep records of closed-vent systems, as specified in § 63.998(d)(1).(vi) For periods of planned routine maintenance of a control device, keep records of the day and time at which each maintenance period begins and ends, and keep records of the type of maintenance performed, as specified in § 63.11497(b)(3).(vii) For each pressure vessel subject to the requirements of § 63.11497(f) you must keep records as specified in paragraphs (c)(4)(vii)(A) and (B) of this section.(A) The date of each performance test conducted according to § 63.11497(f)(2).(B) The record of each performance test conducted according to § 63.11497(f)(2), including the following:(1) Date each defect was detected and the instrument reading (in ppmv) during the performance test.(2) Date of the next performance test that shows the instrument reading is less than 500 ppmv and the instrument reading (in ppmv) during the performance test.(3) Start and end dates of each period after the date in paragraph (c)(4)(ix)(B)(1) of this section when the pressure vessel was completely empty.(4) Estimated emissions from each defect.(5) For each wastewater stream subject to item 2 in table 6 to this subpart, keep records of the wastewater stream identification and the disposition of the organic phase(s), as specified in item 2 to table 6 to this subpart.(6) Except as specified in paragraph (c)(11) of this section, for each large heat exchange system subject to table 8 to this subpart, you must keep records of detected leaks; the date the leak was detected; if demonstrated not to be a leak, the basis for that determination; the date of efforts to repair the leak; and the date the leak is repaired, as specified in table 8 to this subpart.(7) You must keep a record of all transferred liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) For continuous process vents subject to table 3 to this subpart, keep records of the occurrence and duration of each startup and shutdown of operation of process equipment, or of air pollution control and monitoring equipment.(9) If you are subject to the equipment leak requirements specified in § 63.11495(a)(6), then you must keep records as specified in paragraphs (c)(9)(i) through (vii) of this section instead of the records specified in paragraph (c)(1)(i) of this section.(i) Keep a list, summary description, or diagram(s) showing the location and identification number of all equipment in organic HAP service at the facility and the information in paragraphs (c)(9)(i)(A) through (D) of this section.(A) Identification of equipment designated as unsafe to monitor, difficult to monitor, unsafe to inspect, difficult to inspect, or unsafe to repair and the plan for monitoring or inspecting this equipment, as applicable.(B) Identification of the equipment in batch process units, for which you do not elect to pressure test the batch product process equipment train.(ii) For leak detection monitoring and inspections required by paragraphs § 63.11495(a)(6) (e.g., monitoring using Method 21 of appendix A-7 to part 60 of this chapter; visible, audible, or olfactory monitoring; closed vent system inspections; and batch process unit monitoring), record the date of the monitoring or inspection and include a statement of whether leaks were detected. If no leaks are detected, records of the monitoring and inspection results are not required.(iii) When each leak is detected as specified in § 63.11495(a)(6), the following information must be recorded:(A) The instrument and the equipment identification number and the operator name, initials, or identification number.(D) Maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A-7 of this chapter after it is successfully repaired or determined to be nonrepairable.(E) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(1) You may develop a written procedure that identifies the conditions that justify a delay of repair. In such cases, reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(2) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked on-site before depletion and the reason for depletion.(iv) For each pressure relief device subject to the provisions in § 63.165(e), you must keep the records specified in paragraphs (c)(9)(iv)(A) through (C) of this section.(A) Records of the prevention measures implemented as required in § 63.165(e)(3)(ii).(C) For each release to the atmosphere, you must keep the records specified in paragraphs (c)(9)(iv)(C)(1) through (4) of this section.(1) The start and end time and date of each pressure release to the atmosphere.(2) Records of any data, assumptions, and calculations used to estimate of the mass quantity of each organic HAP released during the event.(3) Records of the root cause analysis and corrective action analysis conducted as required in § 63.165(e)(3)(iii), including an identification of the affected facility, a statement noting whether the event resulted from the same root cause(s) identified in a previous analysis and either a description of the recommended corrective action(s) or an explanation of why corrective action is not necessary under § 63.165(e)(7)(i).(4) For any corrective action analysis for which implementation of corrective actions are required in § 63.165(e)(7), a description of the corrective action(s) completed within the first 45 days following the discharge and, for action(s) not already completed, a schedule for implementation, including proposed commencement and completion dates.(v) If you own or operate a batch product process and elect to pressure test the batch product process equipment train to demonstrate compliance with § 63.11495(a)(6), you are exempt from the requirements of paragraphs (c)(9)(i) through (iv) of this section. Instead, you must maintain records of the following information:(B) The dates of each pressure test required in § 63.178(b), the test pressure, and the pressure drop observed during the test.(C) When a batch product process equipment train does not pass two consecutive pressure tests, the following information must be recorded:(1) The date of each pressure test and the date of each leak repair attempt.(2) Repair methods applied in each attempt to repair the leak.(3) The reason for the delay of repair.(4) The expected date for delivery of the replacement equipment and the actual date of delivery of the replacement equipment.(5) The date of successful repair.(vi) You must maintain records of the information specified in paragraphs (c)(9)(vi)(A) through (C) of this section for closed vent systems and control devices subject to the provisions of § 63.172. The records specified in paragraph (c)(9)(vi)(A) of this section must be retained for the life of the equipment.(A) The design specifications and performance demonstrations specified in paragraphs (c)(9)(vi)(A)(1) through (4) of this section.(1) Detailed schematics, design specifications of the control device, and piping and instrumentation diagrams.(2) The dates and descriptions of any changes in the design specifications.(3) The flare design (i.e., steam-assisted, air-assisted, or non-assisted) and the results of the compliance demonstration required by subpart SS of this part.(4) A description of the parameter or parameters monitored, as required in § 63.172(e), to ensure that control devices are operated and maintained in conformance with their design and an explanation of why that parameter (or parameters) was selected for the monitoring.(B) Records of operation of closed vent systems and control devices, as specified in paragraphs (c)(9)(vi)(B)(1) through (3) of this section.(1) Dates and durations when the closed vent systems and control devices required in § 63.11495(a)(6) are not operated as designed as indicated by the monitored parameters, including periods when a flare pilot light system does not have a flame.(2) Dates and durations during which the monitoring system or monitoring device is inoperative.(3) Dates and durations of startups and shutdowns of control devices required in § 63.11495(a)(6).(C) Records of inspections of closed vent systems subject to the provisions of § 63.172, as specified in paragraphs (c)(9)(vi)(C)(1) and (2) of this section.(1) For each inspection conducted in accordance with the provisions of § 63.172(f)(1) or (2) during which leaks were detected, the information specified in paragraph (c)(9)(iii) of this section must be recorded.(2) For each flow event from a bypass line subject to the requirements in § 63.172(j), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements in § 63.11495(a)(6), you must include an estimate of the volume of gas, the concentration of organic HAP in the gas, and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(vii) If you choose to comply with the requirements of § 63.179, you must maintain the following records:(C) A description of the system used to create a negative pressure in the enclosure to ensure that all emissions are routed to the control device.(10) For each flow event from a bypass line subject to the requirements in § 63.11495(e), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements specified in §§ 63.11495 through 63.11499, you must include an estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must keep records as specified in § 63.104(f)(3) instead of the heat exchange system records specified in paragraphs (c)(1)(ii) and (6) of this section.
-
(i) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi), (vii), (x), and (xi). The CEMS must allow the amount of excess zero (low-level) and high-level calibration drift measured at the interval checks to be quantified and recorded.
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(10) Records described in § 63.10(b)(2)(vi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi) that apply to your continuous monitoring system.
-
(c) In addition to the general records required by § 63.10(b)(2)(iii) and (vi) through (xiv), the owner or operator must maintain records of the information in paragraphs (c)(1) through (8) of this section:(1) Records of black liquor solids firing rates in units of Mg/d or ton/d for all recovery furnaces and semichemical combustion units;(2) Records of CaO production rates in units of Mg/d or ton/d for all lime kilns;(3) Records of parameter monitoring data required under § 63.864, including any period when the operating parameter levels were inconsistent with the levels established during the performance test, with a brief explanation of the cause of the monitoring exceedance, the time the monitoring exceedance occurred, the time corrective action was initiated and completed, and the corrective action taken;(4) Records and documentation of supporting calculations for compliance determinations made under § 63.865(a) through (d);(5) Records of parameter operating limits established for each affected source or process unit;(6) Records certifying that an NDCE recovery furnace equipped with a dry ESP system is used to comply with the gaseous organic HAP standard in § 63.862(c)(1);(7) For the bag leak detection system on the hog fuel dryer fabric filter at Cosmo Specialty Fibers' Cosmopolis, Washington facility (Emission Unit no. HD-14), records of each alarm, the time of the alarm, the time corrective action was initiated and completed, and a brief description of the cause of the alarm and the corrective action taken; and(8) Records demonstrating compliance with the requirement in § 63.864(e)(1) to maintain proper operation of an ESP's AVC.
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
Citations to §63.10(b)(2)(vii)
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(2) Records of all required measurements needed to document compliance with management practices as required in § 63.10(b)(2)(vii), including records of monitoring and inspection data required by § 63.11440.
-
(c) You must maintain files of all information required by this subpart for at least 5 years following the date of each occurrence according to the requirements in § 63.10(b)(1). If you are subject, you must comply with the recordkeeping and reporting requirements of § 63.10(b)(2)(iii) and (vi) through (xiv), and the applicable requirements specified in paragraphs (c)(1) through (11) of this section.(1) For each CMPU subject to this subpart, you must keep the records specified in paragraphs (c)(1)(i) through (viii) of this section.(i) Except as specified in paragraph (c)(9) of this section, records of management practice inspections, repairs, and reasons for any delay of repair, as specified in § 63.11495(a)(5).(ii) Except as specified in paragraph (c)(11) of this section, records of small heat exchange system inspections, demonstrations of indications of leaks that do not constitute leaks, repairs, and reasons for any delay in repair as specified in § 63.11495(b).(iii) If batch process vent emissions are less than 10,000 lb/yr for a CMPU, records of batch process vent emission calculations, as specified in § 63.11496(a)(1), the number of batches operated each month, as specified in § 63.11496(a)(3), and any updated emissions calculations, as specified in § 63.11496(a)(3). Alternatively, keep records of the worst-case processes or organic HAP usage, as specified in § 63.11496(a)(2) and (4), respectively.(iv) Records of all TRE calculations for continuous process vents as specified in § 63.11496(b)(2).(v) Records of metal HAP emission calculations as specified in § 63.11496(f)(1) and (2). If total uncontrolled metal HAP process vent emissions from a CMPU subject to this subpart are estimated to be less than 400 lb/yr, also keep records of either the number of batches per month or operating hours, as specified in § 63.11496(f)(2).(vi) Records identifying wastewater streams and the type of treatment they receive, as specified in table 6 to this subpart.(vii) Before April 1, 2029, records of the date, time, and duration of each malfunction of operation of process equipment, control devices, recovery devices, or continuous monitoring systems used to comply with this subpart that causes a failure to meet a standard. The record must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. After April 1, 2029, for any deviation, records of the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions.(viii) Before April 1, 2029, records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.11495(d), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. After April 1, 2029, for any deviation, records of actions taken to minimize emissions in accordance with § 63.11495(d), and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) For batch process vents subject to table 2 to this subpart and continuous process vents subject to table 3 to this subpart, you must keep records specified in paragraphs (c)(2)(i) or (ii) of this section, as applicable.(i) If you route emissions to a control device other than a flare, keep records of performance tests, if applicable, as specified in § 63.998(a)(2)(ii) and (4), keep records of the monitoring system and the monitored parameters, as specified in § 63.998(b) and (c), and keep records of the closed-vent system, as specified in § 63.998(d)(1). If you use a recovery device to maintain the TRE above 1.0 for a continuous process vent, keep records of monitoring parameters during the TRE index value determination, as specified in § 63.998(a)(3).(ii) If you route emissions to a flare, keep records of the flare compliance assessment, as specified in § 63.998(a)(1)(i), keep records of the pilot flame monitoring, as specified in § 63.998(a)(1)(ii) and (iii), and keep records of the closed-vent system, as specified in § 63.998(d)(1).(3) For metal HAP process vents subject to table 4 to this subpart, you must keep records specified in paragraph (c)(3)(i) or (ii) of this section, as applicable.(i) For a new source using a control device other than a baghouse and for any existing source, maintain a monitoring plan, as specified in § 63.11496(f)(3)(i), and keep records of monitoring results, as specified in § 63.11496(f)(3).(ii) For a new source using a baghouse to control metal HAP emissions, keep a site-specific monitoring plan, as specified in §§ 63.11496(f)(4) and 63.11410(g), and keep records of bag leak detection systems, as specified in §§ 63.11496(f)(4) and 63.11410(g)(4).(4) For each storage tank subject to table 5 to this subpart, you must keep records specified in paragraphs (c)(4)(i) through (vii) of this section, as applicable.(i) Keep records of the vessel dimensions, capacity, and liquid stored, as specified in § 63.1065(a).(ii) Keep records of each inspection of an internal floating roof, as specified in § 63.1065(b)(1).(iii) Keep records of each seal gap measurement for external floating roofs, as specified in § 63.1065(b)(2), and keep records of inspections of external floating roofs, as specified in § 63.1065(b)(1).(iv) If you vent emissions to a control device other than a flare, keep records of the operating plan and measured parameter values, as specified in §§ 63.985(c) and 63.998(d)(2).(v) If you vent emissions to a flare, keep records of all periods of operation during which the flare pilot flame is absent, as specified in §§ 63.987(c) and 63.998(a)(1), and keep records of closed-vent systems, as specified in § 63.998(d)(1).(vi) For periods of planned routine maintenance of a control device, keep records of the day and time at which each maintenance period begins and ends, and keep records of the type of maintenance performed, as specified in § 63.11497(b)(3).(vii) For each pressure vessel subject to the requirements of § 63.11497(f) you must keep records as specified in paragraphs (c)(4)(vii)(A) and (B) of this section.(A) The date of each performance test conducted according to § 63.11497(f)(2).(B) The record of each performance test conducted according to § 63.11497(f)(2), including the following:(1) Date each defect was detected and the instrument reading (in ppmv) during the performance test.(2) Date of the next performance test that shows the instrument reading is less than 500 ppmv and the instrument reading (in ppmv) during the performance test.(3) Start and end dates of each period after the date in paragraph (c)(4)(ix)(B)(1) of this section when the pressure vessel was completely empty.(4) Estimated emissions from each defect.(5) For each wastewater stream subject to item 2 in table 6 to this subpart, keep records of the wastewater stream identification and the disposition of the organic phase(s), as specified in item 2 to table 6 to this subpart.(6) Except as specified in paragraph (c)(11) of this section, for each large heat exchange system subject to table 8 to this subpart, you must keep records of detected leaks; the date the leak was detected; if demonstrated not to be a leak, the basis for that determination; the date of efforts to repair the leak; and the date the leak is repaired, as specified in table 8 to this subpart.(7) You must keep a record of all transferred liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) For continuous process vents subject to table 3 to this subpart, keep records of the occurrence and duration of each startup and shutdown of operation of process equipment, or of air pollution control and monitoring equipment.(9) If you are subject to the equipment leak requirements specified in § 63.11495(a)(6), then you must keep records as specified in paragraphs (c)(9)(i) through (vii) of this section instead of the records specified in paragraph (c)(1)(i) of this section.(i) Keep a list, summary description, or diagram(s) showing the location and identification number of all equipment in organic HAP service at the facility and the information in paragraphs (c)(9)(i)(A) through (D) of this section.(A) Identification of equipment designated as unsafe to monitor, difficult to monitor, unsafe to inspect, difficult to inspect, or unsafe to repair and the plan for monitoring or inspecting this equipment, as applicable.(B) Identification of the equipment in batch process units, for which you do not elect to pressure test the batch product process equipment train.(ii) For leak detection monitoring and inspections required by paragraphs § 63.11495(a)(6) (e.g., monitoring using Method 21 of appendix A-7 to part 60 of this chapter; visible, audible, or olfactory monitoring; closed vent system inspections; and batch process unit monitoring), record the date of the monitoring or inspection and include a statement of whether leaks were detected. If no leaks are detected, records of the monitoring and inspection results are not required.(iii) When each leak is detected as specified in § 63.11495(a)(6), the following information must be recorded:(A) The instrument and the equipment identification number and the operator name, initials, or identification number.(D) Maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A-7 of this chapter after it is successfully repaired or determined to be nonrepairable.(E) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(1) You may develop a written procedure that identifies the conditions that justify a delay of repair. In such cases, reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(2) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked on-site before depletion and the reason for depletion.(iv) For each pressure relief device subject to the provisions in § 63.165(e), you must keep the records specified in paragraphs (c)(9)(iv)(A) through (C) of this section.(A) Records of the prevention measures implemented as required in § 63.165(e)(3)(ii).(C) For each release to the atmosphere, you must keep the records specified in paragraphs (c)(9)(iv)(C)(1) through (4) of this section.(1) The start and end time and date of each pressure release to the atmosphere.(2) Records of any data, assumptions, and calculations used to estimate of the mass quantity of each organic HAP released during the event.(3) Records of the root cause analysis and corrective action analysis conducted as required in § 63.165(e)(3)(iii), including an identification of the affected facility, a statement noting whether the event resulted from the same root cause(s) identified in a previous analysis and either a description of the recommended corrective action(s) or an explanation of why corrective action is not necessary under § 63.165(e)(7)(i).(4) For any corrective action analysis for which implementation of corrective actions are required in § 63.165(e)(7), a description of the corrective action(s) completed within the first 45 days following the discharge and, for action(s) not already completed, a schedule for implementation, including proposed commencement and completion dates.(v) If you own or operate a batch product process and elect to pressure test the batch product process equipment train to demonstrate compliance with § 63.11495(a)(6), you are exempt from the requirements of paragraphs (c)(9)(i) through (iv) of this section. Instead, you must maintain records of the following information:(B) The dates of each pressure test required in § 63.178(b), the test pressure, and the pressure drop observed during the test.(C) When a batch product process equipment train does not pass two consecutive pressure tests, the following information must be recorded:(1) The date of each pressure test and the date of each leak repair attempt.(2) Repair methods applied in each attempt to repair the leak.(3) The reason for the delay of repair.(4) The expected date for delivery of the replacement equipment and the actual date of delivery of the replacement equipment.(5) The date of successful repair.(vi) You must maintain records of the information specified in paragraphs (c)(9)(vi)(A) through (C) of this section for closed vent systems and control devices subject to the provisions of § 63.172. The records specified in paragraph (c)(9)(vi)(A) of this section must be retained for the life of the equipment.(A) The design specifications and performance demonstrations specified in paragraphs (c)(9)(vi)(A)(1) through (4) of this section.(1) Detailed schematics, design specifications of the control device, and piping and instrumentation diagrams.(2) The dates and descriptions of any changes in the design specifications.(3) The flare design (i.e., steam-assisted, air-assisted, or non-assisted) and the results of the compliance demonstration required by subpart SS of this part.(4) A description of the parameter or parameters monitored, as required in § 63.172(e), to ensure that control devices are operated and maintained in conformance with their design and an explanation of why that parameter (or parameters) was selected for the monitoring.(B) Records of operation of closed vent systems and control devices, as specified in paragraphs (c)(9)(vi)(B)(1) through (3) of this section.(1) Dates and durations when the closed vent systems and control devices required in § 63.11495(a)(6) are not operated as designed as indicated by the monitored parameters, including periods when a flare pilot light system does not have a flame.(2) Dates and durations during which the monitoring system or monitoring device is inoperative.(3) Dates and durations of startups and shutdowns of control devices required in § 63.11495(a)(6).(C) Records of inspections of closed vent systems subject to the provisions of § 63.172, as specified in paragraphs (c)(9)(vi)(C)(1) and (2) of this section.(1) For each inspection conducted in accordance with the provisions of § 63.172(f)(1) or (2) during which leaks were detected, the information specified in paragraph (c)(9)(iii) of this section must be recorded.(2) For each flow event from a bypass line subject to the requirements in § 63.172(j), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements in § 63.11495(a)(6), you must include an estimate of the volume of gas, the concentration of organic HAP in the gas, and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(vii) If you choose to comply with the requirements of § 63.179, you must maintain the following records:(C) A description of the system used to create a negative pressure in the enclosure to ensure that all emissions are routed to the control device.(10) For each flow event from a bypass line subject to the requirements in § 63.11495(e), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements specified in §§ 63.11495 through 63.11499, you must include an estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must keep records as specified in § 63.104(f)(3) instead of the heat exchange system records specified in paragraphs (c)(1)(ii) and (6) of this section.
-
(i) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi), (vii), (x), and (xi). The CEMS must allow the amount of excess zero (low-level) and high-level calibration drift measured at the interval checks to be quantified and recorded.
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vii) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi) that apply to your continuous monitoring system.
-
(c) In addition to the general records required by § 63.10(b)(2)(iii) and (vi) through (xiv), the owner or operator must maintain records of the information in paragraphs (c)(1) through (8) of this section:(1) Records of black liquor solids firing rates in units of Mg/d or ton/d for all recovery furnaces and semichemical combustion units;(2) Records of CaO production rates in units of Mg/d or ton/d for all lime kilns;(3) Records of parameter monitoring data required under § 63.864, including any period when the operating parameter levels were inconsistent with the levels established during the performance test, with a brief explanation of the cause of the monitoring exceedance, the time the monitoring exceedance occurred, the time corrective action was initiated and completed, and the corrective action taken;(4) Records and documentation of supporting calculations for compliance determinations made under § 63.865(a) through (d);(5) Records of parameter operating limits established for each affected source or process unit;(6) Records certifying that an NDCE recovery furnace equipped with a dry ESP system is used to comply with the gaseous organic HAP standard in § 63.862(c)(1);(7) For the bag leak detection system on the hog fuel dryer fabric filter at Cosmo Specialty Fibers' Cosmopolis, Washington facility (Emission Unit no. HD-14), records of each alarm, the time of the alarm, the time corrective action was initiated and completed, and a brief description of the cause of the alarm and the corrective action taken; and(8) Records demonstrating compliance with the requirement in § 63.864(e)(1) to maintain proper operation of an ESP's AVC.
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
Citations to §63.10(b)(2)(vii)(A)
-
(1) Where this subpart requires a continuous record using CEMS or CPMS, you must maintain, at a minimum, the records specified in § 63.10(b)(2)(vii)(A).
-
(5) Monitoring data recorded during periods of unavoidable CMS breakdowns, out-of-control periods, repairs, maintenance periods, calibration checks, and zero (low-level) and high-level adjustments must not be included in any data average computed under this part. For the owner or operator complying with the requirements of § 63.10(b)(2)(vii)(A) or (B), data averages must include any data recorded during periods of monitor breakdown or malfunction.
Citations to §63.10(b)(2)(vii)(B)
-
(5) Monitoring data recorded during periods of unavoidable CMS breakdowns, out-of-control periods, repairs, maintenance periods, calibration checks, and zero (low-level) and high-level adjustments must not be included in any data average computed under this part. For the owner or operator complying with the requirements of § 63.10(b)(2)(vii)(A) or (B), data averages must include any data recorded during periods of monitor breakdown or malfunction.
Citations to §63.10(b)(2)(viii)
-
(2) Records of performance stack tests, fuel analyses, or other compliance demonstrations and performance evaluations, as required in § 63.10(b)(2)(viii).
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(c) You must maintain files of all information required by this subpart for at least 5 years following the date of each occurrence according to the requirements in § 63.10(b)(1). If you are subject, you must comply with the recordkeeping and reporting requirements of § 63.10(b)(2)(iii) and (vi) through (xiv), and the applicable requirements specified in paragraphs (c)(1) through (11) of this section.(1) For each CMPU subject to this subpart, you must keep the records specified in paragraphs (c)(1)(i) through (viii) of this section.(i) Except as specified in paragraph (c)(9) of this section, records of management practice inspections, repairs, and reasons for any delay of repair, as specified in § 63.11495(a)(5).(ii) Except as specified in paragraph (c)(11) of this section, records of small heat exchange system inspections, demonstrations of indications of leaks that do not constitute leaks, repairs, and reasons for any delay in repair as specified in § 63.11495(b).(iii) If batch process vent emissions are less than 10,000 lb/yr for a CMPU, records of batch process vent emission calculations, as specified in § 63.11496(a)(1), the number of batches operated each month, as specified in § 63.11496(a)(3), and any updated emissions calculations, as specified in § 63.11496(a)(3). Alternatively, keep records of the worst-case processes or organic HAP usage, as specified in § 63.11496(a)(2) and (4), respectively.(iv) Records of all TRE calculations for continuous process vents as specified in § 63.11496(b)(2).(v) Records of metal HAP emission calculations as specified in § 63.11496(f)(1) and (2). If total uncontrolled metal HAP process vent emissions from a CMPU subject to this subpart are estimated to be less than 400 lb/yr, also keep records of either the number of batches per month or operating hours, as specified in § 63.11496(f)(2).(vi) Records identifying wastewater streams and the type of treatment they receive, as specified in table 6 to this subpart.(vii) Before April 1, 2029, records of the date, time, and duration of each malfunction of operation of process equipment, control devices, recovery devices, or continuous monitoring systems used to comply with this subpart that causes a failure to meet a standard. The record must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. After April 1, 2029, for any deviation, records of the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions.(viii) Before April 1, 2029, records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.11495(d), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. After April 1, 2029, for any deviation, records of actions taken to minimize emissions in accordance with § 63.11495(d), and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) For batch process vents subject to table 2 to this subpart and continuous process vents subject to table 3 to this subpart, you must keep records specified in paragraphs (c)(2)(i) or (ii) of this section, as applicable.(i) If you route emissions to a control device other than a flare, keep records of performance tests, if applicable, as specified in § 63.998(a)(2)(ii) and (4), keep records of the monitoring system and the monitored parameters, as specified in § 63.998(b) and (c), and keep records of the closed-vent system, as specified in § 63.998(d)(1). If you use a recovery device to maintain the TRE above 1.0 for a continuous process vent, keep records of monitoring parameters during the TRE index value determination, as specified in § 63.998(a)(3).(ii) If you route emissions to a flare, keep records of the flare compliance assessment, as specified in § 63.998(a)(1)(i), keep records of the pilot flame monitoring, as specified in § 63.998(a)(1)(ii) and (iii), and keep records of the closed-vent system, as specified in § 63.998(d)(1).(3) For metal HAP process vents subject to table 4 to this subpart, you must keep records specified in paragraph (c)(3)(i) or (ii) of this section, as applicable.(i) For a new source using a control device other than a baghouse and for any existing source, maintain a monitoring plan, as specified in § 63.11496(f)(3)(i), and keep records of monitoring results, as specified in § 63.11496(f)(3).(ii) For a new source using a baghouse to control metal HAP emissions, keep a site-specific monitoring plan, as specified in §§ 63.11496(f)(4) and 63.11410(g), and keep records of bag leak detection systems, as specified in §§ 63.11496(f)(4) and 63.11410(g)(4).(4) For each storage tank subject to table 5 to this subpart, you must keep records specified in paragraphs (c)(4)(i) through (vii) of this section, as applicable.(i) Keep records of the vessel dimensions, capacity, and liquid stored, as specified in § 63.1065(a).(ii) Keep records of each inspection of an internal floating roof, as specified in § 63.1065(b)(1).(iii) Keep records of each seal gap measurement for external floating roofs, as specified in § 63.1065(b)(2), and keep records of inspections of external floating roofs, as specified in § 63.1065(b)(1).(iv) If you vent emissions to a control device other than a flare, keep records of the operating plan and measured parameter values, as specified in §§ 63.985(c) and 63.998(d)(2).(v) If you vent emissions to a flare, keep records of all periods of operation during which the flare pilot flame is absent, as specified in §§ 63.987(c) and 63.998(a)(1), and keep records of closed-vent systems, as specified in § 63.998(d)(1).(vi) For periods of planned routine maintenance of a control device, keep records of the day and time at which each maintenance period begins and ends, and keep records of the type of maintenance performed, as specified in § 63.11497(b)(3).(vii) For each pressure vessel subject to the requirements of § 63.11497(f) you must keep records as specified in paragraphs (c)(4)(vii)(A) and (B) of this section.(A) The date of each performance test conducted according to § 63.11497(f)(2).(B) The record of each performance test conducted according to § 63.11497(f)(2), including the following:(1) Date each defect was detected and the instrument reading (in ppmv) during the performance test.(2) Date of the next performance test that shows the instrument reading is less than 500 ppmv and the instrument reading (in ppmv) during the performance test.(3) Start and end dates of each period after the date in paragraph (c)(4)(ix)(B)(1) of this section when the pressure vessel was completely empty.(4) Estimated emissions from each defect.(5) For each wastewater stream subject to item 2 in table 6 to this subpart, keep records of the wastewater stream identification and the disposition of the organic phase(s), as specified in item 2 to table 6 to this subpart.(6) Except as specified in paragraph (c)(11) of this section, for each large heat exchange system subject to table 8 to this subpart, you must keep records of detected leaks; the date the leak was detected; if demonstrated not to be a leak, the basis for that determination; the date of efforts to repair the leak; and the date the leak is repaired, as specified in table 8 to this subpart.(7) You must keep a record of all transferred liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) For continuous process vents subject to table 3 to this subpart, keep records of the occurrence and duration of each startup and shutdown of operation of process equipment, or of air pollution control and monitoring equipment.(9) If you are subject to the equipment leak requirements specified in § 63.11495(a)(6), then you must keep records as specified in paragraphs (c)(9)(i) through (vii) of this section instead of the records specified in paragraph (c)(1)(i) of this section.(i) Keep a list, summary description, or diagram(s) showing the location and identification number of all equipment in organic HAP service at the facility and the information in paragraphs (c)(9)(i)(A) through (D) of this section.(A) Identification of equipment designated as unsafe to monitor, difficult to monitor, unsafe to inspect, difficult to inspect, or unsafe to repair and the plan for monitoring or inspecting this equipment, as applicable.(B) Identification of the equipment in batch process units, for which you do not elect to pressure test the batch product process equipment train.(ii) For leak detection monitoring and inspections required by paragraphs § 63.11495(a)(6) (e.g., monitoring using Method 21 of appendix A-7 to part 60 of this chapter; visible, audible, or olfactory monitoring; closed vent system inspections; and batch process unit monitoring), record the date of the monitoring or inspection and include a statement of whether leaks were detected. If no leaks are detected, records of the monitoring and inspection results are not required.(iii) When each leak is detected as specified in § 63.11495(a)(6), the following information must be recorded:(A) The instrument and the equipment identification number and the operator name, initials, or identification number.(D) Maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A-7 of this chapter after it is successfully repaired or determined to be nonrepairable.(E) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(1) You may develop a written procedure that identifies the conditions that justify a delay of repair. In such cases, reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(2) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked on-site before depletion and the reason for depletion.(iv) For each pressure relief device subject to the provisions in § 63.165(e), you must keep the records specified in paragraphs (c)(9)(iv)(A) through (C) of this section.(A) Records of the prevention measures implemented as required in § 63.165(e)(3)(ii).(C) For each release to the atmosphere, you must keep the records specified in paragraphs (c)(9)(iv)(C)(1) through (4) of this section.(1) The start and end time and date of each pressure release to the atmosphere.(2) Records of any data, assumptions, and calculations used to estimate of the mass quantity of each organic HAP released during the event.(3) Records of the root cause analysis and corrective action analysis conducted as required in § 63.165(e)(3)(iii), including an identification of the affected facility, a statement noting whether the event resulted from the same root cause(s) identified in a previous analysis and either a description of the recommended corrective action(s) or an explanation of why corrective action is not necessary under § 63.165(e)(7)(i).(4) For any corrective action analysis for which implementation of corrective actions are required in § 63.165(e)(7), a description of the corrective action(s) completed within the first 45 days following the discharge and, for action(s) not already completed, a schedule for implementation, including proposed commencement and completion dates.(v) If you own or operate a batch product process and elect to pressure test the batch product process equipment train to demonstrate compliance with § 63.11495(a)(6), you are exempt from the requirements of paragraphs (c)(9)(i) through (iv) of this section. Instead, you must maintain records of the following information:(B) The dates of each pressure test required in § 63.178(b), the test pressure, and the pressure drop observed during the test.(C) When a batch product process equipment train does not pass two consecutive pressure tests, the following information must be recorded:(1) The date of each pressure test and the date of each leak repair attempt.(2) Repair methods applied in each attempt to repair the leak.(3) The reason for the delay of repair.(4) The expected date for delivery of the replacement equipment and the actual date of delivery of the replacement equipment.(5) The date of successful repair.(vi) You must maintain records of the information specified in paragraphs (c)(9)(vi)(A) through (C) of this section for closed vent systems and control devices subject to the provisions of § 63.172. The records specified in paragraph (c)(9)(vi)(A) of this section must be retained for the life of the equipment.(A) The design specifications and performance demonstrations specified in paragraphs (c)(9)(vi)(A)(1) through (4) of this section.(1) Detailed schematics, design specifications of the control device, and piping and instrumentation diagrams.(2) The dates and descriptions of any changes in the design specifications.(3) The flare design (i.e., steam-assisted, air-assisted, or non-assisted) and the results of the compliance demonstration required by subpart SS of this part.(4) A description of the parameter or parameters monitored, as required in § 63.172(e), to ensure that control devices are operated and maintained in conformance with their design and an explanation of why that parameter (or parameters) was selected for the monitoring.(B) Records of operation of closed vent systems and control devices, as specified in paragraphs (c)(9)(vi)(B)(1) through (3) of this section.(1) Dates and durations when the closed vent systems and control devices required in § 63.11495(a)(6) are not operated as designed as indicated by the monitored parameters, including periods when a flare pilot light system does not have a flame.(2) Dates and durations during which the monitoring system or monitoring device is inoperative.(3) Dates and durations of startups and shutdowns of control devices required in § 63.11495(a)(6).(C) Records of inspections of closed vent systems subject to the provisions of § 63.172, as specified in paragraphs (c)(9)(vi)(C)(1) and (2) of this section.(1) For each inspection conducted in accordance with the provisions of § 63.172(f)(1) or (2) during which leaks were detected, the information specified in paragraph (c)(9)(iii) of this section must be recorded.(2) For each flow event from a bypass line subject to the requirements in § 63.172(j), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements in § 63.11495(a)(6), you must include an estimate of the volume of gas, the concentration of organic HAP in the gas, and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(vii) If you choose to comply with the requirements of § 63.179, you must maintain the following records:(C) A description of the system used to create a negative pressure in the enclosure to ensure that all emissions are routed to the control device.(10) For each flow event from a bypass line subject to the requirements in § 63.11495(e), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements specified in §§ 63.11495 through 63.11499, you must include an estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must keep records as specified in § 63.104(f)(3) instead of the heat exchange system records specified in paragraphs (c)(1)(ii) and (6) of this section.
-
(2) Copies of emission tests used to demonstrate compliance and performance evaluations as required in § 63.10(b)(2)(viii).
-
(iii) Records of performance tests and performance evaluations as required in § 63.10(b)(2)(viii).
-
(1) Records of performance tests as required in § 63.10(b)(2)(viii). You must also collect the applicable control device operating parameters required in § 63.11940 over the full period of the performance test.
-
(3) Records of performance tests and performance evaluations as required in § 63.10(b)(2)(viii).
-
(3) Records of performance tests, performance evaluations, and opacity and visible emission observations as required in § 63.10(b)(2)(viii).
-
(3) Records of performance tests and performance evaluations as required in § 63.10(b)(2)(viii) and (ix).
-
(4) Records of performance tests and performance evaluations as required in § 63.10(b)(2)(viii).
-
(2) Records of performance tests as required in § 63.10(b)(2)(viii).
-
(2) Records of performance tests and performance evaluations as required in § 63.10(b)(2)(viii).
-
(3) Records of performance tests and performance evaluations as required in § 63.10(b)(2)(viii).
-
(3) Records of performance tests, performance evaluations, and opacity and VE observations as required in § 63.10(b)(2)(viii).
-
(3) Records of performance tests and performance evaluations as required in § 63.10(b)(2)(viii).
-
(5) Records of performance tests, performance evaluations, and opacity observations as required in § 63.10(b)(2)(viii).
-
(2) Records of performance tests, fuel analyses, or other compliance demonstrations and performance evaluations as required in § 63.10(b)(2)(viii).
-
(3) Records of performance tests and performance evaluations as required by § 63.10(b)(2)(viii).
-
(5) Records of performance tests, performance evaluations, and opacity observations as required in § 63.10(b)(2)(viii).
-
(9) Results of performance tests and performance evaluations as required by § 63.10(b)(2)(viii).
-
(1) Records of performance tests as required in § 63.10(b)(2)(viii).
-
(2) Records of performance tests as required in § 63.10(b)(2)(viii).
-
(2) Records of performance tests as required in § 63.10(b)(2)(viii).
-
(c) In addition to the general records required by § 63.10(b)(2)(iii) and (vi) through (xiv), the owner or operator must maintain records of the information in paragraphs (c)(1) through (8) of this section:(1) Records of black liquor solids firing rates in units of Mg/d or ton/d for all recovery furnaces and semichemical combustion units;(2) Records of CaO production rates in units of Mg/d or ton/d for all lime kilns;(3) Records of parameter monitoring data required under § 63.864, including any period when the operating parameter levels were inconsistent with the levels established during the performance test, with a brief explanation of the cause of the monitoring exceedance, the time the monitoring exceedance occurred, the time corrective action was initiated and completed, and the corrective action taken;(4) Records and documentation of supporting calculations for compliance determinations made under § 63.865(a) through (d);(5) Records of parameter operating limits established for each affected source or process unit;(6) Records certifying that an NDCE recovery furnace equipped with a dry ESP system is used to comply with the gaseous organic HAP standard in § 63.862(c)(1);(7) For the bag leak detection system on the hog fuel dryer fabric filter at Cosmo Specialty Fibers' Cosmopolis, Washington facility (Emission Unit no. HD-14), records of each alarm, the time of the alarm, the time corrective action was initiated and completed, and a brief description of the cause of the alarm and the corrective action taken; and(8) Records demonstrating compliance with the requirement in § 63.864(e)(1) to maintain proper operation of an ESP's AVC.
-
(3) Records of performance tests, performance evaluations, and opacity and visible emission observations as required in § 63.10(b)(2)(viii).
-
(1) Records of performance tests, as required in § 63.10(b)(2)(viii).
-
(2) Records of performance tests as required in § 63.10(b)(2)(viii).
-
(2) Records of performance evaluations as required in § 63.10(b)(2)(viii).
-
(3) Records of performance tests and performance evaluations as required in § 63.10(b)(2)(viii).
-
(3) Records of performance tests as required in § 63.10(b)(2)(viii).
-
(3) Records of performance tests and performance evaluations as required in § 63.10(b)(2)(viii).
Citations to §63.10(b)(2)(x)
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(c) You must maintain files of all information required by this subpart for at least 5 years following the date of each occurrence according to the requirements in § 63.10(b)(1). If you are subject, you must comply with the recordkeeping and reporting requirements of § 63.10(b)(2)(iii) and (vi) through (xiv), and the applicable requirements specified in paragraphs (c)(1) through (11) of this section.(1) For each CMPU subject to this subpart, you must keep the records specified in paragraphs (c)(1)(i) through (viii) of this section.(i) Except as specified in paragraph (c)(9) of this section, records of management practice inspections, repairs, and reasons for any delay of repair, as specified in § 63.11495(a)(5).(ii) Except as specified in paragraph (c)(11) of this section, records of small heat exchange system inspections, demonstrations of indications of leaks that do not constitute leaks, repairs, and reasons for any delay in repair as specified in § 63.11495(b).(iii) If batch process vent emissions are less than 10,000 lb/yr for a CMPU, records of batch process vent emission calculations, as specified in § 63.11496(a)(1), the number of batches operated each month, as specified in § 63.11496(a)(3), and any updated emissions calculations, as specified in § 63.11496(a)(3). Alternatively, keep records of the worst-case processes or organic HAP usage, as specified in § 63.11496(a)(2) and (4), respectively.(iv) Records of all TRE calculations for continuous process vents as specified in § 63.11496(b)(2).(v) Records of metal HAP emission calculations as specified in § 63.11496(f)(1) and (2). If total uncontrolled metal HAP process vent emissions from a CMPU subject to this subpart are estimated to be less than 400 lb/yr, also keep records of either the number of batches per month or operating hours, as specified in § 63.11496(f)(2).(vi) Records identifying wastewater streams and the type of treatment they receive, as specified in table 6 to this subpart.(vii) Before April 1, 2029, records of the date, time, and duration of each malfunction of operation of process equipment, control devices, recovery devices, or continuous monitoring systems used to comply with this subpart that causes a failure to meet a standard. The record must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. After April 1, 2029, for any deviation, records of the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions.(viii) Before April 1, 2029, records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.11495(d), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. After April 1, 2029, for any deviation, records of actions taken to minimize emissions in accordance with § 63.11495(d), and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) For batch process vents subject to table 2 to this subpart and continuous process vents subject to table 3 to this subpart, you must keep records specified in paragraphs (c)(2)(i) or (ii) of this section, as applicable.(i) If you route emissions to a control device other than a flare, keep records of performance tests, if applicable, as specified in § 63.998(a)(2)(ii) and (4), keep records of the monitoring system and the monitored parameters, as specified in § 63.998(b) and (c), and keep records of the closed-vent system, as specified in § 63.998(d)(1). If you use a recovery device to maintain the TRE above 1.0 for a continuous process vent, keep records of monitoring parameters during the TRE index value determination, as specified in § 63.998(a)(3).(ii) If you route emissions to a flare, keep records of the flare compliance assessment, as specified in § 63.998(a)(1)(i), keep records of the pilot flame monitoring, as specified in § 63.998(a)(1)(ii) and (iii), and keep records of the closed-vent system, as specified in § 63.998(d)(1).(3) For metal HAP process vents subject to table 4 to this subpart, you must keep records specified in paragraph (c)(3)(i) or (ii) of this section, as applicable.(i) For a new source using a control device other than a baghouse and for any existing source, maintain a monitoring plan, as specified in § 63.11496(f)(3)(i), and keep records of monitoring results, as specified in § 63.11496(f)(3).(ii) For a new source using a baghouse to control metal HAP emissions, keep a site-specific monitoring plan, as specified in §§ 63.11496(f)(4) and 63.11410(g), and keep records of bag leak detection systems, as specified in §§ 63.11496(f)(4) and 63.11410(g)(4).(4) For each storage tank subject to table 5 to this subpart, you must keep records specified in paragraphs (c)(4)(i) through (vii) of this section, as applicable.(i) Keep records of the vessel dimensions, capacity, and liquid stored, as specified in § 63.1065(a).(ii) Keep records of each inspection of an internal floating roof, as specified in § 63.1065(b)(1).(iii) Keep records of each seal gap measurement for external floating roofs, as specified in § 63.1065(b)(2), and keep records of inspections of external floating roofs, as specified in § 63.1065(b)(1).(iv) If you vent emissions to a control device other than a flare, keep records of the operating plan and measured parameter values, as specified in §§ 63.985(c) and 63.998(d)(2).(v) If you vent emissions to a flare, keep records of all periods of operation during which the flare pilot flame is absent, as specified in §§ 63.987(c) and 63.998(a)(1), and keep records of closed-vent systems, as specified in § 63.998(d)(1).(vi) For periods of planned routine maintenance of a control device, keep records of the day and time at which each maintenance period begins and ends, and keep records of the type of maintenance performed, as specified in § 63.11497(b)(3).(vii) For each pressure vessel subject to the requirements of § 63.11497(f) you must keep records as specified in paragraphs (c)(4)(vii)(A) and (B) of this section.(A) The date of each performance test conducted according to § 63.11497(f)(2).(B) The record of each performance test conducted according to § 63.11497(f)(2), including the following:(1) Date each defect was detected and the instrument reading (in ppmv) during the performance test.(2) Date of the next performance test that shows the instrument reading is less than 500 ppmv and the instrument reading (in ppmv) during the performance test.(3) Start and end dates of each period after the date in paragraph (c)(4)(ix)(B)(1) of this section when the pressure vessel was completely empty.(4) Estimated emissions from each defect.(5) For each wastewater stream subject to item 2 in table 6 to this subpart, keep records of the wastewater stream identification and the disposition of the organic phase(s), as specified in item 2 to table 6 to this subpart.(6) Except as specified in paragraph (c)(11) of this section, for each large heat exchange system subject to table 8 to this subpart, you must keep records of detected leaks; the date the leak was detected; if demonstrated not to be a leak, the basis for that determination; the date of efforts to repair the leak; and the date the leak is repaired, as specified in table 8 to this subpart.(7) You must keep a record of all transferred liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) For continuous process vents subject to table 3 to this subpart, keep records of the occurrence and duration of each startup and shutdown of operation of process equipment, or of air pollution control and monitoring equipment.(9) If you are subject to the equipment leak requirements specified in § 63.11495(a)(6), then you must keep records as specified in paragraphs (c)(9)(i) through (vii) of this section instead of the records specified in paragraph (c)(1)(i) of this section.(i) Keep a list, summary description, or diagram(s) showing the location and identification number of all equipment in organic HAP service at the facility and the information in paragraphs (c)(9)(i)(A) through (D) of this section.(A) Identification of equipment designated as unsafe to monitor, difficult to monitor, unsafe to inspect, difficult to inspect, or unsafe to repair and the plan for monitoring or inspecting this equipment, as applicable.(B) Identification of the equipment in batch process units, for which you do not elect to pressure test the batch product process equipment train.(ii) For leak detection monitoring and inspections required by paragraphs § 63.11495(a)(6) (e.g., monitoring using Method 21 of appendix A-7 to part 60 of this chapter; visible, audible, or olfactory monitoring; closed vent system inspections; and batch process unit monitoring), record the date of the monitoring or inspection and include a statement of whether leaks were detected. If no leaks are detected, records of the monitoring and inspection results are not required.(iii) When each leak is detected as specified in § 63.11495(a)(6), the following information must be recorded:(A) The instrument and the equipment identification number and the operator name, initials, or identification number.(D) Maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A-7 of this chapter after it is successfully repaired or determined to be nonrepairable.(E) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(1) You may develop a written procedure that identifies the conditions that justify a delay of repair. In such cases, reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(2) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked on-site before depletion and the reason for depletion.(iv) For each pressure relief device subject to the provisions in § 63.165(e), you must keep the records specified in paragraphs (c)(9)(iv)(A) through (C) of this section.(A) Records of the prevention measures implemented as required in § 63.165(e)(3)(ii).(C) For each release to the atmosphere, you must keep the records specified in paragraphs (c)(9)(iv)(C)(1) through (4) of this section.(1) The start and end time and date of each pressure release to the atmosphere.(2) Records of any data, assumptions, and calculations used to estimate of the mass quantity of each organic HAP released during the event.(3) Records of the root cause analysis and corrective action analysis conducted as required in § 63.165(e)(3)(iii), including an identification of the affected facility, a statement noting whether the event resulted from the same root cause(s) identified in a previous analysis and either a description of the recommended corrective action(s) or an explanation of why corrective action is not necessary under § 63.165(e)(7)(i).(4) For any corrective action analysis for which implementation of corrective actions are required in § 63.165(e)(7), a description of the corrective action(s) completed within the first 45 days following the discharge and, for action(s) not already completed, a schedule for implementation, including proposed commencement and completion dates.(v) If you own or operate a batch product process and elect to pressure test the batch product process equipment train to demonstrate compliance with § 63.11495(a)(6), you are exempt from the requirements of paragraphs (c)(9)(i) through (iv) of this section. Instead, you must maintain records of the following information:(B) The dates of each pressure test required in § 63.178(b), the test pressure, and the pressure drop observed during the test.(C) When a batch product process equipment train does not pass two consecutive pressure tests, the following information must be recorded:(1) The date of each pressure test and the date of each leak repair attempt.(2) Repair methods applied in each attempt to repair the leak.(3) The reason for the delay of repair.(4) The expected date for delivery of the replacement equipment and the actual date of delivery of the replacement equipment.(5) The date of successful repair.(vi) You must maintain records of the information specified in paragraphs (c)(9)(vi)(A) through (C) of this section for closed vent systems and control devices subject to the provisions of § 63.172. The records specified in paragraph (c)(9)(vi)(A) of this section must be retained for the life of the equipment.(A) The design specifications and performance demonstrations specified in paragraphs (c)(9)(vi)(A)(1) through (4) of this section.(1) Detailed schematics, design specifications of the control device, and piping and instrumentation diagrams.(2) The dates and descriptions of any changes in the design specifications.(3) The flare design (i.e., steam-assisted, air-assisted, or non-assisted) and the results of the compliance demonstration required by subpart SS of this part.(4) A description of the parameter or parameters monitored, as required in § 63.172(e), to ensure that control devices are operated and maintained in conformance with their design and an explanation of why that parameter (or parameters) was selected for the monitoring.(B) Records of operation of closed vent systems and control devices, as specified in paragraphs (c)(9)(vi)(B)(1) through (3) of this section.(1) Dates and durations when the closed vent systems and control devices required in § 63.11495(a)(6) are not operated as designed as indicated by the monitored parameters, including periods when a flare pilot light system does not have a flame.(2) Dates and durations during which the monitoring system or monitoring device is inoperative.(3) Dates and durations of startups and shutdowns of control devices required in § 63.11495(a)(6).(C) Records of inspections of closed vent systems subject to the provisions of § 63.172, as specified in paragraphs (c)(9)(vi)(C)(1) and (2) of this section.(1) For each inspection conducted in accordance with the provisions of § 63.172(f)(1) or (2) during which leaks were detected, the information specified in paragraph (c)(9)(iii) of this section must be recorded.(2) For each flow event from a bypass line subject to the requirements in § 63.172(j), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements in § 63.11495(a)(6), you must include an estimate of the volume of gas, the concentration of organic HAP in the gas, and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(vii) If you choose to comply with the requirements of § 63.179, you must maintain the following records:(C) A description of the system used to create a negative pressure in the enclosure to ensure that all emissions are routed to the control device.(10) For each flow event from a bypass line subject to the requirements in § 63.11495(e), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements specified in §§ 63.11495 through 63.11499, you must include an estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must keep records as specified in § 63.104(f)(3) instead of the heat exchange system records specified in paragraphs (c)(1)(ii) and (6) of this section.
-
(iv) Records of CPMS (if a CPMS is used to demonstrate compliance) calibration checks and adjustments and maintenance performed on CPMS as required by § 63.10(b)(2)(x) and (xi).
-
(i) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi), (vii), (x), and (xi). The CEMS must allow the amount of excess zero (low-level) and high-level calibration drift measured at the interval checks to be quantified and recorded.
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vii) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi) that apply to your continuous monitoring system.
-
(c) In addition to the general records required by § 63.10(b)(2)(iii) and (vi) through (xiv), the owner or operator must maintain records of the information in paragraphs (c)(1) through (8) of this section:(1) Records of black liquor solids firing rates in units of Mg/d or ton/d for all recovery furnaces and semichemical combustion units;(2) Records of CaO production rates in units of Mg/d or ton/d for all lime kilns;(3) Records of parameter monitoring data required under § 63.864, including any period when the operating parameter levels were inconsistent with the levels established during the performance test, with a brief explanation of the cause of the monitoring exceedance, the time the monitoring exceedance occurred, the time corrective action was initiated and completed, and the corrective action taken;(4) Records and documentation of supporting calculations for compliance determinations made under § 63.865(a) through (d);(5) Records of parameter operating limits established for each affected source or process unit;(6) Records certifying that an NDCE recovery furnace equipped with a dry ESP system is used to comply with the gaseous organic HAP standard in § 63.862(c)(1);(7) For the bag leak detection system on the hog fuel dryer fabric filter at Cosmo Specialty Fibers' Cosmopolis, Washington facility (Emission Unit no. HD-14), records of each alarm, the time of the alarm, the time corrective action was initiated and completed, and a brief description of the cause of the alarm and the corrective action taken; and(8) Records demonstrating compliance with the requirement in § 63.864(e)(1) to maintain proper operation of an ESP's AVC.
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
Citations to §63.10(b)(2)(xi)
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(c) You must maintain files of all information required by this subpart for at least 5 years following the date of each occurrence according to the requirements in § 63.10(b)(1). If you are subject, you must comply with the recordkeeping and reporting requirements of § 63.10(b)(2)(iii) and (vi) through (xiv), and the applicable requirements specified in paragraphs (c)(1) through (11) of this section.(1) For each CMPU subject to this subpart, you must keep the records specified in paragraphs (c)(1)(i) through (viii) of this section.(i) Except as specified in paragraph (c)(9) of this section, records of management practice inspections, repairs, and reasons for any delay of repair, as specified in § 63.11495(a)(5).(ii) Except as specified in paragraph (c)(11) of this section, records of small heat exchange system inspections, demonstrations of indications of leaks that do not constitute leaks, repairs, and reasons for any delay in repair as specified in § 63.11495(b).(iii) If batch process vent emissions are less than 10,000 lb/yr for a CMPU, records of batch process vent emission calculations, as specified in § 63.11496(a)(1), the number of batches operated each month, as specified in § 63.11496(a)(3), and any updated emissions calculations, as specified in § 63.11496(a)(3). Alternatively, keep records of the worst-case processes or organic HAP usage, as specified in § 63.11496(a)(2) and (4), respectively.(iv) Records of all TRE calculations for continuous process vents as specified in § 63.11496(b)(2).(v) Records of metal HAP emission calculations as specified in § 63.11496(f)(1) and (2). If total uncontrolled metal HAP process vent emissions from a CMPU subject to this subpart are estimated to be less than 400 lb/yr, also keep records of either the number of batches per month or operating hours, as specified in § 63.11496(f)(2).(vi) Records identifying wastewater streams and the type of treatment they receive, as specified in table 6 to this subpart.(vii) Before April 1, 2029, records of the date, time, and duration of each malfunction of operation of process equipment, control devices, recovery devices, or continuous monitoring systems used to comply with this subpart that causes a failure to meet a standard. The record must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. After April 1, 2029, for any deviation, records of the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions.(viii) Before April 1, 2029, records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.11495(d), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. After April 1, 2029, for any deviation, records of actions taken to minimize emissions in accordance with § 63.11495(d), and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) For batch process vents subject to table 2 to this subpart and continuous process vents subject to table 3 to this subpart, you must keep records specified in paragraphs (c)(2)(i) or (ii) of this section, as applicable.(i) If you route emissions to a control device other than a flare, keep records of performance tests, if applicable, as specified in § 63.998(a)(2)(ii) and (4), keep records of the monitoring system and the monitored parameters, as specified in § 63.998(b) and (c), and keep records of the closed-vent system, as specified in § 63.998(d)(1). If you use a recovery device to maintain the TRE above 1.0 for a continuous process vent, keep records of monitoring parameters during the TRE index value determination, as specified in § 63.998(a)(3).(ii) If you route emissions to a flare, keep records of the flare compliance assessment, as specified in § 63.998(a)(1)(i), keep records of the pilot flame monitoring, as specified in § 63.998(a)(1)(ii) and (iii), and keep records of the closed-vent system, as specified in § 63.998(d)(1).(3) For metal HAP process vents subject to table 4 to this subpart, you must keep records specified in paragraph (c)(3)(i) or (ii) of this section, as applicable.(i) For a new source using a control device other than a baghouse and for any existing source, maintain a monitoring plan, as specified in § 63.11496(f)(3)(i), and keep records of monitoring results, as specified in § 63.11496(f)(3).(ii) For a new source using a baghouse to control metal HAP emissions, keep a site-specific monitoring plan, as specified in §§ 63.11496(f)(4) and 63.11410(g), and keep records of bag leak detection systems, as specified in §§ 63.11496(f)(4) and 63.11410(g)(4).(4) For each storage tank subject to table 5 to this subpart, you must keep records specified in paragraphs (c)(4)(i) through (vii) of this section, as applicable.(i) Keep records of the vessel dimensions, capacity, and liquid stored, as specified in § 63.1065(a).(ii) Keep records of each inspection of an internal floating roof, as specified in § 63.1065(b)(1).(iii) Keep records of each seal gap measurement for external floating roofs, as specified in § 63.1065(b)(2), and keep records of inspections of external floating roofs, as specified in § 63.1065(b)(1).(iv) If you vent emissions to a control device other than a flare, keep records of the operating plan and measured parameter values, as specified in §§ 63.985(c) and 63.998(d)(2).(v) If you vent emissions to a flare, keep records of all periods of operation during which the flare pilot flame is absent, as specified in §§ 63.987(c) and 63.998(a)(1), and keep records of closed-vent systems, as specified in § 63.998(d)(1).(vi) For periods of planned routine maintenance of a control device, keep records of the day and time at which each maintenance period begins and ends, and keep records of the type of maintenance performed, as specified in § 63.11497(b)(3).(vii) For each pressure vessel subject to the requirements of § 63.11497(f) you must keep records as specified in paragraphs (c)(4)(vii)(A) and (B) of this section.(A) The date of each performance test conducted according to § 63.11497(f)(2).(B) The record of each performance test conducted according to § 63.11497(f)(2), including the following:(1) Date each defect was detected and the instrument reading (in ppmv) during the performance test.(2) Date of the next performance test that shows the instrument reading is less than 500 ppmv and the instrument reading (in ppmv) during the performance test.(3) Start and end dates of each period after the date in paragraph (c)(4)(ix)(B)(1) of this section when the pressure vessel was completely empty.(4) Estimated emissions from each defect.(5) For each wastewater stream subject to item 2 in table 6 to this subpart, keep records of the wastewater stream identification and the disposition of the organic phase(s), as specified in item 2 to table 6 to this subpart.(6) Except as specified in paragraph (c)(11) of this section, for each large heat exchange system subject to table 8 to this subpart, you must keep records of detected leaks; the date the leak was detected; if demonstrated not to be a leak, the basis for that determination; the date of efforts to repair the leak; and the date the leak is repaired, as specified in table 8 to this subpart.(7) You must keep a record of all transferred liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) For continuous process vents subject to table 3 to this subpart, keep records of the occurrence and duration of each startup and shutdown of operation of process equipment, or of air pollution control and monitoring equipment.(9) If you are subject to the equipment leak requirements specified in § 63.11495(a)(6), then you must keep records as specified in paragraphs (c)(9)(i) through (vii) of this section instead of the records specified in paragraph (c)(1)(i) of this section.(i) Keep a list, summary description, or diagram(s) showing the location and identification number of all equipment in organic HAP service at the facility and the information in paragraphs (c)(9)(i)(A) through (D) of this section.(A) Identification of equipment designated as unsafe to monitor, difficult to monitor, unsafe to inspect, difficult to inspect, or unsafe to repair and the plan for monitoring or inspecting this equipment, as applicable.(B) Identification of the equipment in batch process units, for which you do not elect to pressure test the batch product process equipment train.(ii) For leak detection monitoring and inspections required by paragraphs § 63.11495(a)(6) (e.g., monitoring using Method 21 of appendix A-7 to part 60 of this chapter; visible, audible, or olfactory monitoring; closed vent system inspections; and batch process unit monitoring), record the date of the monitoring or inspection and include a statement of whether leaks were detected. If no leaks are detected, records of the monitoring and inspection results are not required.(iii) When each leak is detected as specified in § 63.11495(a)(6), the following information must be recorded:(A) The instrument and the equipment identification number and the operator name, initials, or identification number.(D) Maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A-7 of this chapter after it is successfully repaired or determined to be nonrepairable.(E) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(1) You may develop a written procedure that identifies the conditions that justify a delay of repair. In such cases, reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(2) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked on-site before depletion and the reason for depletion.(iv) For each pressure relief device subject to the provisions in § 63.165(e), you must keep the records specified in paragraphs (c)(9)(iv)(A) through (C) of this section.(A) Records of the prevention measures implemented as required in § 63.165(e)(3)(ii).(C) For each release to the atmosphere, you must keep the records specified in paragraphs (c)(9)(iv)(C)(1) through (4) of this section.(1) The start and end time and date of each pressure release to the atmosphere.(2) Records of any data, assumptions, and calculations used to estimate of the mass quantity of each organic HAP released during the event.(3) Records of the root cause analysis and corrective action analysis conducted as required in § 63.165(e)(3)(iii), including an identification of the affected facility, a statement noting whether the event resulted from the same root cause(s) identified in a previous analysis and either a description of the recommended corrective action(s) or an explanation of why corrective action is not necessary under § 63.165(e)(7)(i).(4) For any corrective action analysis for which implementation of corrective actions are required in § 63.165(e)(7), a description of the corrective action(s) completed within the first 45 days following the discharge and, for action(s) not already completed, a schedule for implementation, including proposed commencement and completion dates.(v) If you own or operate a batch product process and elect to pressure test the batch product process equipment train to demonstrate compliance with § 63.11495(a)(6), you are exempt from the requirements of paragraphs (c)(9)(i) through (iv) of this section. Instead, you must maintain records of the following information:(B) The dates of each pressure test required in § 63.178(b), the test pressure, and the pressure drop observed during the test.(C) When a batch product process equipment train does not pass two consecutive pressure tests, the following information must be recorded:(1) The date of each pressure test and the date of each leak repair attempt.(2) Repair methods applied in each attempt to repair the leak.(3) The reason for the delay of repair.(4) The expected date for delivery of the replacement equipment and the actual date of delivery of the replacement equipment.(5) The date of successful repair.(vi) You must maintain records of the information specified in paragraphs (c)(9)(vi)(A) through (C) of this section for closed vent systems and control devices subject to the provisions of § 63.172. The records specified in paragraph (c)(9)(vi)(A) of this section must be retained for the life of the equipment.(A) The design specifications and performance demonstrations specified in paragraphs (c)(9)(vi)(A)(1) through (4) of this section.(1) Detailed schematics, design specifications of the control device, and piping and instrumentation diagrams.(2) The dates and descriptions of any changes in the design specifications.(3) The flare design (i.e., steam-assisted, air-assisted, or non-assisted) and the results of the compliance demonstration required by subpart SS of this part.(4) A description of the parameter or parameters monitored, as required in § 63.172(e), to ensure that control devices are operated and maintained in conformance with their design and an explanation of why that parameter (or parameters) was selected for the monitoring.(B) Records of operation of closed vent systems and control devices, as specified in paragraphs (c)(9)(vi)(B)(1) through (3) of this section.(1) Dates and durations when the closed vent systems and control devices required in § 63.11495(a)(6) are not operated as designed as indicated by the monitored parameters, including periods when a flare pilot light system does not have a flame.(2) Dates and durations during which the monitoring system or monitoring device is inoperative.(3) Dates and durations of startups and shutdowns of control devices required in § 63.11495(a)(6).(C) Records of inspections of closed vent systems subject to the provisions of § 63.172, as specified in paragraphs (c)(9)(vi)(C)(1) and (2) of this section.(1) For each inspection conducted in accordance with the provisions of § 63.172(f)(1) or (2) during which leaks were detected, the information specified in paragraph (c)(9)(iii) of this section must be recorded.(2) For each flow event from a bypass line subject to the requirements in § 63.172(j), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements in § 63.11495(a)(6), you must include an estimate of the volume of gas, the concentration of organic HAP in the gas, and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(vii) If you choose to comply with the requirements of § 63.179, you must maintain the following records:(C) A description of the system used to create a negative pressure in the enclosure to ensure that all emissions are routed to the control device.(10) For each flow event from a bypass line subject to the requirements in § 63.11495(e), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements specified in §§ 63.11495 through 63.11499, you must include an estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must keep records as specified in § 63.104(f)(3) instead of the heat exchange system records specified in paragraphs (c)(1)(ii) and (6) of this section.
-
(iv) Records of CPMS (if a CPMS is used to demonstrate compliance) calibration checks and adjustments and maintenance performed on CPMS as required by § 63.10(b)(2)(x) and (xi).
-
(i) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi), (vii), (x), and (xi). The CEMS must allow the amount of excess zero (low-level) and high-level calibration drift measured at the interval checks to be quantified and recorded.
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vii) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi) that apply to your continuous monitoring system.
-
(c) In addition to the general records required by § 63.10(b)(2)(iii) and (vi) through (xiv), the owner or operator must maintain records of the information in paragraphs (c)(1) through (8) of this section:(1) Records of black liquor solids firing rates in units of Mg/d or ton/d for all recovery furnaces and semichemical combustion units;(2) Records of CaO production rates in units of Mg/d or ton/d for all lime kilns;(3) Records of parameter monitoring data required under § 63.864, including any period when the operating parameter levels were inconsistent with the levels established during the performance test, with a brief explanation of the cause of the monitoring exceedance, the time the monitoring exceedance occurred, the time corrective action was initiated and completed, and the corrective action taken;(4) Records and documentation of supporting calculations for compliance determinations made under § 63.865(a) through (d);(5) Records of parameter operating limits established for each affected source or process unit;(6) Records certifying that an NDCE recovery furnace equipped with a dry ESP system is used to comply with the gaseous organic HAP standard in § 63.862(c)(1);(7) For the bag leak detection system on the hog fuel dryer fabric filter at Cosmo Specialty Fibers' Cosmopolis, Washington facility (Emission Unit no. HD-14), records of each alarm, the time of the alarm, the time corrective action was initiated and completed, and a brief description of the cause of the alarm and the corrective action taken; and(8) Records demonstrating compliance with the requirement in § 63.864(e)(1) to maintain proper operation of an ESP's AVC.
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
-
(1) Records described in § 63.10(b)(2)(vi) through (xi).
Citations to §63.10(b)(2)(xii)
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(c) You must maintain files of all information required by this subpart for at least 5 years following the date of each occurrence according to the requirements in § 63.10(b)(1). If you are subject, you must comply with the recordkeeping and reporting requirements of § 63.10(b)(2)(iii) and (vi) through (xiv), and the applicable requirements specified in paragraphs (c)(1) through (11) of this section.(1) For each CMPU subject to this subpart, you must keep the records specified in paragraphs (c)(1)(i) through (viii) of this section.(i) Except as specified in paragraph (c)(9) of this section, records of management practice inspections, repairs, and reasons for any delay of repair, as specified in § 63.11495(a)(5).(ii) Except as specified in paragraph (c)(11) of this section, records of small heat exchange system inspections, demonstrations of indications of leaks that do not constitute leaks, repairs, and reasons for any delay in repair as specified in § 63.11495(b).(iii) If batch process vent emissions are less than 10,000 lb/yr for a CMPU, records of batch process vent emission calculations, as specified in § 63.11496(a)(1), the number of batches operated each month, as specified in § 63.11496(a)(3), and any updated emissions calculations, as specified in § 63.11496(a)(3). Alternatively, keep records of the worst-case processes or organic HAP usage, as specified in § 63.11496(a)(2) and (4), respectively.(iv) Records of all TRE calculations for continuous process vents as specified in § 63.11496(b)(2).(v) Records of metal HAP emission calculations as specified in § 63.11496(f)(1) and (2). If total uncontrolled metal HAP process vent emissions from a CMPU subject to this subpart are estimated to be less than 400 lb/yr, also keep records of either the number of batches per month or operating hours, as specified in § 63.11496(f)(2).(vi) Records identifying wastewater streams and the type of treatment they receive, as specified in table 6 to this subpart.(vii) Before April 1, 2029, records of the date, time, and duration of each malfunction of operation of process equipment, control devices, recovery devices, or continuous monitoring systems used to comply with this subpart that causes a failure to meet a standard. The record must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. After April 1, 2029, for any deviation, records of the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions.(viii) Before April 1, 2029, records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.11495(d), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. After April 1, 2029, for any deviation, records of actions taken to minimize emissions in accordance with § 63.11495(d), and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) For batch process vents subject to table 2 to this subpart and continuous process vents subject to table 3 to this subpart, you must keep records specified in paragraphs (c)(2)(i) or (ii) of this section, as applicable.(i) If you route emissions to a control device other than a flare, keep records of performance tests, if applicable, as specified in § 63.998(a)(2)(ii) and (4), keep records of the monitoring system and the monitored parameters, as specified in § 63.998(b) and (c), and keep records of the closed-vent system, as specified in § 63.998(d)(1). If you use a recovery device to maintain the TRE above 1.0 for a continuous process vent, keep records of monitoring parameters during the TRE index value determination, as specified in § 63.998(a)(3).(ii) If you route emissions to a flare, keep records of the flare compliance assessment, as specified in § 63.998(a)(1)(i), keep records of the pilot flame monitoring, as specified in § 63.998(a)(1)(ii) and (iii), and keep records of the closed-vent system, as specified in § 63.998(d)(1).(3) For metal HAP process vents subject to table 4 to this subpart, you must keep records specified in paragraph (c)(3)(i) or (ii) of this section, as applicable.(i) For a new source using a control device other than a baghouse and for any existing source, maintain a monitoring plan, as specified in § 63.11496(f)(3)(i), and keep records of monitoring results, as specified in § 63.11496(f)(3).(ii) For a new source using a baghouse to control metal HAP emissions, keep a site-specific monitoring plan, as specified in §§ 63.11496(f)(4) and 63.11410(g), and keep records of bag leak detection systems, as specified in §§ 63.11496(f)(4) and 63.11410(g)(4).(4) For each storage tank subject to table 5 to this subpart, you must keep records specified in paragraphs (c)(4)(i) through (vii) of this section, as applicable.(i) Keep records of the vessel dimensions, capacity, and liquid stored, as specified in § 63.1065(a).(ii) Keep records of each inspection of an internal floating roof, as specified in § 63.1065(b)(1).(iii) Keep records of each seal gap measurement for external floating roofs, as specified in § 63.1065(b)(2), and keep records of inspections of external floating roofs, as specified in § 63.1065(b)(1).(iv) If you vent emissions to a control device other than a flare, keep records of the operating plan and measured parameter values, as specified in §§ 63.985(c) and 63.998(d)(2).(v) If you vent emissions to a flare, keep records of all periods of operation during which the flare pilot flame is absent, as specified in §§ 63.987(c) and 63.998(a)(1), and keep records of closed-vent systems, as specified in § 63.998(d)(1).(vi) For periods of planned routine maintenance of a control device, keep records of the day and time at which each maintenance period begins and ends, and keep records of the type of maintenance performed, as specified in § 63.11497(b)(3).(vii) For each pressure vessel subject to the requirements of § 63.11497(f) you must keep records as specified in paragraphs (c)(4)(vii)(A) and (B) of this section.(A) The date of each performance test conducted according to § 63.11497(f)(2).(B) The record of each performance test conducted according to § 63.11497(f)(2), including the following:(1) Date each defect was detected and the instrument reading (in ppmv) during the performance test.(2) Date of the next performance test that shows the instrument reading is less than 500 ppmv and the instrument reading (in ppmv) during the performance test.(3) Start and end dates of each period after the date in paragraph (c)(4)(ix)(B)(1) of this section when the pressure vessel was completely empty.(4) Estimated emissions from each defect.(5) For each wastewater stream subject to item 2 in table 6 to this subpart, keep records of the wastewater stream identification and the disposition of the organic phase(s), as specified in item 2 to table 6 to this subpart.(6) Except as specified in paragraph (c)(11) of this section, for each large heat exchange system subject to table 8 to this subpart, you must keep records of detected leaks; the date the leak was detected; if demonstrated not to be a leak, the basis for that determination; the date of efforts to repair the leak; and the date the leak is repaired, as specified in table 8 to this subpart.(7) You must keep a record of all transferred liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) For continuous process vents subject to table 3 to this subpart, keep records of the occurrence and duration of each startup and shutdown of operation of process equipment, or of air pollution control and monitoring equipment.(9) If you are subject to the equipment leak requirements specified in § 63.11495(a)(6), then you must keep records as specified in paragraphs (c)(9)(i) through (vii) of this section instead of the records specified in paragraph (c)(1)(i) of this section.(i) Keep a list, summary description, or diagram(s) showing the location and identification number of all equipment in organic HAP service at the facility and the information in paragraphs (c)(9)(i)(A) through (D) of this section.(A) Identification of equipment designated as unsafe to monitor, difficult to monitor, unsafe to inspect, difficult to inspect, or unsafe to repair and the plan for monitoring or inspecting this equipment, as applicable.(B) Identification of the equipment in batch process units, for which you do not elect to pressure test the batch product process equipment train.(ii) For leak detection monitoring and inspections required by paragraphs § 63.11495(a)(6) (e.g., monitoring using Method 21 of appendix A-7 to part 60 of this chapter; visible, audible, or olfactory monitoring; closed vent system inspections; and batch process unit monitoring), record the date of the monitoring or inspection and include a statement of whether leaks were detected. If no leaks are detected, records of the monitoring and inspection results are not required.(iii) When each leak is detected as specified in § 63.11495(a)(6), the following information must be recorded:(A) The instrument and the equipment identification number and the operator name, initials, or identification number.(D) Maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A-7 of this chapter after it is successfully repaired or determined to be nonrepairable.(E) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(1) You may develop a written procedure that identifies the conditions that justify a delay of repair. In such cases, reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(2) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked on-site before depletion and the reason for depletion.(iv) For each pressure relief device subject to the provisions in § 63.165(e), you must keep the records specified in paragraphs (c)(9)(iv)(A) through (C) of this section.(A) Records of the prevention measures implemented as required in § 63.165(e)(3)(ii).(C) For each release to the atmosphere, you must keep the records specified in paragraphs (c)(9)(iv)(C)(1) through (4) of this section.(1) The start and end time and date of each pressure release to the atmosphere.(2) Records of any data, assumptions, and calculations used to estimate of the mass quantity of each organic HAP released during the event.(3) Records of the root cause analysis and corrective action analysis conducted as required in § 63.165(e)(3)(iii), including an identification of the affected facility, a statement noting whether the event resulted from the same root cause(s) identified in a previous analysis and either a description of the recommended corrective action(s) or an explanation of why corrective action is not necessary under § 63.165(e)(7)(i).(4) For any corrective action analysis for which implementation of corrective actions are required in § 63.165(e)(7), a description of the corrective action(s) completed within the first 45 days following the discharge and, for action(s) not already completed, a schedule for implementation, including proposed commencement and completion dates.(v) If you own or operate a batch product process and elect to pressure test the batch product process equipment train to demonstrate compliance with § 63.11495(a)(6), you are exempt from the requirements of paragraphs (c)(9)(i) through (iv) of this section. Instead, you must maintain records of the following information:(B) The dates of each pressure test required in § 63.178(b), the test pressure, and the pressure drop observed during the test.(C) When a batch product process equipment train does not pass two consecutive pressure tests, the following information must be recorded:(1) The date of each pressure test and the date of each leak repair attempt.(2) Repair methods applied in each attempt to repair the leak.(3) The reason for the delay of repair.(4) The expected date for delivery of the replacement equipment and the actual date of delivery of the replacement equipment.(5) The date of successful repair.(vi) You must maintain records of the information specified in paragraphs (c)(9)(vi)(A) through (C) of this section for closed vent systems and control devices subject to the provisions of § 63.172. The records specified in paragraph (c)(9)(vi)(A) of this section must be retained for the life of the equipment.(A) The design specifications and performance demonstrations specified in paragraphs (c)(9)(vi)(A)(1) through (4) of this section.(1) Detailed schematics, design specifications of the control device, and piping and instrumentation diagrams.(2) The dates and descriptions of any changes in the design specifications.(3) The flare design (i.e., steam-assisted, air-assisted, or non-assisted) and the results of the compliance demonstration required by subpart SS of this part.(4) A description of the parameter or parameters monitored, as required in § 63.172(e), to ensure that control devices are operated and maintained in conformance with their design and an explanation of why that parameter (or parameters) was selected for the monitoring.(B) Records of operation of closed vent systems and control devices, as specified in paragraphs (c)(9)(vi)(B)(1) through (3) of this section.(1) Dates and durations when the closed vent systems and control devices required in § 63.11495(a)(6) are not operated as designed as indicated by the monitored parameters, including periods when a flare pilot light system does not have a flame.(2) Dates and durations during which the monitoring system or monitoring device is inoperative.(3) Dates and durations of startups and shutdowns of control devices required in § 63.11495(a)(6).(C) Records of inspections of closed vent systems subject to the provisions of § 63.172, as specified in paragraphs (c)(9)(vi)(C)(1) and (2) of this section.(1) For each inspection conducted in accordance with the provisions of § 63.172(f)(1) or (2) during which leaks were detected, the information specified in paragraph (c)(9)(iii) of this section must be recorded.(2) For each flow event from a bypass line subject to the requirements in § 63.172(j), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements in § 63.11495(a)(6), you must include an estimate of the volume of gas, the concentration of organic HAP in the gas, and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(vii) If you choose to comply with the requirements of § 63.179, you must maintain the following records:(C) A description of the system used to create a negative pressure in the enclosure to ensure that all emissions are routed to the control device.(10) For each flow event from a bypass line subject to the requirements in § 63.11495(e), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements specified in §§ 63.11495 through 63.11499, you must include an estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must keep records as specified in § 63.104(f)(3) instead of the heat exchange system records specified in paragraphs (c)(1)(ii) and (6) of this section.
-
(c) In addition to the general records required by § 63.10(b)(2)(iii) and (vi) through (xiv), the owner or operator must maintain records of the information in paragraphs (c)(1) through (8) of this section:(1) Records of black liquor solids firing rates in units of Mg/d or ton/d for all recovery furnaces and semichemical combustion units;(2) Records of CaO production rates in units of Mg/d or ton/d for all lime kilns;(3) Records of parameter monitoring data required under § 63.864, including any period when the operating parameter levels were inconsistent with the levels established during the performance test, with a brief explanation of the cause of the monitoring exceedance, the time the monitoring exceedance occurred, the time corrective action was initiated and completed, and the corrective action taken;(4) Records and documentation of supporting calculations for compliance determinations made under § 63.865(a) through (d);(5) Records of parameter operating limits established for each affected source or process unit;(6) Records certifying that an NDCE recovery furnace equipped with a dry ESP system is used to comply with the gaseous organic HAP standard in § 63.862(c)(1);(7) For the bag leak detection system on the hog fuel dryer fabric filter at Cosmo Specialty Fibers' Cosmopolis, Washington facility (Emission Unit no. HD-14), records of each alarm, the time of the alarm, the time corrective action was initiated and completed, and a brief description of the cause of the alarm and the corrective action taken; and(8) Records demonstrating compliance with the requirement in § 63.864(e)(1) to maintain proper operation of an ESP's AVC.
Citations to §63.10(b)(2)(xiii)
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(c) You must maintain files of all information required by this subpart for at least 5 years following the date of each occurrence according to the requirements in § 63.10(b)(1). If you are subject, you must comply with the recordkeeping and reporting requirements of § 63.10(b)(2)(iii) and (vi) through (xiv), and the applicable requirements specified in paragraphs (c)(1) through (11) of this section.(1) For each CMPU subject to this subpart, you must keep the records specified in paragraphs (c)(1)(i) through (viii) of this section.(i) Except as specified in paragraph (c)(9) of this section, records of management practice inspections, repairs, and reasons for any delay of repair, as specified in § 63.11495(a)(5).(ii) Except as specified in paragraph (c)(11) of this section, records of small heat exchange system inspections, demonstrations of indications of leaks that do not constitute leaks, repairs, and reasons for any delay in repair as specified in § 63.11495(b).(iii) If batch process vent emissions are less than 10,000 lb/yr for a CMPU, records of batch process vent emission calculations, as specified in § 63.11496(a)(1), the number of batches operated each month, as specified in § 63.11496(a)(3), and any updated emissions calculations, as specified in § 63.11496(a)(3). Alternatively, keep records of the worst-case processes or organic HAP usage, as specified in § 63.11496(a)(2) and (4), respectively.(iv) Records of all TRE calculations for continuous process vents as specified in § 63.11496(b)(2).(v) Records of metal HAP emission calculations as specified in § 63.11496(f)(1) and (2). If total uncontrolled metal HAP process vent emissions from a CMPU subject to this subpart are estimated to be less than 400 lb/yr, also keep records of either the number of batches per month or operating hours, as specified in § 63.11496(f)(2).(vi) Records identifying wastewater streams and the type of treatment they receive, as specified in table 6 to this subpart.(vii) Before April 1, 2029, records of the date, time, and duration of each malfunction of operation of process equipment, control devices, recovery devices, or continuous monitoring systems used to comply with this subpart that causes a failure to meet a standard. The record must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. After April 1, 2029, for any deviation, records of the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions.(viii) Before April 1, 2029, records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.11495(d), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. After April 1, 2029, for any deviation, records of actions taken to minimize emissions in accordance with § 63.11495(d), and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) For batch process vents subject to table 2 to this subpart and continuous process vents subject to table 3 to this subpart, you must keep records specified in paragraphs (c)(2)(i) or (ii) of this section, as applicable.(i) If you route emissions to a control device other than a flare, keep records of performance tests, if applicable, as specified in § 63.998(a)(2)(ii) and (4), keep records of the monitoring system and the monitored parameters, as specified in § 63.998(b) and (c), and keep records of the closed-vent system, as specified in § 63.998(d)(1). If you use a recovery device to maintain the TRE above 1.0 for a continuous process vent, keep records of monitoring parameters during the TRE index value determination, as specified in § 63.998(a)(3).(ii) If you route emissions to a flare, keep records of the flare compliance assessment, as specified in § 63.998(a)(1)(i), keep records of the pilot flame monitoring, as specified in § 63.998(a)(1)(ii) and (iii), and keep records of the closed-vent system, as specified in § 63.998(d)(1).(3) For metal HAP process vents subject to table 4 to this subpart, you must keep records specified in paragraph (c)(3)(i) or (ii) of this section, as applicable.(i) For a new source using a control device other than a baghouse and for any existing source, maintain a monitoring plan, as specified in § 63.11496(f)(3)(i), and keep records of monitoring results, as specified in § 63.11496(f)(3).(ii) For a new source using a baghouse to control metal HAP emissions, keep a site-specific monitoring plan, as specified in §§ 63.11496(f)(4) and 63.11410(g), and keep records of bag leak detection systems, as specified in §§ 63.11496(f)(4) and 63.11410(g)(4).(4) For each storage tank subject to table 5 to this subpart, you must keep records specified in paragraphs (c)(4)(i) through (vii) of this section, as applicable.(i) Keep records of the vessel dimensions, capacity, and liquid stored, as specified in § 63.1065(a).(ii) Keep records of each inspection of an internal floating roof, as specified in § 63.1065(b)(1).(iii) Keep records of each seal gap measurement for external floating roofs, as specified in § 63.1065(b)(2), and keep records of inspections of external floating roofs, as specified in § 63.1065(b)(1).(iv) If you vent emissions to a control device other than a flare, keep records of the operating plan and measured parameter values, as specified in §§ 63.985(c) and 63.998(d)(2).(v) If you vent emissions to a flare, keep records of all periods of operation during which the flare pilot flame is absent, as specified in §§ 63.987(c) and 63.998(a)(1), and keep records of closed-vent systems, as specified in § 63.998(d)(1).(vi) For periods of planned routine maintenance of a control device, keep records of the day and time at which each maintenance period begins and ends, and keep records of the type of maintenance performed, as specified in § 63.11497(b)(3).(vii) For each pressure vessel subject to the requirements of § 63.11497(f) you must keep records as specified in paragraphs (c)(4)(vii)(A) and (B) of this section.(A) The date of each performance test conducted according to § 63.11497(f)(2).(B) The record of each performance test conducted according to § 63.11497(f)(2), including the following:(1) Date each defect was detected and the instrument reading (in ppmv) during the performance test.(2) Date of the next performance test that shows the instrument reading is less than 500 ppmv and the instrument reading (in ppmv) during the performance test.(3) Start and end dates of each period after the date in paragraph (c)(4)(ix)(B)(1) of this section when the pressure vessel was completely empty.(4) Estimated emissions from each defect.(5) For each wastewater stream subject to item 2 in table 6 to this subpart, keep records of the wastewater stream identification and the disposition of the organic phase(s), as specified in item 2 to table 6 to this subpart.(6) Except as specified in paragraph (c)(11) of this section, for each large heat exchange system subject to table 8 to this subpart, you must keep records of detected leaks; the date the leak was detected; if demonstrated not to be a leak, the basis for that determination; the date of efforts to repair the leak; and the date the leak is repaired, as specified in table 8 to this subpart.(7) You must keep a record of all transferred liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) For continuous process vents subject to table 3 to this subpart, keep records of the occurrence and duration of each startup and shutdown of operation of process equipment, or of air pollution control and monitoring equipment.(9) If you are subject to the equipment leak requirements specified in § 63.11495(a)(6), then you must keep records as specified in paragraphs (c)(9)(i) through (vii) of this section instead of the records specified in paragraph (c)(1)(i) of this section.(i) Keep a list, summary description, or diagram(s) showing the location and identification number of all equipment in organic HAP service at the facility and the information in paragraphs (c)(9)(i)(A) through (D) of this section.(A) Identification of equipment designated as unsafe to monitor, difficult to monitor, unsafe to inspect, difficult to inspect, or unsafe to repair and the plan for monitoring or inspecting this equipment, as applicable.(B) Identification of the equipment in batch process units, for which you do not elect to pressure test the batch product process equipment train.(ii) For leak detection monitoring and inspections required by paragraphs § 63.11495(a)(6) (e.g., monitoring using Method 21 of appendix A-7 to part 60 of this chapter; visible, audible, or olfactory monitoring; closed vent system inspections; and batch process unit monitoring), record the date of the monitoring or inspection and include a statement of whether leaks were detected. If no leaks are detected, records of the monitoring and inspection results are not required.(iii) When each leak is detected as specified in § 63.11495(a)(6), the following information must be recorded:(A) The instrument and the equipment identification number and the operator name, initials, or identification number.(D) Maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A-7 of this chapter after it is successfully repaired or determined to be nonrepairable.(E) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(1) You may develop a written procedure that identifies the conditions that justify a delay of repair. In such cases, reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(2) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked on-site before depletion and the reason for depletion.(iv) For each pressure relief device subject to the provisions in § 63.165(e), you must keep the records specified in paragraphs (c)(9)(iv)(A) through (C) of this section.(A) Records of the prevention measures implemented as required in § 63.165(e)(3)(ii).(C) For each release to the atmosphere, you must keep the records specified in paragraphs (c)(9)(iv)(C)(1) through (4) of this section.(1) The start and end time and date of each pressure release to the atmosphere.(2) Records of any data, assumptions, and calculations used to estimate of the mass quantity of each organic HAP released during the event.(3) Records of the root cause analysis and corrective action analysis conducted as required in § 63.165(e)(3)(iii), including an identification of the affected facility, a statement noting whether the event resulted from the same root cause(s) identified in a previous analysis and either a description of the recommended corrective action(s) or an explanation of why corrective action is not necessary under § 63.165(e)(7)(i).(4) For any corrective action analysis for which implementation of corrective actions are required in § 63.165(e)(7), a description of the corrective action(s) completed within the first 45 days following the discharge and, for action(s) not already completed, a schedule for implementation, including proposed commencement and completion dates.(v) If you own or operate a batch product process and elect to pressure test the batch product process equipment train to demonstrate compliance with § 63.11495(a)(6), you are exempt from the requirements of paragraphs (c)(9)(i) through (iv) of this section. Instead, you must maintain records of the following information:(B) The dates of each pressure test required in § 63.178(b), the test pressure, and the pressure drop observed during the test.(C) When a batch product process equipment train does not pass two consecutive pressure tests, the following information must be recorded:(1) The date of each pressure test and the date of each leak repair attempt.(2) Repair methods applied in each attempt to repair the leak.(3) The reason for the delay of repair.(4) The expected date for delivery of the replacement equipment and the actual date of delivery of the replacement equipment.(5) The date of successful repair.(vi) You must maintain records of the information specified in paragraphs (c)(9)(vi)(A) through (C) of this section for closed vent systems and control devices subject to the provisions of § 63.172. The records specified in paragraph (c)(9)(vi)(A) of this section must be retained for the life of the equipment.(A) The design specifications and performance demonstrations specified in paragraphs (c)(9)(vi)(A)(1) through (4) of this section.(1) Detailed schematics, design specifications of the control device, and piping and instrumentation diagrams.(2) The dates and descriptions of any changes in the design specifications.(3) The flare design (i.e., steam-assisted, air-assisted, or non-assisted) and the results of the compliance demonstration required by subpart SS of this part.(4) A description of the parameter or parameters monitored, as required in § 63.172(e), to ensure that control devices are operated and maintained in conformance with their design and an explanation of why that parameter (or parameters) was selected for the monitoring.(B) Records of operation of closed vent systems and control devices, as specified in paragraphs (c)(9)(vi)(B)(1) through (3) of this section.(1) Dates and durations when the closed vent systems and control devices required in § 63.11495(a)(6) are not operated as designed as indicated by the monitored parameters, including periods when a flare pilot light system does not have a flame.(2) Dates and durations during which the monitoring system or monitoring device is inoperative.(3) Dates and durations of startups and shutdowns of control devices required in § 63.11495(a)(6).(C) Records of inspections of closed vent systems subject to the provisions of § 63.172, as specified in paragraphs (c)(9)(vi)(C)(1) and (2) of this section.(1) For each inspection conducted in accordance with the provisions of § 63.172(f)(1) or (2) during which leaks were detected, the information specified in paragraph (c)(9)(iii) of this section must be recorded.(2) For each flow event from a bypass line subject to the requirements in § 63.172(j), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements in § 63.11495(a)(6), you must include an estimate of the volume of gas, the concentration of organic HAP in the gas, and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(vii) If you choose to comply with the requirements of § 63.179, you must maintain the following records:(C) A description of the system used to create a negative pressure in the enclosure to ensure that all emissions are routed to the control device.(10) For each flow event from a bypass line subject to the requirements in § 63.11495(e), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements specified in §§ 63.11495 through 63.11499, you must include an estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must keep records as specified in § 63.104(f)(3) instead of the heat exchange system records specified in paragraphs (c)(1)(ii) and (6) of this section.
-
(c) In addition to the general records required by § 63.10(b)(2)(iii) and (vi) through (xiv), the owner or operator must maintain records of the information in paragraphs (c)(1) through (8) of this section:(1) Records of black liquor solids firing rates in units of Mg/d or ton/d for all recovery furnaces and semichemical combustion units;(2) Records of CaO production rates in units of Mg/d or ton/d for all lime kilns;(3) Records of parameter monitoring data required under § 63.864, including any period when the operating parameter levels were inconsistent with the levels established during the performance test, with a brief explanation of the cause of the monitoring exceedance, the time the monitoring exceedance occurred, the time corrective action was initiated and completed, and the corrective action taken;(4) Records and documentation of supporting calculations for compliance determinations made under § 63.865(a) through (d);(5) Records of parameter operating limits established for each affected source or process unit;(6) Records certifying that an NDCE recovery furnace equipped with a dry ESP system is used to comply with the gaseous organic HAP standard in § 63.862(c)(1);(7) For the bag leak detection system on the hog fuel dryer fabric filter at Cosmo Specialty Fibers' Cosmopolis, Washington facility (Emission Unit no. HD-14), records of each alarm, the time of the alarm, the time corrective action was initiated and completed, and a brief description of the cause of the alarm and the corrective action taken; and(8) Records demonstrating compliance with the requirement in § 63.864(e)(1) to maintain proper operation of an ESP's AVC.
Citations to §63.10(b)(2)(xiv)
-
(1) In accordance with 40 CFR 63.10(b)(2)(xiv), a copy of each notification or report that you submit to comply with this subpart. You must also keep records of all supporting documentation for the initial Notifications of Compliance Status, semiannual compliance reports, or quarterly compliance reports that you submit.
-
(1) Records supporting your initial notification of applicability and your notification of compliance status according to § 63.10(b)(2)(xiv).
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(1) As required in § 63.10(b)(2)(xiv), you must keep a copy of each notification and report that you submitted to comply with this subpart and all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted.
-
(1) A copy of each notification that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of any Initial Notification and Notification of Compliance Status that you submitted and all documentation supporting those notifications, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) As required in § 63.10(b)(2)(xiv), you must keep a copy of each notification that you submitted to comply with this subpart and all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted.
-
(c) You must maintain files of all information required by this subpart for at least 5 years following the date of each occurrence according to the requirements in § 63.10(b)(1). If you are subject, you must comply with the recordkeeping and reporting requirements of § 63.10(b)(2)(iii) and (vi) through (xiv), and the applicable requirements specified in paragraphs (c)(1) through (11) of this section.(1) For each CMPU subject to this subpart, you must keep the records specified in paragraphs (c)(1)(i) through (viii) of this section.(i) Except as specified in paragraph (c)(9) of this section, records of management practice inspections, repairs, and reasons for any delay of repair, as specified in § 63.11495(a)(5).(ii) Except as specified in paragraph (c)(11) of this section, records of small heat exchange system inspections, demonstrations of indications of leaks that do not constitute leaks, repairs, and reasons for any delay in repair as specified in § 63.11495(b).(iii) If batch process vent emissions are less than 10,000 lb/yr for a CMPU, records of batch process vent emission calculations, as specified in § 63.11496(a)(1), the number of batches operated each month, as specified in § 63.11496(a)(3), and any updated emissions calculations, as specified in § 63.11496(a)(3). Alternatively, keep records of the worst-case processes or organic HAP usage, as specified in § 63.11496(a)(2) and (4), respectively.(iv) Records of all TRE calculations for continuous process vents as specified in § 63.11496(b)(2).(v) Records of metal HAP emission calculations as specified in § 63.11496(f)(1) and (2). If total uncontrolled metal HAP process vent emissions from a CMPU subject to this subpart are estimated to be less than 400 lb/yr, also keep records of either the number of batches per month or operating hours, as specified in § 63.11496(f)(2).(vi) Records identifying wastewater streams and the type of treatment they receive, as specified in table 6 to this subpart.(vii) Before April 1, 2029, records of the date, time, and duration of each malfunction of operation of process equipment, control devices, recovery devices, or continuous monitoring systems used to comply with this subpart that causes a failure to meet a standard. The record must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. After April 1, 2029, for any deviation, records of the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions.(viii) Before April 1, 2029, records of actions taken during periods of malfunction to minimize emissions in accordance with § 63.11495(d), including corrective actions to restore malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. After April 1, 2029, for any deviation, records of actions taken to minimize emissions in accordance with § 63.11495(d), and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) For batch process vents subject to table 2 to this subpart and continuous process vents subject to table 3 to this subpart, you must keep records specified in paragraphs (c)(2)(i) or (ii) of this section, as applicable.(i) If you route emissions to a control device other than a flare, keep records of performance tests, if applicable, as specified in § 63.998(a)(2)(ii) and (4), keep records of the monitoring system and the monitored parameters, as specified in § 63.998(b) and (c), and keep records of the closed-vent system, as specified in § 63.998(d)(1). If you use a recovery device to maintain the TRE above 1.0 for a continuous process vent, keep records of monitoring parameters during the TRE index value determination, as specified in § 63.998(a)(3).(ii) If you route emissions to a flare, keep records of the flare compliance assessment, as specified in § 63.998(a)(1)(i), keep records of the pilot flame monitoring, as specified in § 63.998(a)(1)(ii) and (iii), and keep records of the closed-vent system, as specified in § 63.998(d)(1).(3) For metal HAP process vents subject to table 4 to this subpart, you must keep records specified in paragraph (c)(3)(i) or (ii) of this section, as applicable.(i) For a new source using a control device other than a baghouse and for any existing source, maintain a monitoring plan, as specified in § 63.11496(f)(3)(i), and keep records of monitoring results, as specified in § 63.11496(f)(3).(ii) For a new source using a baghouse to control metal HAP emissions, keep a site-specific monitoring plan, as specified in §§ 63.11496(f)(4) and 63.11410(g), and keep records of bag leak detection systems, as specified in §§ 63.11496(f)(4) and 63.11410(g)(4).(4) For each storage tank subject to table 5 to this subpart, you must keep records specified in paragraphs (c)(4)(i) through (vii) of this section, as applicable.(i) Keep records of the vessel dimensions, capacity, and liquid stored, as specified in § 63.1065(a).(ii) Keep records of each inspection of an internal floating roof, as specified in § 63.1065(b)(1).(iii) Keep records of each seal gap measurement for external floating roofs, as specified in § 63.1065(b)(2), and keep records of inspections of external floating roofs, as specified in § 63.1065(b)(1).(iv) If you vent emissions to a control device other than a flare, keep records of the operating plan and measured parameter values, as specified in §§ 63.985(c) and 63.998(d)(2).(v) If you vent emissions to a flare, keep records of all periods of operation during which the flare pilot flame is absent, as specified in §§ 63.987(c) and 63.998(a)(1), and keep records of closed-vent systems, as specified in § 63.998(d)(1).(vi) For periods of planned routine maintenance of a control device, keep records of the day and time at which each maintenance period begins and ends, and keep records of the type of maintenance performed, as specified in § 63.11497(b)(3).(vii) For each pressure vessel subject to the requirements of § 63.11497(f) you must keep records as specified in paragraphs (c)(4)(vii)(A) and (B) of this section.(A) The date of each performance test conducted according to § 63.11497(f)(2).(B) The record of each performance test conducted according to § 63.11497(f)(2), including the following:(1) Date each defect was detected and the instrument reading (in ppmv) during the performance test.(2) Date of the next performance test that shows the instrument reading is less than 500 ppmv and the instrument reading (in ppmv) during the performance test.(3) Start and end dates of each period after the date in paragraph (c)(4)(ix)(B)(1) of this section when the pressure vessel was completely empty.(4) Estimated emissions from each defect.(5) For each wastewater stream subject to item 2 in table 6 to this subpart, keep records of the wastewater stream identification and the disposition of the organic phase(s), as specified in item 2 to table 6 to this subpart.(6) Except as specified in paragraph (c)(11) of this section, for each large heat exchange system subject to table 8 to this subpart, you must keep records of detected leaks; the date the leak was detected; if demonstrated not to be a leak, the basis for that determination; the date of efforts to repair the leak; and the date the leak is repaired, as specified in table 8 to this subpart.(7) You must keep a record of all transferred liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) For continuous process vents subject to table 3 to this subpart, keep records of the occurrence and duration of each startup and shutdown of operation of process equipment, or of air pollution control and monitoring equipment.(9) If you are subject to the equipment leak requirements specified in § 63.11495(a)(6), then you must keep records as specified in paragraphs (c)(9)(i) through (vii) of this section instead of the records specified in paragraph (c)(1)(i) of this section.(i) Keep a list, summary description, or diagram(s) showing the location and identification number of all equipment in organic HAP service at the facility and the information in paragraphs (c)(9)(i)(A) through (D) of this section.(A) Identification of equipment designated as unsafe to monitor, difficult to monitor, unsafe to inspect, difficult to inspect, or unsafe to repair and the plan for monitoring or inspecting this equipment, as applicable.(B) Identification of the equipment in batch process units, for which you do not elect to pressure test the batch product process equipment train.(ii) For leak detection monitoring and inspections required by paragraphs § 63.11495(a)(6) (e.g., monitoring using Method 21 of appendix A-7 to part 60 of this chapter; visible, audible, or olfactory monitoring; closed vent system inspections; and batch process unit monitoring), record the date of the monitoring or inspection and include a statement of whether leaks were detected. If no leaks are detected, records of the monitoring and inspection results are not required.(iii) When each leak is detected as specified in § 63.11495(a)(6), the following information must be recorded:(A) The instrument and the equipment identification number and the operator name, initials, or identification number.(D) Maximum instrument reading measured by Method 21 of 40 CFR part 60, appendix A-7 of this chapter after it is successfully repaired or determined to be nonrepairable.(E) “Repair delayed” and the reason for the delay if a leak is not repaired within 15 calendar days after discovery of the leak.(1) You may develop a written procedure that identifies the conditions that justify a delay of repair. In such cases, reasons for delay of repair may be documented by citing the relevant sections of the written procedure.(2) If delay of repair was caused by depletion of stocked parts, there must be documentation that the spare parts were sufficiently stocked on-site before depletion and the reason for depletion.(iv) For each pressure relief device subject to the provisions in § 63.165(e), you must keep the records specified in paragraphs (c)(9)(iv)(A) through (C) of this section.(A) Records of the prevention measures implemented as required in § 63.165(e)(3)(ii).(C) For each release to the atmosphere, you must keep the records specified in paragraphs (c)(9)(iv)(C)(1) through (4) of this section.(1) The start and end time and date of each pressure release to the atmosphere.(2) Records of any data, assumptions, and calculations used to estimate of the mass quantity of each organic HAP released during the event.(3) Records of the root cause analysis and corrective action analysis conducted as required in § 63.165(e)(3)(iii), including an identification of the affected facility, a statement noting whether the event resulted from the same root cause(s) identified in a previous analysis and either a description of the recommended corrective action(s) or an explanation of why corrective action is not necessary under § 63.165(e)(7)(i).(4) For any corrective action analysis for which implementation of corrective actions are required in § 63.165(e)(7), a description of the corrective action(s) completed within the first 45 days following the discharge and, for action(s) not already completed, a schedule for implementation, including proposed commencement and completion dates.(v) If you own or operate a batch product process and elect to pressure test the batch product process equipment train to demonstrate compliance with § 63.11495(a)(6), you are exempt from the requirements of paragraphs (c)(9)(i) through (iv) of this section. Instead, you must maintain records of the following information:(B) The dates of each pressure test required in § 63.178(b), the test pressure, and the pressure drop observed during the test.(C) When a batch product process equipment train does not pass two consecutive pressure tests, the following information must be recorded:(1) The date of each pressure test and the date of each leak repair attempt.(2) Repair methods applied in each attempt to repair the leak.(3) The reason for the delay of repair.(4) The expected date for delivery of the replacement equipment and the actual date of delivery of the replacement equipment.(5) The date of successful repair.(vi) You must maintain records of the information specified in paragraphs (c)(9)(vi)(A) through (C) of this section for closed vent systems and control devices subject to the provisions of § 63.172. The records specified in paragraph (c)(9)(vi)(A) of this section must be retained for the life of the equipment.(A) The design specifications and performance demonstrations specified in paragraphs (c)(9)(vi)(A)(1) through (4) of this section.(1) Detailed schematics, design specifications of the control device, and piping and instrumentation diagrams.(2) The dates and descriptions of any changes in the design specifications.(3) The flare design (i.e., steam-assisted, air-assisted, or non-assisted) and the results of the compliance demonstration required by subpart SS of this part.(4) A description of the parameter or parameters monitored, as required in § 63.172(e), to ensure that control devices are operated and maintained in conformance with their design and an explanation of why that parameter (or parameters) was selected for the monitoring.(B) Records of operation of closed vent systems and control devices, as specified in paragraphs (c)(9)(vi)(B)(1) through (3) of this section.(1) Dates and durations when the closed vent systems and control devices required in § 63.11495(a)(6) are not operated as designed as indicated by the monitored parameters, including periods when a flare pilot light system does not have a flame.(2) Dates and durations during which the monitoring system or monitoring device is inoperative.(3) Dates and durations of startups and shutdowns of control devices required in § 63.11495(a)(6).(C) Records of inspections of closed vent systems subject to the provisions of § 63.172, as specified in paragraphs (c)(9)(vi)(C)(1) and (2) of this section.(1) For each inspection conducted in accordance with the provisions of § 63.172(f)(1) or (2) during which leaks were detected, the information specified in paragraph (c)(9)(iii) of this section must be recorded.(2) For each flow event from a bypass line subject to the requirements in § 63.172(j), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements in § 63.11495(a)(6), you must include an estimate of the volume of gas, the concentration of organic HAP in the gas, and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(vii) If you choose to comply with the requirements of § 63.179, you must maintain the following records:(C) A description of the system used to create a negative pressure in the enclosure to ensure that all emissions are routed to the control device.(10) For each flow event from a bypass line subject to the requirements in § 63.11495(e), you must maintain records sufficient to determine whether or not the detected flow included flow requiring control. For each flow event from a bypass line requiring control that is released either directly to the atmosphere or to a control device not meeting the requirements specified in §§ 63.11495 through 63.11499, you must include an estimate of the volume of gas, the concentration of organic HAP in the gas and the resulting emissions of organic HAP that bypassed the control device using process knowledge and engineering estimates.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must keep records as specified in § 63.104(f)(3) instead of the heat exchange system records specified in paragraphs (c)(1)(ii) and (6) of this section.
-
(2) The records specified in § 63.10(b)(2)(i) through (iii) and (xiv) of the General Provisions of this part.
-
(1) As required in § 63.10(b)(2)(xiv), you must keep a copy of each notification that you submitted to comply with this subpart and all documentation supporting any Initial Notification, Notification of Compliance Status, and annual compliance certifications that you submitted.
-
(1) As required in § 63.10(b)(2)(xiv), you must keep a copy of each notification that you submitted to comply with this subpart and all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted.
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(i) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification of Applicability or NOCSR that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) As required in § 63.10(b)(2)(xiv), you must keep a copy of each notification that you submitted in accordance with paragraph (a) of this section, and all documentation supporting any Notification of Applicability and Notification of Compliance Status that you submitted.
-
(1) As required in § 63.10(b)(2)(xiv), you must keep a copy of each notification that you submitted to comply with this subpart in accordance with paragraph (a) of this section, and all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted.
-
(1) As required in § 63.10(b)(2)(xiv), you must keep a copy of each notification that you submitted to comply with this subpart and all documentation supporting any Initial Notification, Notification of Compliance Status, and semiannual compliance certifications that you submitted.
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any initial notification or notification of compliance status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any initial notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Notification of Compliance Status and compliance report that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirement in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Notification of Compliance Status and periodic report of compliance that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any initial notification or notification of compliance status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status or semiannual compliance report that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any initial notification or notification of compliance status that you submitted, according to the requirements of § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any initial notification or notification of compliance status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(1) and (b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any initial notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(c) In addition to the general records required by § 63.10(b)(2)(iii) and (vi) through (xiv), the owner or operator must maintain records of the information in paragraphs (c)(1) through (8) of this section:(1) Records of black liquor solids firing rates in units of Mg/d or ton/d for all recovery furnaces and semichemical combustion units;(2) Records of CaO production rates in units of Mg/d or ton/d for all lime kilns;(3) Records of parameter monitoring data required under § 63.864, including any period when the operating parameter levels were inconsistent with the levels established during the performance test, with a brief explanation of the cause of the monitoring exceedance, the time the monitoring exceedance occurred, the time corrective action was initiated and completed, and the corrective action taken;(4) Records and documentation of supporting calculations for compliance determinations made under § 63.865(a) through (d);(5) Records of parameter operating limits established for each affected source or process unit;(6) Records certifying that an NDCE recovery furnace equipped with a dry ESP system is used to comply with the gaseous organic HAP standard in § 63.862(c)(1);(7) For the bag leak detection system on the hog fuel dryer fabric filter at Cosmo Specialty Fibers' Cosmopolis, Washington facility (Emission Unit no. HD-14), records of each alarm, the time of the alarm, the time corrective action was initiated and completed, and a brief description of the cause of the alarm and the corrective action taken; and(8) Records demonstrating compliance with the requirement in § 63.864(e)(1) to maintain proper operation of an ESP's AVC.
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(a) You must keep a copy of each notification and report that you submit to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(a) You must keep a copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, as required in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any initial notification or notification of compliance status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any initial notification or notification of compliance status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any Initial Notification or Notification of Compliance Status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
-
(1) A copy of each notification and report that you submitted to comply with this subpart, including all documentation supporting any initial notification or notification of compliance status that you submitted, according to the requirements in § 63.10(b)(2)(xiv).
Citations to §63.10(b)(3)
-
(3) An owner or operator of a stationary source who is in the relevant source category and who determines that the source is not subject to a relevant standard or other requirement established under this part must keep a record as specified in § 63.10(b)(3).
-
(j) You must comply with the following requirements of the general provisions in subpart A of this part: §§ 63.1 through 63.5; § 63.6(a), (b), and (c); § 63.9; § 63.10(a), (b)(1), (b)(2)(xiv), (b)(3), (d)(1) and (4), and (f); and §§ 63.13 through 63.16. Requirements of the general provisions not cited in the preceding sentence do not apply to the owner or operator of a new or existing affected source that is classified as a small foundry.
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
The terms used in this subpart are defined in the CAA; and in this section as follows:
-
(2) The owner or operator of a stationary source that is not subject to this subpart shall keep a record of the applicability determination, as specified in § 63.10(b)(3).
-
(a) This subpart applies to owners and operators of natural gas transmission and storage facilities that transport or store natural gas prior to entering the pipeline to a local distribution company or to a final end user (if there is no local distribution company), and that are major sources of hazardous air pollutants (HAP) emissions as defined in § 63.1271. Emissions for major source determination purposes can be estimated using the maximum natural gas throughput calculated in either paragraph (a)(1) or (2) of this section and paragraphs (a)(3) and (4) of this section. As an alternative to calculating the maximum natural gas throughput, the owner or operator of a new or existing source may use the facility design maximum natural gas throughput to estimate the maximum potential emissions. Other means to determine the facility's major source status are allowed, provided the information is documented and recorded to the Administrator's satisfaction in accordance with § 63.10(b)(3). A compressor station that transports natural gas prior to the point of custody transfer or to a natural gas processing plant (if present) is not considered a part of the natural gas transmission and storage source category. A facility that is determined to be an area source, but subsequently increases its emissions or its potential to emit above the major source levels (without obtaining and complying with other limitations that keep its potential to emit HAP below major source levels), and becomes a major source, must comply with all applicable provisions of this subpart starting on the applicable compliance date specified in paragraph (d) of this section. Nothing in this paragraph is intended to preclude a source from limiting its potential to emit through other appropriate mechanisms that may be available through the permitting authority.(1) Facilities that store natural gas or facilities that transport and store natural gas shall calculate maximum annual facility natural gas throughput using the following equation:(i) -(iii) [Reserved](2) Facilities that only transport natural gas shall calculate the maximum natural gas throughput as the highest annual natural gas throughput over the 5 years prior to June 17, 1999, multiplied by a factor of 1.2.(3) The owner or operator shall maintain records of the annual facility natural gas throughput each year and upon request, submit such records to the Administrator. If the facility annual natural gas throughput increases above the maximum natural gas throughput calculated in paragraph (a)(1) or (a)(2) of this section, the maximum natural gas throughput must be recalculated using the higher throughput multiplied by a factor of 1.2.(4) The owner or operator shall determine the maximum values for other parameters used to calculate potential emissions as the maximum over the same period for which maximum throughput is determined as specified in paragraph (a)(1) or (a)(2) of this section. These parameters shall be based on an annual average or the highest single measured value. For estimating maximum potential emissions from glycol dehydration units, the glycol circulation rate used in the calculation shall be the unit's maximum rate under its physical and operational design consistent with the definition of potential to emit in § 63.2.
-
(b) The owner or operator shall maintain records for each affected source as required by § 63.10(b)(2) and (b)(3) of this part; and(1) All documentation supporting initial notifications and notifications of compliance status under § 63.9;(2) All records of applicability determination, including supporting analyses; and(3) If the owner or operator has been granted a waiver under § 63.8(f)(6), any information demonstrating whether a source is meeting the requirements for a waiver of recordkeeping or reporting requirements.
-
(2) The owner or operator of a stationary source that is not subject to this subpart shall keep a record of the applicability determination, as specified in § 63.10(b)(3) of subpart A of this part.
-
(xi) As required by § 63.10(b)(3), records of any applicability determination, including supporting analyses.
-
(3) Records specified in § 63.10(b)(3); and
-
(1) Facilities that are major or area sources of hazardous air pollutants (HAP) as defined in § 63.761. Emissions for major source determination purposes can be estimated using the maximum natural gas or hydrocarbon liquid throughput, as appropriate, calculated in paragraphs (a)(1)(i) through (iii) of this section. As an alternative to calculating the maximum natural gas or hydrocarbon liquid throughput, the owner or operator of a new or existing source may use the facility's design maximum natural gas or hydrocarbon liquid throughput to estimate the maximum potential emissions. Other means to determine the facility's major source status are allowed, provided the information is documented and recorded to the Administrator's satisfaction in accordance with § 63.10(b)(3). A facility that is determined to be an area source, but subsequently increases its emissions or its potential to emit above the major source levels, and becomes a major source, must comply with all provisions of this subpart applicable to a major source starting on the applicable compliance date specified in paragraph (f) of this section. Nothing in this paragraph is intended to preclude a source from limiting its potential to emit through other appropriate mechanisms that may be available through the permitting authority.(i) If the owner or operator documents, to the Administrator's satisfaction, a decline in annual natural gas or hydrocarbon liquid throughput, as appropriate, each year for the 5 years prior to October 15, 2012, the owner or operator shall calculate the maximum natural gas or hydrocarbon liquid throughput used to determine maximum potential emissions according to the requirements specified in paragraph (a)(1)(i)(A) of this section. In all other circumstances, the owner or operator shall calculate the maximum throughput used to determine whether a facility is a major source in accordance with the requirements specified in paragraph (a)(1)(i)(B) of this section.(A) The maximum natural gas or hydrocarbon liquid throughput is the average of the annual natural gas or hydrocarbon liquid throughput for the 3 years prior to October 15, 2012, multiplied by a factor of 1.2.(B) The maximum natural gas or hydrocarbon liquid throughput is the highest annual natural gas or hydrocarbon liquid throughput over the 5 years prior to October 15, 2012, multiplied by a factor of 1.2.(ii) The owner or operator shall maintain records of the annual facility natural gas or hydrocarbon liquid throughput each year and upon request submit such records to the Administrator. If the facility annual natural gas or hydrocarbon liquid throughput increases above the maximum natural gas or hydrocarbon liquid throughput calculated in paragraph (a)(1)(i)(A) or (a)(1)(i)(B) of this section, the maximum natural gas or hydrocarbon liquid throughput must be recalculated using the higher throughput multiplied by a factor of 1.2.(iii) The owner or operator shall determine the maximum values for other parameters used to calculate emissions as the maximum for the period over which the maximum natural gas or hydrocarbon liquid throughput is determined in accordance with paragraph (a)(1)(i)(A) or (B) of this section. Parameters, other than glycol circulation rate, shall be based on either highest measured values or annual average. For estimating maximum potential emissions from glycol dehydration units, the glycol circulation rate used in the calculation shall be the unit's maximum rate under its physical and operational design consistent with the definition of potential to emit in § 63.2.
-
(2) Records specified in § 63.10(b)(3) of this part for each applicability determination performed by the owner or operator in accordance with the requirements of § 63.820(a) of this subpart, and
Citations to §63.10(b)(b)(3)
-
(j) You must comply with the following requirements of the general provisions in subpart A of this part: §§ 63.1 through 63.5; § 63.6(a), (b), and (c); § 63.9; § 63.10(a), (b)(1), (b)(2)(xiv), (b)(3), (d)(1) and (4), and (f); and §§ 63.13 through 63.16. Requirements of the general provisions not cited in the preceding sentence do not apply to the owner or operator of a new or existing affected source that is classified as a small foundry.
-
(b) In addition to the records required by § 63.10(b)(2)(iii) and (vi) through (xiv) and (b)(3), you must keep records of the information specified in paragraphs (b)(1) through (15) of this section.(1) You must keep records of your written materials specifications according to § 63.10885(a) and records that demonstrate compliance with the requirements for restricted metallic scrap in § 63.10885(a)(1) and/or for the use of general scrap in § 63.10885(a)(2) and for mercury in § 63.10885(b)(1) through (3), as applicable. You must keep records documenting compliance with § 63.10885(b)(4) for scrap that does not contain motor vehicle scrap.(2) If you are subject to the requirements for a site-specific plan for mercury under § 63.10885(b)(1), you must maintain records of the number of mercury switches removed or the weight of mercury recovered from the switches and properly managed, the estimated number of vehicles processed, and an estimate of the percent of mercury switches recovered.(3) If you are subject to the option for approved mercury programs under § 63.10885(b)(2), you must maintain records identifying each scrap provider and documenting the scrap provider's participation in an approved mercury switch removal program. If your scrap provider is a broker, you must maintain records identifying each of the broker's scrap suppliers and documenting the scrap supplier's participation in an approved mercury switch removal program.(4) You must keep records to document use of any binder chemical formulation that does not contain methanol as a specific ingredient of the catalyst formulation for each furfuryl alcohol warm box mold or core making line as required by § 63.10886. These records must be the Material Safety Data Sheet (provided that it contains appropriate information), a certified product data sheet, or a manufacturer's hazardous air pollutant data sheet.(5) You must keep records of the annual quantity and composition of each HAP-containing chemical binder or coating material used to make molds and cores. These records must be copies of purchasing records, Material Safety Data Sheets, or other documentation that provide information on the binder or coating materials used.(6) You must keep records of monthly metal melt production for each calendar year.(7) You must keep a copy of the operation and maintenance plan as required by § 63.10896(a) and records that demonstrate compliance with plan requirements.(8) If you use emissions averaging, you must keep records of the monthly metal melting rate for each furnace at your iron and steel foundry, and records of the calculated pounds of PM or total metal HAP per ton of metal melted for the group of all metal melting furnaces required by § 63.10897(h).(9) If applicable, you must keep records for bag leak detection systems as follows:(i) Records of the bag leak detection system output;(ii) Records of bag leak detection system adjustments, including the date and time of the adjustment, the initial bag leak detection system settings, and the final bag leak detection system settings; and(iii) The date and time of all bag leak detection system alarms, and for each valid alarm, the time you initiated corrective action, the corrective action taken, and the date on which corrective action was completed.(10) You must keep records of capture system inspections and repairs as required by § 63.10897(e).(11) You must keep records demonstrating conformance with your specifications for the operation of CPMS as required by § 63.10897(f).(12) You must keep records of corrective action(s) for exceedances and excursions as required by § 63.10897(g).(13) You must record the results of each inspection and maintenance required by § 63.10897(a) for PM control devices in a logbook (written or electronic format). You must keep the logbook onsite and make the logbook available to the Administrator upon request. You must keep records of the information specified in paragraphs (b)(13)(i) through (iii) of this section.(i) The date and time of each recorded action for a fabric filter, the results of each inspection, and the results of any maintenance performed on the bag filters.(ii) The date and time of each recorded action for a wet or dry electrostatic precipitator (including ductwork), the results of each inspection, and the results of any maintenance performed for the electrostatic precipitator.(iii) The date and time of each recorded action for a wet scrubber (including ductwork), the results of each inspection, and the results of any maintenance performed on the wet scrubber.(14) You must keep records of the site-specific performance evaluation test plan required under § 63.8(d)(2) for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan as required under § 63.8(d)(2)(vi).(15) You must keep the following records for each failure to meet an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.(ii) List of the affected sources or equipment for each failure, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(iii) Actions taken to minimize emissions in accordance with § 63.10896(c), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
Citations to §63.10(b)(d)(1)
-
(j) You must comply with the following requirements of the general provisions in subpart A of this part: §§ 63.1 through 63.5; § 63.6(a), (b), and (c); § 63.9; § 63.10(a), (b)(1), (b)(2)(xiv), (b)(3), (d)(1) and (4), and (f); and §§ 63.13 through 63.16. Requirements of the general provisions not cited in the preceding sentence do not apply to the owner or operator of a new or existing affected source that is classified as a small foundry.
Citations to §63.10(b)(d)(4)
-
(j) You must comply with the following requirements of the general provisions in subpart A of this part: §§ 63.1 through 63.5; § 63.6(a), (b), and (c); § 63.9; § 63.10(a), (b)(1), (b)(2)(xiv), (b)(3), (d)(1) and (4), and (f); and §§ 63.13 through 63.16. Requirements of the general provisions not cited in the preceding sentence do not apply to the owner or operator of a new or existing affected source that is classified as a small foundry.
Citations to §63.10(b)(d)(5)
-
(4) Each owner or operator subject to this subpart is not required to comply with § 63.10(b)(2)(i), (b)(2)(iv), (b)(2)(v), and (d)(5).
Citations to §63.10(b)(d)(f)
-
(j) You must comply with the following requirements of the general provisions in subpart A of this part: §§ 63.1 through 63.5; § 63.6(a), (b), and (c); § 63.9; § 63.10(a), (b)(1), (b)(2)(xiv), (b)(3), (d)(1) and (4), and (f); and §§ 63.13 through 63.16. Requirements of the general provisions not cited in the preceding sentence do not apply to the owner or operator of a new or existing affected source that is classified as a small foundry.
Citations to §63.10(b)(iii)
-
(4) Records of all maintenance on the air pollution control equipment, if applicable, as required in § 63.10(b)(iii).
Citations to §63.10(c)
-
-
-
(vi) Ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) (as applicable in Table 8 to this subpart), (e)(1), and (e)(2)(i).
-
-
-
(7) Ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i) and the requirements of § 63.11585.
-
(v) Records of CPMS as required by § 63.10(c) and § 63.11583(d)(5).
-
(e) A semiannual report as required by § 63.10(e)(3) of the general provisions in subpart A of this part if measured emissions exceed the applicable standard or a monitored parameter varies from the level established during performance testing. The report must contain the information specified in § 63.10(c) of the general provisions, as well as the relevant records required by § 63.1192(b) of this subpart.
-
-
-
(3) Records specified in § 63.10(c) for each monitoring system operated by the owner or operator in accordance with the requirements of § 63.1283(d). Notwithstanding the previous sentence, monitoring data recorded during periods identified in paragraphs (b)(3)(i) through (iv) of this section shall not be included in any average or percent leak rate computed under this subpart. Records shall be kept of the times and durations of all such periods and any other periods during process or control device operation when monitors are not operating or failed to collect required data.(i) Monitoring system breakdowns, repairs, calibration checks, and zero (low-level) and high-level adjustments;(ii) [Reserved](iii) Periods of non-operation resulting in cessation of the emissions to which the monitoring applies; and(iv) Excursions due to invalid data as defined in § 63.1283(d)(6)(iii).
-
-
(c) In addition to the recordkeeping requirements in paragraph (b) of this section, the owner or operator of an affected source equipped with a continuous monitoring system shall maintain all records required by § 63.10(c).
-
(e) As required by § 63.10(e)(3)(v) of this part, the owner or operator shall report semiannually if measured emissions are in excess of the applicable standard or a monitored parameter deviates from the levels established during the performance test. The report shall contain the information specified in § 63.10(c) of this part as well as the additional records required by the recordkeeping requirements of paragraph (d) of this section. When no deviations have occurred, the owner or operator shall submit a report stating that no excess emissions occurred during the reporting period.
-
(6) For each continuous monitoring system, records required by § 63.10(c).
-
-
-
-
(2) Records specified in § 63.10(c) for each CMS operated by the owner or operator in accordance with the requirements of § 63.3350(b), as indicated in Table 2 to subpart JJJJ of part 63.
-
(a) If you own or operate an affected source subject to § 63.362, you must comply with the recordkeeping requirements in § 63.10(a) through (c), according to the applicability in table 6 to this subpart, and in this section. All records required to be maintained by this subpart or a subpart referenced by this subpart shall be maintained in such a manner that they can be readily accessed and are suitable for inspection.
-
(4) Additional records specified in § 63.10(c) for each continuous monitoring system operated by the owner or operator in accordance with § 63.5150(a)(2).
-
(10) Records of 15-minute periods when the pressure was not maintained as required in § 63.544(c) or power was lost to the continuous pressure monitoring system as required in § 63.548(k). Records of which wall is chosen as the windward wall must be included in the records required by § 63.10(c) if a total enclosure located within a larger structure is not impacted by ambient wind.
-
-
(3) Before January 21, 2021, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 20, 2021, the owner or operator shall keep these written procedures on record for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, the owner or operator shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan required under § 63.8(d)(2); and
-
-
-
-
(1) Magnetic tape manufacturing operations that are subject to § 63.703(b) and are not at major sources are not subject to §§ 63.6(e), 63.6(f), 63.6(g), 63.6(i)(4), 63.7, 63.8, 63.9 (c) through (h), 63.10(b)(2), 63.10(c), 63.10(d) (2) through (5), 63.10(e), and 63.11 of subpart A.
-
-
(iii) Ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) (as applicable in Table 10 to this subpart), (e)(1), and (e)(2)(i).
-
-
(3) Records specified in § 63.10(c) for each monitoring system operated by the owner or operator in accordance with the requirements of § 63.773(d). Notwithstanding the requirements of § 63.10(c), monitoring data recorded during periods identified in paragraphs (b)(3)(i) through (iv) of this section shall not be included in any average or percent leak rate computed under this subpart. Records shall be kept of the times and durations of all such periods and any other periods during process or control device operation when monitors are not operating or failed to collect required data.(i) Monitoring system breakdowns, repairs, calibration checks, and zero (low-level) and high-level adjustments;(ii) [Reserved](iii) Periods of non-operation resulting in cessation of the emissions to which the monitoring applies; and(iv) Excursions due to invalid data as defined in § 63.773(d)(6)(iv).
-
(a) Each owner or operator of an affected source shall comply with the applicable recordkeeping and reporting requirements in § 63.10 (a), (b), (d), and (f). Any owner that receives approval pursuant to § 63.783(c) to use an add-on control system to control coating emissions shall also comply with the applicable requirements of § 63.10 (c) and (e). A summary of recordkeeping and reporting requirements is provided in Table 3 of this subpart.
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
-
(3) Records specified in § 63.10(c) of this part for each continuous monitoring system operated by the owner or operator in accordance with the requirements of § 63.828(a) of this subpart.
-
(xii) For a potline equipped with an HF continuous emission monitor, records of information and data required by § 63.10(c);
-
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
Citations to §63.10(c)(1)
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(2) Records described in § 63.10(c)(1) through (6).
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(2)
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(2) Records described in § 63.10(c)(1) through (6).
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(3)
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(2) Records described in § 63.10(c)(1) through (6).
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(4)
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(2) Records described in § 63.10(c)(1) through (6).
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(5)
-
(v) All excess emissions and monitoring system performance reports and all summary reports, if required, shall be delivered or postmarked by the 30th day following the end of each calendar half or quarter, as appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all the information required in paragraphs (c)(5) through (c)(13) of this section, in §§ 63.8(c)(7) and 63.8(c)(8), and in the relevant standard, and they shall contain the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances of a parameter have occurred, or a CMS has not been inoperative, out of control, repaired, or adjusted, such information shall be stated in the report.
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13) of subpart A of this part.
-
(2) Records described in § 63.10(c)(1) through (6).
-
(b) You must submit an initial compliance report that provides summary, monitoring system performance, and deviation information to the Administrator on April 5, 2027, or once the report template for this subpart has been available on the Compliance and Emissions Data Reporting Interface (CEDRI) website for one year, whichever date is later, to the EPA via CEDRI, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Anything submitted using CEDRI cannot later be claimed CBI. You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim, submit a complete report, including information claimed to be CBI, to the EPA. The CBI report must be generated using the appropriate form on the CEDRI website or an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website. Submit the CBI file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Commercial Sterilization Facilities Sector Lead, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph. All CBI claims must be asserted at the time of submission. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available. Reports of deviations from an operating limit shall include all information required in § 63.10(c)(5) through (13), as applicable in table 6 to this subpart, along with information from any calibration tests in which the monitoring equipment is not in compliance with Performance Specification 19 in appendix B and Procedure 7 in appendix F to part 60 of this chapter or the method used for parameter monitoring device calibration. Reports shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. If your report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces this requirement. When no deviations have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. In addition, the summary report shall include:(i) Date that facility commenced construction or reconstruction;(ii) Hours of commercial sterilization operation over the previous 12 months; and(iv) If you are electing to determine the mass of EtO sent to the control device from the SCV(s) via the procedure in § 63.364(f)(1)(i), you must report the daily EtO use from each applicable chamber for the previous 7 months.(v) If so, indicate the affected sources that are included in each combined emission stream limitation.(vi) If you are electing to comply with a site-wide emission limit, report the daily EtO use over the previous 7 months.(2) If your sterilization facility is demonstrating continuous compliance through periodic performance testing, you must report the following:(i) Control system ID;(ii) Control device ID;(iii) Control device type; and(iv) Recirculation tank ID if an acid-water scrubber is used to meet the emission standard and you elect to comply with the maximum scrubber liquor height limit;(3) You must report the following for each sterilization chamber at your facility:(i) The sterilization chamber ID;(ii) The ID of the control system that the SCV was routed to, if applicable;(iii) The portion of SCV exhaust that was routed to the control system, if applicable;(iv) The ID of the EtO CEMS that was used to monitor SCV emissions, if applicable;(v) The portion of SCV exhaust that was monitored with the EtO CEMS, if applicable;(vi) The ID of the control system that the CEV was routed to, if applicable;(vii) The portion of CEV exhaust that was routed to the control system, if applicable;(viii) The ID of the EtO CEMS that was used to monitor CEV emissions, if applicable;(ix) The portion of CEV exhaust that was monitored with the EtO CEMS, if applicable;(4) If emissions from any room in your facility are subject to an emission standard, you must report the following for each room where there is the potential for EtO emissions:(i) Room ID;(ii) Documentation of emissions occurring within the room, including aeration, EtO storage, EtO dispensing, pre-aeration handling of sterilized material, and post-aeration handling of sterilized material;(iii) The ID of the control system that the room air was routed to, if applicable;(iv) The portion of room air that was routed to the control system, if applicable;(v) The ID of the EtO CEMS that was used to monitor room air emissions, if applicable;(vi) The portion of room air that was monitored with the EtO CEMS, if applicable;(5) If an EtO CEMS was used to demonstrate continuous compliance with an emission standard for more than 30-operating days, you must report the following:(ii) The affected sources that are included in each inlet that is being monitored with EtO CEMS;(v) The daily sum of EtO emissions from each outlet of the control system, along with 30-operating day rolling sums.(vi) For each day, calculate and report the daily mass emission limit that the control system must achieve based on the previous 30 days of data. For control systems with multiple emission streams, and complying with a combined emission stream limitation in § 63.362(i) or a SWEL in § 63.362(j), report the daily 30-operating day mass emission limit as determined in accordance with CES in § 63.362(i)(1)(i) and (i)(2)(i) or with § 63.362(j)(1)(i) and (j)(2)(i), as applicable.(6) If any portion of your facility is required to be operated with PTE, you must report the following:(i) If you are choosing to demonstrate continuous compliance through the use of volumetric flow rate monitoring, you must report the 3-hr rolling average, rolled hourly volumetric flow from each outlet where air from the PTE is sent, in cubic feet per second.(ii) If you are choosing to demonstrate continuous compliance through use of differential pressure monitoring, you must report the 3-hr rolling average, rolled hourly pressure differential reading, in inches water.(7) If you are complying with the requirement to follow the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door, you must provide a certification from your responsible official that this approach is being followed and you are meeting the monitoring requirements at § 63.362(h).(8) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and facility EtO use is less than 4 tpy, you must report the following for each room where there are Group 2 room air emissions:(i) Room ID;(ii) Number of room air changes per hour;(iii) Room temperature, in degrees Celsius; and(9) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and EtO use is less than 4 tpy, you are not required to report the information in paragraph (b)(8) of this section if you meet the following requirements:(i) You are complying with the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door; and(ii) The requirements of § 63.363 are met.(10) For each instance, report the date, time, the cause and duration of each deviation. For each deviation the report must include a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to determine the emissions.
-
(4) All excess emissions and monitoring system performance reports and all summary reports, if required per paragraph (e)(5) and (6) of this section, shall be delivered or postmarked within 30 days following the end of each calendar year, or within 30 days following the end of each six month period, if appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all information required in § 63.10(c)(5) through (13) of subpart A of this part as applicable in Table 1 of § 63.560 and information from any calibration tests in which the monitoring equipment is not in compliance with PS 8 or other methods used for accuracy testing of temperature, pressure, or flow monitoring devices. The written report shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. This information will be kept for a minimum of 5 years and made readily available to the Administrator or delegated State authority upon request.
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(3) If measured parameters meet any of the conditions specified in § 63.864(k)(1) or (2), the owner or operator of the affected source must submit a semiannual report describing the excess emissions that occurred. If the total duration of monitoring exceedances for the reporting period is 1 percent or greater of the total reporting period operating time, or the total CMS downtime for the reporting period is 5 percent or greater of the total reporting period operating time, or any violations according to § 63.864(k)(2) occurred, information from both the summary report and the excess emissions and continuous monitoring system performance report must be submitted. This report will be titled “Excess Emissions and Continuous Monitoring System Performance Report” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section, in addition to the information required in § 63.10(c)(5) through (14), as specified in paragraphs (c)(3)(i) through (vi) of this section. Reporting monitoring exceedances does not constitute a violation of the applicable standard unless the violation criteria in § 63.864(k)(2) and (3) are reached.(i) An identification of the date and time identifying each period during which the CMS was inoperative except for zero (low-level) and high-level checks.(ii) An identification of the date and time identifying each period during which the CMS was out of control, as defined in § 63.8(c)(7).(iii) The specific identification of each period of excess emissions and parameter monitoring exceedances as described in paragraphs (c)(3)(iii)(A) through (E) of this section.(A) (1) The total number of 6-minute averages in the reporting period (excluding process unit downtime).(2) [Reserved](3) The number of 6-minute averages in the reporting period that exceeded the relevant opacity limit.(4) The percent of 6-minute averages in the reporting period that exceed the relevant opacity limit.(5) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(B) [Reserved](C) (1) The operating limits established during the performance test for scrubbing liquid flow rate and pressure drop across the scrubber (or alternatively, fan amperage or RPM if used for smelt dissolving tank scrubbers).(2) The number of 3-hour wet scrubber parameter averages below the minimum operating limit established during the performance test, if applicable.(3) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(D) (1) The operating limit established during the performance test.(2) The number of 1-hour and 3-hour temperature averages below the minimum operating limit established during the performance test.(3) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(E) For alternative parameters established according to § 63.864(e)(13) or (14) subject to the requirements of § 63.864(k)(1) and (2):(1) The type of operating parameters monitored for compliance.(2) The operating limits established during the performance test.(3) The number of 3-hour parameter averages outside of the operating limits established during the performance test.(4) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(6)
-
(v) All excess emissions and monitoring system performance reports and all summary reports, if required, shall be delivered or postmarked by the 30th day following the end of each calendar half or quarter, as appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all the information required in paragraphs (c)(5) through (c)(13) of this section, in §§ 63.8(c)(7) and 63.8(c)(8), and in the relevant standard, and they shall contain the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances of a parameter have occurred, or a CMS has not been inoperative, out of control, repaired, or adjusted, such information shall be stated in the report.
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13) of subpart A of this part.
-
(2) Records described in § 63.10(c)(1) through (6).
-
(b) You must submit an initial compliance report that provides summary, monitoring system performance, and deviation information to the Administrator on April 5, 2027, or once the report template for this subpart has been available on the Compliance and Emissions Data Reporting Interface (CEDRI) website for one year, whichever date is later, to the EPA via CEDRI, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Anything submitted using CEDRI cannot later be claimed CBI. You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim, submit a complete report, including information claimed to be CBI, to the EPA. The CBI report must be generated using the appropriate form on the CEDRI website or an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website. Submit the CBI file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Commercial Sterilization Facilities Sector Lead, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph. All CBI claims must be asserted at the time of submission. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available. Reports of deviations from an operating limit shall include all information required in § 63.10(c)(5) through (13), as applicable in table 6 to this subpart, along with information from any calibration tests in which the monitoring equipment is not in compliance with Performance Specification 19 in appendix B and Procedure 7 in appendix F to part 60 of this chapter or the method used for parameter monitoring device calibration. Reports shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. If your report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces this requirement. When no deviations have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. In addition, the summary report shall include:(i) Date that facility commenced construction or reconstruction;(ii) Hours of commercial sterilization operation over the previous 12 months; and(iv) If you are electing to determine the mass of EtO sent to the control device from the SCV(s) via the procedure in § 63.364(f)(1)(i), you must report the daily EtO use from each applicable chamber for the previous 7 months.(v) If so, indicate the affected sources that are included in each combined emission stream limitation.(vi) If you are electing to comply with a site-wide emission limit, report the daily EtO use over the previous 7 months.(2) If your sterilization facility is demonstrating continuous compliance through periodic performance testing, you must report the following:(i) Control system ID;(ii) Control device ID;(iii) Control device type; and(iv) Recirculation tank ID if an acid-water scrubber is used to meet the emission standard and you elect to comply with the maximum scrubber liquor height limit;(3) You must report the following for each sterilization chamber at your facility:(i) The sterilization chamber ID;(ii) The ID of the control system that the SCV was routed to, if applicable;(iii) The portion of SCV exhaust that was routed to the control system, if applicable;(iv) The ID of the EtO CEMS that was used to monitor SCV emissions, if applicable;(v) The portion of SCV exhaust that was monitored with the EtO CEMS, if applicable;(vi) The ID of the control system that the CEV was routed to, if applicable;(vii) The portion of CEV exhaust that was routed to the control system, if applicable;(viii) The ID of the EtO CEMS that was used to monitor CEV emissions, if applicable;(ix) The portion of CEV exhaust that was monitored with the EtO CEMS, if applicable;(4) If emissions from any room in your facility are subject to an emission standard, you must report the following for each room where there is the potential for EtO emissions:(i) Room ID;(ii) Documentation of emissions occurring within the room, including aeration, EtO storage, EtO dispensing, pre-aeration handling of sterilized material, and post-aeration handling of sterilized material;(iii) The ID of the control system that the room air was routed to, if applicable;(iv) The portion of room air that was routed to the control system, if applicable;(v) The ID of the EtO CEMS that was used to monitor room air emissions, if applicable;(vi) The portion of room air that was monitored with the EtO CEMS, if applicable;(5) If an EtO CEMS was used to demonstrate continuous compliance with an emission standard for more than 30-operating days, you must report the following:(ii) The affected sources that are included in each inlet that is being monitored with EtO CEMS;(v) The daily sum of EtO emissions from each outlet of the control system, along with 30-operating day rolling sums.(vi) For each day, calculate and report the daily mass emission limit that the control system must achieve based on the previous 30 days of data. For control systems with multiple emission streams, and complying with a combined emission stream limitation in § 63.362(i) or a SWEL in § 63.362(j), report the daily 30-operating day mass emission limit as determined in accordance with CES in § 63.362(i)(1)(i) and (i)(2)(i) or with § 63.362(j)(1)(i) and (j)(2)(i), as applicable.(6) If any portion of your facility is required to be operated with PTE, you must report the following:(i) If you are choosing to demonstrate continuous compliance through the use of volumetric flow rate monitoring, you must report the 3-hr rolling average, rolled hourly volumetric flow from each outlet where air from the PTE is sent, in cubic feet per second.(ii) If you are choosing to demonstrate continuous compliance through use of differential pressure monitoring, you must report the 3-hr rolling average, rolled hourly pressure differential reading, in inches water.(7) If you are complying with the requirement to follow the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door, you must provide a certification from your responsible official that this approach is being followed and you are meeting the monitoring requirements at § 63.362(h).(8) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and facility EtO use is less than 4 tpy, you must report the following for each room where there are Group 2 room air emissions:(i) Room ID;(ii) Number of room air changes per hour;(iii) Room temperature, in degrees Celsius; and(9) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and EtO use is less than 4 tpy, you are not required to report the information in paragraph (b)(8) of this section if you meet the following requirements:(i) You are complying with the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door; and(ii) The requirements of § 63.363 are met.(10) For each instance, report the date, time, the cause and duration of each deviation. For each deviation the report must include a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to determine the emissions.
-
(4) All excess emissions and monitoring system performance reports and all summary reports, if required per paragraph (e)(5) and (6) of this section, shall be delivered or postmarked within 30 days following the end of each calendar year, or within 30 days following the end of each six month period, if appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all information required in § 63.10(c)(5) through (13) of subpart A of this part as applicable in Table 1 of § 63.560 and information from any calibration tests in which the monitoring equipment is not in compliance with PS 8 or other methods used for accuracy testing of temperature, pressure, or flow monitoring devices. The written report shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. This information will be kept for a minimum of 5 years and made readily available to the Administrator or delegated State authority upon request.
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(3) If measured parameters meet any of the conditions specified in § 63.864(k)(1) or (2), the owner or operator of the affected source must submit a semiannual report describing the excess emissions that occurred. If the total duration of monitoring exceedances for the reporting period is 1 percent or greater of the total reporting period operating time, or the total CMS downtime for the reporting period is 5 percent or greater of the total reporting period operating time, or any violations according to § 63.864(k)(2) occurred, information from both the summary report and the excess emissions and continuous monitoring system performance report must be submitted. This report will be titled “Excess Emissions and Continuous Monitoring System Performance Report” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section, in addition to the information required in § 63.10(c)(5) through (14), as specified in paragraphs (c)(3)(i) through (vi) of this section. Reporting monitoring exceedances does not constitute a violation of the applicable standard unless the violation criteria in § 63.864(k)(2) and (3) are reached.(i) An identification of the date and time identifying each period during which the CMS was inoperative except for zero (low-level) and high-level checks.(ii) An identification of the date and time identifying each period during which the CMS was out of control, as defined in § 63.8(c)(7).(iii) The specific identification of each period of excess emissions and parameter monitoring exceedances as described in paragraphs (c)(3)(iii)(A) through (E) of this section.(A) (1) The total number of 6-minute averages in the reporting period (excluding process unit downtime).(2) [Reserved](3) The number of 6-minute averages in the reporting period that exceeded the relevant opacity limit.(4) The percent of 6-minute averages in the reporting period that exceed the relevant opacity limit.(5) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(B) [Reserved](C) (1) The operating limits established during the performance test for scrubbing liquid flow rate and pressure drop across the scrubber (or alternatively, fan amperage or RPM if used for smelt dissolving tank scrubbers).(2) The number of 3-hour wet scrubber parameter averages below the minimum operating limit established during the performance test, if applicable.(3) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(D) (1) The operating limit established during the performance test.(2) The number of 1-hour and 3-hour temperature averages below the minimum operating limit established during the performance test.(3) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(E) For alternative parameters established according to § 63.864(e)(13) or (14) subject to the requirements of § 63.864(k)(1) and (2):(1) The type of operating parameters monitored for compliance.(2) The operating limits established during the performance test.(3) The number of 3-hour parameter averages outside of the operating limits established during the performance test.(4) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(7)
-
(v) All excess emissions and monitoring system performance reports and all summary reports, if required, shall be delivered or postmarked by the 30th day following the end of each calendar half or quarter, as appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all the information required in paragraphs (c)(5) through (c)(13) of this section, in §§ 63.8(c)(7) and 63.8(c)(8), and in the relevant standard, and they shall contain the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances of a parameter have occurred, or a CMS has not been inoperative, out of control, repaired, or adjusted, such information shall be stated in the report.
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13) of subpart A of this part.
-
(b) You must submit an initial compliance report that provides summary, monitoring system performance, and deviation information to the Administrator on April 5, 2027, or once the report template for this subpart has been available on the Compliance and Emissions Data Reporting Interface (CEDRI) website for one year, whichever date is later, to the EPA via CEDRI, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Anything submitted using CEDRI cannot later be claimed CBI. You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim, submit a complete report, including information claimed to be CBI, to the EPA. The CBI report must be generated using the appropriate form on the CEDRI website or an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website. Submit the CBI file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Commercial Sterilization Facilities Sector Lead, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph. All CBI claims must be asserted at the time of submission. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available. Reports of deviations from an operating limit shall include all information required in § 63.10(c)(5) through (13), as applicable in table 6 to this subpart, along with information from any calibration tests in which the monitoring equipment is not in compliance with Performance Specification 19 in appendix B and Procedure 7 in appendix F to part 60 of this chapter or the method used for parameter monitoring device calibration. Reports shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. If your report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces this requirement. When no deviations have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. In addition, the summary report shall include:(i) Date that facility commenced construction or reconstruction;(ii) Hours of commercial sterilization operation over the previous 12 months; and(iv) If you are electing to determine the mass of EtO sent to the control device from the SCV(s) via the procedure in § 63.364(f)(1)(i), you must report the daily EtO use from each applicable chamber for the previous 7 months.(v) If so, indicate the affected sources that are included in each combined emission stream limitation.(vi) If you are electing to comply with a site-wide emission limit, report the daily EtO use over the previous 7 months.(2) If your sterilization facility is demonstrating continuous compliance through periodic performance testing, you must report the following:(i) Control system ID;(ii) Control device ID;(iii) Control device type; and(iv) Recirculation tank ID if an acid-water scrubber is used to meet the emission standard and you elect to comply with the maximum scrubber liquor height limit;(3) You must report the following for each sterilization chamber at your facility:(i) The sterilization chamber ID;(ii) The ID of the control system that the SCV was routed to, if applicable;(iii) The portion of SCV exhaust that was routed to the control system, if applicable;(iv) The ID of the EtO CEMS that was used to monitor SCV emissions, if applicable;(v) The portion of SCV exhaust that was monitored with the EtO CEMS, if applicable;(vi) The ID of the control system that the CEV was routed to, if applicable;(vii) The portion of CEV exhaust that was routed to the control system, if applicable;(viii) The ID of the EtO CEMS that was used to monitor CEV emissions, if applicable;(ix) The portion of CEV exhaust that was monitored with the EtO CEMS, if applicable;(4) If emissions from any room in your facility are subject to an emission standard, you must report the following for each room where there is the potential for EtO emissions:(i) Room ID;(ii) Documentation of emissions occurring within the room, including aeration, EtO storage, EtO dispensing, pre-aeration handling of sterilized material, and post-aeration handling of sterilized material;(iii) The ID of the control system that the room air was routed to, if applicable;(iv) The portion of room air that was routed to the control system, if applicable;(v) The ID of the EtO CEMS that was used to monitor room air emissions, if applicable;(vi) The portion of room air that was monitored with the EtO CEMS, if applicable;(5) If an EtO CEMS was used to demonstrate continuous compliance with an emission standard for more than 30-operating days, you must report the following:(ii) The affected sources that are included in each inlet that is being monitored with EtO CEMS;(v) The daily sum of EtO emissions from each outlet of the control system, along with 30-operating day rolling sums.(vi) For each day, calculate and report the daily mass emission limit that the control system must achieve based on the previous 30 days of data. For control systems with multiple emission streams, and complying with a combined emission stream limitation in § 63.362(i) or a SWEL in § 63.362(j), report the daily 30-operating day mass emission limit as determined in accordance with CES in § 63.362(i)(1)(i) and (i)(2)(i) or with § 63.362(j)(1)(i) and (j)(2)(i), as applicable.(6) If any portion of your facility is required to be operated with PTE, you must report the following:(i) If you are choosing to demonstrate continuous compliance through the use of volumetric flow rate monitoring, you must report the 3-hr rolling average, rolled hourly volumetric flow from each outlet where air from the PTE is sent, in cubic feet per second.(ii) If you are choosing to demonstrate continuous compliance through use of differential pressure monitoring, you must report the 3-hr rolling average, rolled hourly pressure differential reading, in inches water.(7) If you are complying with the requirement to follow the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door, you must provide a certification from your responsible official that this approach is being followed and you are meeting the monitoring requirements at § 63.362(h).(8) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and facility EtO use is less than 4 tpy, you must report the following for each room where there are Group 2 room air emissions:(i) Room ID;(ii) Number of room air changes per hour;(iii) Room temperature, in degrees Celsius; and(9) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and EtO use is less than 4 tpy, you are not required to report the information in paragraph (b)(8) of this section if you meet the following requirements:(i) You are complying with the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door; and(ii) The requirements of § 63.363 are met.(10) For each instance, report the date, time, the cause and duration of each deviation. For each deviation the report must include a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to determine the emissions.
-
(4) All excess emissions and monitoring system performance reports and all summary reports, if required per paragraph (e)(5) and (6) of this section, shall be delivered or postmarked within 30 days following the end of each calendar year, or within 30 days following the end of each six month period, if appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all information required in § 63.10(c)(5) through (13) of subpart A of this part as applicable in Table 1 of § 63.560 and information from any calibration tests in which the monitoring equipment is not in compliance with PS 8 or other methods used for accuracy testing of temperature, pressure, or flow monitoring devices. The written report shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. This information will be kept for a minimum of 5 years and made readily available to the Administrator or delegated State authority upon request.
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(3) If measured parameters meet any of the conditions specified in § 63.864(k)(1) or (2), the owner or operator of the affected source must submit a semiannual report describing the excess emissions that occurred. If the total duration of monitoring exceedances for the reporting period is 1 percent or greater of the total reporting period operating time, or the total CMS downtime for the reporting period is 5 percent or greater of the total reporting period operating time, or any violations according to § 63.864(k)(2) occurred, information from both the summary report and the excess emissions and continuous monitoring system performance report must be submitted. This report will be titled “Excess Emissions and Continuous Monitoring System Performance Report” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section, in addition to the information required in § 63.10(c)(5) through (14), as specified in paragraphs (c)(3)(i) through (vi) of this section. Reporting monitoring exceedances does not constitute a violation of the applicable standard unless the violation criteria in § 63.864(k)(2) and (3) are reached.(i) An identification of the date and time identifying each period during which the CMS was inoperative except for zero (low-level) and high-level checks.(ii) An identification of the date and time identifying each period during which the CMS was out of control, as defined in § 63.8(c)(7).(iii) The specific identification of each period of excess emissions and parameter monitoring exceedances as described in paragraphs (c)(3)(iii)(A) through (E) of this section.(A) (1) The total number of 6-minute averages in the reporting period (excluding process unit downtime).(2) [Reserved](3) The number of 6-minute averages in the reporting period that exceeded the relevant opacity limit.(4) The percent of 6-minute averages in the reporting period that exceed the relevant opacity limit.(5) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(B) [Reserved](C) (1) The operating limits established during the performance test for scrubbing liquid flow rate and pressure drop across the scrubber (or alternatively, fan amperage or RPM if used for smelt dissolving tank scrubbers).(2) The number of 3-hour wet scrubber parameter averages below the minimum operating limit established during the performance test, if applicable.(3) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(D) (1) The operating limit established during the performance test.(2) The number of 1-hour and 3-hour temperature averages below the minimum operating limit established during the performance test.(3) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(E) For alternative parameters established according to § 63.864(e)(13) or (14) subject to the requirements of § 63.864(k)(1) and (2):(1) The type of operating parameters monitored for compliance.(2) The operating limits established during the performance test.(3) The number of 3-hour parameter averages outside of the operating limits established during the performance test.(4) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(8)
-
(v) All excess emissions and monitoring system performance reports and all summary reports, if required, shall be delivered or postmarked by the 30th day following the end of each calendar half or quarter, as appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all the information required in paragraphs (c)(5) through (c)(13) of this section, in §§ 63.8(c)(7) and 63.8(c)(8), and in the relevant standard, and they shall contain the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances of a parameter have occurred, or a CMS has not been inoperative, out of control, repaired, or adjusted, such information shall be stated in the report.
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13) of subpart A of this part.
-
(b) You must submit an initial compliance report that provides summary, monitoring system performance, and deviation information to the Administrator on April 5, 2027, or once the report template for this subpart has been available on the Compliance and Emissions Data Reporting Interface (CEDRI) website for one year, whichever date is later, to the EPA via CEDRI, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Anything submitted using CEDRI cannot later be claimed CBI. You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim, submit a complete report, including information claimed to be CBI, to the EPA. The CBI report must be generated using the appropriate form on the CEDRI website or an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website. Submit the CBI file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Commercial Sterilization Facilities Sector Lead, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph. All CBI claims must be asserted at the time of submission. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available. Reports of deviations from an operating limit shall include all information required in § 63.10(c)(5) through (13), as applicable in table 6 to this subpart, along with information from any calibration tests in which the monitoring equipment is not in compliance with Performance Specification 19 in appendix B and Procedure 7 in appendix F to part 60 of this chapter or the method used for parameter monitoring device calibration. Reports shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. If your report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces this requirement. When no deviations have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. In addition, the summary report shall include:(i) Date that facility commenced construction or reconstruction;(ii) Hours of commercial sterilization operation over the previous 12 months; and(iv) If you are electing to determine the mass of EtO sent to the control device from the SCV(s) via the procedure in § 63.364(f)(1)(i), you must report the daily EtO use from each applicable chamber for the previous 7 months.(v) If so, indicate the affected sources that are included in each combined emission stream limitation.(vi) If you are electing to comply with a site-wide emission limit, report the daily EtO use over the previous 7 months.(2) If your sterilization facility is demonstrating continuous compliance through periodic performance testing, you must report the following:(i) Control system ID;(ii) Control device ID;(iii) Control device type; and(iv) Recirculation tank ID if an acid-water scrubber is used to meet the emission standard and you elect to comply with the maximum scrubber liquor height limit;(3) You must report the following for each sterilization chamber at your facility:(i) The sterilization chamber ID;(ii) The ID of the control system that the SCV was routed to, if applicable;(iii) The portion of SCV exhaust that was routed to the control system, if applicable;(iv) The ID of the EtO CEMS that was used to monitor SCV emissions, if applicable;(v) The portion of SCV exhaust that was monitored with the EtO CEMS, if applicable;(vi) The ID of the control system that the CEV was routed to, if applicable;(vii) The portion of CEV exhaust that was routed to the control system, if applicable;(viii) The ID of the EtO CEMS that was used to monitor CEV emissions, if applicable;(ix) The portion of CEV exhaust that was monitored with the EtO CEMS, if applicable;(4) If emissions from any room in your facility are subject to an emission standard, you must report the following for each room where there is the potential for EtO emissions:(i) Room ID;(ii) Documentation of emissions occurring within the room, including aeration, EtO storage, EtO dispensing, pre-aeration handling of sterilized material, and post-aeration handling of sterilized material;(iii) The ID of the control system that the room air was routed to, if applicable;(iv) The portion of room air that was routed to the control system, if applicable;(v) The ID of the EtO CEMS that was used to monitor room air emissions, if applicable;(vi) The portion of room air that was monitored with the EtO CEMS, if applicable;(5) If an EtO CEMS was used to demonstrate continuous compliance with an emission standard for more than 30-operating days, you must report the following:(ii) The affected sources that are included in each inlet that is being monitored with EtO CEMS;(v) The daily sum of EtO emissions from each outlet of the control system, along with 30-operating day rolling sums.(vi) For each day, calculate and report the daily mass emission limit that the control system must achieve based on the previous 30 days of data. For control systems with multiple emission streams, and complying with a combined emission stream limitation in § 63.362(i) or a SWEL in § 63.362(j), report the daily 30-operating day mass emission limit as determined in accordance with CES in § 63.362(i)(1)(i) and (i)(2)(i) or with § 63.362(j)(1)(i) and (j)(2)(i), as applicable.(6) If any portion of your facility is required to be operated with PTE, you must report the following:(i) If you are choosing to demonstrate continuous compliance through the use of volumetric flow rate monitoring, you must report the 3-hr rolling average, rolled hourly volumetric flow from each outlet where air from the PTE is sent, in cubic feet per second.(ii) If you are choosing to demonstrate continuous compliance through use of differential pressure monitoring, you must report the 3-hr rolling average, rolled hourly pressure differential reading, in inches water.(7) If you are complying with the requirement to follow the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door, you must provide a certification from your responsible official that this approach is being followed and you are meeting the monitoring requirements at § 63.362(h).(8) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and facility EtO use is less than 4 tpy, you must report the following for each room where there are Group 2 room air emissions:(i) Room ID;(ii) Number of room air changes per hour;(iii) Room temperature, in degrees Celsius; and(9) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and EtO use is less than 4 tpy, you are not required to report the information in paragraph (b)(8) of this section if you meet the following requirements:(i) You are complying with the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door; and(ii) The requirements of § 63.363 are met.(10) For each instance, report the date, time, the cause and duration of each deviation. For each deviation the report must include a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to determine the emissions.
-
(4) All excess emissions and monitoring system performance reports and all summary reports, if required per paragraph (e)(5) and (6) of this section, shall be delivered or postmarked within 30 days following the end of each calendar year, or within 30 days following the end of each six month period, if appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all information required in § 63.10(c)(5) through (13) of subpart A of this part as applicable in Table 1 of § 63.560 and information from any calibration tests in which the monitoring equipment is not in compliance with PS 8 or other methods used for accuracy testing of temperature, pressure, or flow monitoring devices. The written report shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. This information will be kept for a minimum of 5 years and made readily available to the Administrator or delegated State authority upon request.
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(3) If measured parameters meet any of the conditions specified in § 63.864(k)(1) or (2), the owner or operator of the affected source must submit a semiannual report describing the excess emissions that occurred. If the total duration of monitoring exceedances for the reporting period is 1 percent or greater of the total reporting period operating time, or the total CMS downtime for the reporting period is 5 percent or greater of the total reporting period operating time, or any violations according to § 63.864(k)(2) occurred, information from both the summary report and the excess emissions and continuous monitoring system performance report must be submitted. This report will be titled “Excess Emissions and Continuous Monitoring System Performance Report” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section, in addition to the information required in § 63.10(c)(5) through (14), as specified in paragraphs (c)(3)(i) through (vi) of this section. Reporting monitoring exceedances does not constitute a violation of the applicable standard unless the violation criteria in § 63.864(k)(2) and (3) are reached.(i) An identification of the date and time identifying each period during which the CMS was inoperative except for zero (low-level) and high-level checks.(ii) An identification of the date and time identifying each period during which the CMS was out of control, as defined in § 63.8(c)(7).(iii) The specific identification of each period of excess emissions and parameter monitoring exceedances as described in paragraphs (c)(3)(iii)(A) through (E) of this section.(A) (1) The total number of 6-minute averages in the reporting period (excluding process unit downtime).(2) [Reserved](3) The number of 6-minute averages in the reporting period that exceeded the relevant opacity limit.(4) The percent of 6-minute averages in the reporting period that exceed the relevant opacity limit.(5) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(B) [Reserved](C) (1) The operating limits established during the performance test for scrubbing liquid flow rate and pressure drop across the scrubber (or alternatively, fan amperage or RPM if used for smelt dissolving tank scrubbers).(2) The number of 3-hour wet scrubber parameter averages below the minimum operating limit established during the performance test, if applicable.(3) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(D) (1) The operating limit established during the performance test.(2) The number of 1-hour and 3-hour temperature averages below the minimum operating limit established during the performance test.(3) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(E) For alternative parameters established according to § 63.864(e)(13) or (14) subject to the requirements of § 63.864(k)(1) and (2):(1) The type of operating parameters monitored for compliance.(2) The operating limits established during the performance test.(3) The number of 3-hour parameter averages outside of the operating limits established during the performance test.(4) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(9)
-
(v) All excess emissions and monitoring system performance reports and all summary reports, if required, shall be delivered or postmarked by the 30th day following the end of each calendar half or quarter, as appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all the information required in paragraphs (c)(5) through (c)(13) of this section, in §§ 63.8(c)(7) and 63.8(c)(8), and in the relevant standard, and they shall contain the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances of a parameter have occurred, or a CMS has not been inoperative, out of control, repaired, or adjusted, such information shall be stated in the report.
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13) of subpart A of this part.
-
(b) You must submit an initial compliance report that provides summary, monitoring system performance, and deviation information to the Administrator on April 5, 2027, or once the report template for this subpart has been available on the Compliance and Emissions Data Reporting Interface (CEDRI) website for one year, whichever date is later, to the EPA via CEDRI, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Anything submitted using CEDRI cannot later be claimed CBI. You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim, submit a complete report, including information claimed to be CBI, to the EPA. The CBI report must be generated using the appropriate form on the CEDRI website or an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website. Submit the CBI file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Commercial Sterilization Facilities Sector Lead, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph. All CBI claims must be asserted at the time of submission. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available. Reports of deviations from an operating limit shall include all information required in § 63.10(c)(5) through (13), as applicable in table 6 to this subpart, along with information from any calibration tests in which the monitoring equipment is not in compliance with Performance Specification 19 in appendix B and Procedure 7 in appendix F to part 60 of this chapter or the method used for parameter monitoring device calibration. Reports shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. If your report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces this requirement. When no deviations have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. In addition, the summary report shall include:(i) Date that facility commenced construction or reconstruction;(ii) Hours of commercial sterilization operation over the previous 12 months; and(iv) If you are electing to determine the mass of EtO sent to the control device from the SCV(s) via the procedure in § 63.364(f)(1)(i), you must report the daily EtO use from each applicable chamber for the previous 7 months.(v) If so, indicate the affected sources that are included in each combined emission stream limitation.(vi) If you are electing to comply with a site-wide emission limit, report the daily EtO use over the previous 7 months.(2) If your sterilization facility is demonstrating continuous compliance through periodic performance testing, you must report the following:(i) Control system ID;(ii) Control device ID;(iii) Control device type; and(iv) Recirculation tank ID if an acid-water scrubber is used to meet the emission standard and you elect to comply with the maximum scrubber liquor height limit;(3) You must report the following for each sterilization chamber at your facility:(i) The sterilization chamber ID;(ii) The ID of the control system that the SCV was routed to, if applicable;(iii) The portion of SCV exhaust that was routed to the control system, if applicable;(iv) The ID of the EtO CEMS that was used to monitor SCV emissions, if applicable;(v) The portion of SCV exhaust that was monitored with the EtO CEMS, if applicable;(vi) The ID of the control system that the CEV was routed to, if applicable;(vii) The portion of CEV exhaust that was routed to the control system, if applicable;(viii) The ID of the EtO CEMS that was used to monitor CEV emissions, if applicable;(ix) The portion of CEV exhaust that was monitored with the EtO CEMS, if applicable;(4) If emissions from any room in your facility are subject to an emission standard, you must report the following for each room where there is the potential for EtO emissions:(i) Room ID;(ii) Documentation of emissions occurring within the room, including aeration, EtO storage, EtO dispensing, pre-aeration handling of sterilized material, and post-aeration handling of sterilized material;(iii) The ID of the control system that the room air was routed to, if applicable;(iv) The portion of room air that was routed to the control system, if applicable;(v) The ID of the EtO CEMS that was used to monitor room air emissions, if applicable;(vi) The portion of room air that was monitored with the EtO CEMS, if applicable;(5) If an EtO CEMS was used to demonstrate continuous compliance with an emission standard for more than 30-operating days, you must report the following:(ii) The affected sources that are included in each inlet that is being monitored with EtO CEMS;(v) The daily sum of EtO emissions from each outlet of the control system, along with 30-operating day rolling sums.(vi) For each day, calculate and report the daily mass emission limit that the control system must achieve based on the previous 30 days of data. For control systems with multiple emission streams, and complying with a combined emission stream limitation in § 63.362(i) or a SWEL in § 63.362(j), report the daily 30-operating day mass emission limit as determined in accordance with CES in § 63.362(i)(1)(i) and (i)(2)(i) or with § 63.362(j)(1)(i) and (j)(2)(i), as applicable.(6) If any portion of your facility is required to be operated with PTE, you must report the following:(i) If you are choosing to demonstrate continuous compliance through the use of volumetric flow rate monitoring, you must report the 3-hr rolling average, rolled hourly volumetric flow from each outlet where air from the PTE is sent, in cubic feet per second.(ii) If you are choosing to demonstrate continuous compliance through use of differential pressure monitoring, you must report the 3-hr rolling average, rolled hourly pressure differential reading, in inches water.(7) If you are complying with the requirement to follow the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door, you must provide a certification from your responsible official that this approach is being followed and you are meeting the monitoring requirements at § 63.362(h).(8) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and facility EtO use is less than 4 tpy, you must report the following for each room where there are Group 2 room air emissions:(i) Room ID;(ii) Number of room air changes per hour;(iii) Room temperature, in degrees Celsius; and(9) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and EtO use is less than 4 tpy, you are not required to report the information in paragraph (b)(8) of this section if you meet the following requirements:(i) You are complying with the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door; and(ii) The requirements of § 63.363 are met.(10) For each instance, report the date, time, the cause and duration of each deviation. For each deviation the report must include a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to determine the emissions.
-
(4) All excess emissions and monitoring system performance reports and all summary reports, if required per paragraph (e)(5) and (6) of this section, shall be delivered or postmarked within 30 days following the end of each calendar year, or within 30 days following the end of each six month period, if appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all information required in § 63.10(c)(5) through (13) of subpart A of this part as applicable in Table 1 of § 63.560 and information from any calibration tests in which the monitoring equipment is not in compliance with PS 8 or other methods used for accuracy testing of temperature, pressure, or flow monitoring devices. The written report shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. This information will be kept for a minimum of 5 years and made readily available to the Administrator or delegated State authority upon request.
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(3) If measured parameters meet any of the conditions specified in § 63.864(k)(1) or (2), the owner or operator of the affected source must submit a semiannual report describing the excess emissions that occurred. If the total duration of monitoring exceedances for the reporting period is 1 percent or greater of the total reporting period operating time, or the total CMS downtime for the reporting period is 5 percent or greater of the total reporting period operating time, or any violations according to § 63.864(k)(2) occurred, information from both the summary report and the excess emissions and continuous monitoring system performance report must be submitted. This report will be titled “Excess Emissions and Continuous Monitoring System Performance Report” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section, in addition to the information required in § 63.10(c)(5) through (14), as specified in paragraphs (c)(3)(i) through (vi) of this section. Reporting monitoring exceedances does not constitute a violation of the applicable standard unless the violation criteria in § 63.864(k)(2) and (3) are reached.(i) An identification of the date and time identifying each period during which the CMS was inoperative except for zero (low-level) and high-level checks.(ii) An identification of the date and time identifying each period during which the CMS was out of control, as defined in § 63.8(c)(7).(iii) The specific identification of each period of excess emissions and parameter monitoring exceedances as described in paragraphs (c)(3)(iii)(A) through (E) of this section.(A) (1) The total number of 6-minute averages in the reporting period (excluding process unit downtime).(2) [Reserved](3) The number of 6-minute averages in the reporting period that exceeded the relevant opacity limit.(4) The percent of 6-minute averages in the reporting period that exceed the relevant opacity limit.(5) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(B) [Reserved](C) (1) The operating limits established during the performance test for scrubbing liquid flow rate and pressure drop across the scrubber (or alternatively, fan amperage or RPM if used for smelt dissolving tank scrubbers).(2) The number of 3-hour wet scrubber parameter averages below the minimum operating limit established during the performance test, if applicable.(3) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(D) (1) The operating limit established during the performance test.(2) The number of 1-hour and 3-hour temperature averages below the minimum operating limit established during the performance test.(3) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(E) For alternative parameters established according to § 63.864(e)(13) or (14) subject to the requirements of § 63.864(k)(1) and (2):(1) The type of operating parameters monitored for compliance.(2) The operating limits established during the performance test.(3) The number of 3-hour parameter averages outside of the operating limits established during the performance test.(4) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(10)
-
(15) In order to satisfy the requirements of paragraphs (c)(10) through (c)(12) of this section and to avoid duplicative recordkeeping efforts, the owner or operator may use the affected source's startup, shutdown, and malfunction plan or records kept to satisfy the recordkeeping requirements of the startup, shutdown, and malfunction plan specified in § 63.6(e), provided that such plan and records adequately address the requirements of paragraphs (c)(10) through (c)(12).
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13) of subpart A of this part.
-
(b) You must submit an initial compliance report that provides summary, monitoring system performance, and deviation information to the Administrator on April 5, 2027, or once the report template for this subpart has been available on the Compliance and Emissions Data Reporting Interface (CEDRI) website for one year, whichever date is later, to the EPA via CEDRI, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Anything submitted using CEDRI cannot later be claimed CBI. You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim, submit a complete report, including information claimed to be CBI, to the EPA. The CBI report must be generated using the appropriate form on the CEDRI website or an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website. Submit the CBI file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Commercial Sterilization Facilities Sector Lead, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph. All CBI claims must be asserted at the time of submission. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available. Reports of deviations from an operating limit shall include all information required in § 63.10(c)(5) through (13), as applicable in table 6 to this subpart, along with information from any calibration tests in which the monitoring equipment is not in compliance with Performance Specification 19 in appendix B and Procedure 7 in appendix F to part 60 of this chapter or the method used for parameter monitoring device calibration. Reports shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. If your report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces this requirement. When no deviations have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. In addition, the summary report shall include:(i) Date that facility commenced construction or reconstruction;(ii) Hours of commercial sterilization operation over the previous 12 months; and(iv) If you are electing to determine the mass of EtO sent to the control device from the SCV(s) via the procedure in § 63.364(f)(1)(i), you must report the daily EtO use from each applicable chamber for the previous 7 months.(v) If so, indicate the affected sources that are included in each combined emission stream limitation.(vi) If you are electing to comply with a site-wide emission limit, report the daily EtO use over the previous 7 months.(2) If your sterilization facility is demonstrating continuous compliance through periodic performance testing, you must report the following:(i) Control system ID;(ii) Control device ID;(iii) Control device type; and(iv) Recirculation tank ID if an acid-water scrubber is used to meet the emission standard and you elect to comply with the maximum scrubber liquor height limit;(3) You must report the following for each sterilization chamber at your facility:(i) The sterilization chamber ID;(ii) The ID of the control system that the SCV was routed to, if applicable;(iii) The portion of SCV exhaust that was routed to the control system, if applicable;(iv) The ID of the EtO CEMS that was used to monitor SCV emissions, if applicable;(v) The portion of SCV exhaust that was monitored with the EtO CEMS, if applicable;(vi) The ID of the control system that the CEV was routed to, if applicable;(vii) The portion of CEV exhaust that was routed to the control system, if applicable;(viii) The ID of the EtO CEMS that was used to monitor CEV emissions, if applicable;(ix) The portion of CEV exhaust that was monitored with the EtO CEMS, if applicable;(4) If emissions from any room in your facility are subject to an emission standard, you must report the following for each room where there is the potential for EtO emissions:(i) Room ID;(ii) Documentation of emissions occurring within the room, including aeration, EtO storage, EtO dispensing, pre-aeration handling of sterilized material, and post-aeration handling of sterilized material;(iii) The ID of the control system that the room air was routed to, if applicable;(iv) The portion of room air that was routed to the control system, if applicable;(v) The ID of the EtO CEMS that was used to monitor room air emissions, if applicable;(vi) The portion of room air that was monitored with the EtO CEMS, if applicable;(5) If an EtO CEMS was used to demonstrate continuous compliance with an emission standard for more than 30-operating days, you must report the following:(ii) The affected sources that are included in each inlet that is being monitored with EtO CEMS;(v) The daily sum of EtO emissions from each outlet of the control system, along with 30-operating day rolling sums.(vi) For each day, calculate and report the daily mass emission limit that the control system must achieve based on the previous 30 days of data. For control systems with multiple emission streams, and complying with a combined emission stream limitation in § 63.362(i) or a SWEL in § 63.362(j), report the daily 30-operating day mass emission limit as determined in accordance with CES in § 63.362(i)(1)(i) and (i)(2)(i) or with § 63.362(j)(1)(i) and (j)(2)(i), as applicable.(6) If any portion of your facility is required to be operated with PTE, you must report the following:(i) If you are choosing to demonstrate continuous compliance through the use of volumetric flow rate monitoring, you must report the 3-hr rolling average, rolled hourly volumetric flow from each outlet where air from the PTE is sent, in cubic feet per second.(ii) If you are choosing to demonstrate continuous compliance through use of differential pressure monitoring, you must report the 3-hr rolling average, rolled hourly pressure differential reading, in inches water.(7) If you are complying with the requirement to follow the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door, you must provide a certification from your responsible official that this approach is being followed and you are meeting the monitoring requirements at § 63.362(h).(8) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and facility EtO use is less than 4 tpy, you must report the following for each room where there are Group 2 room air emissions:(i) Room ID;(ii) Number of room air changes per hour;(iii) Room temperature, in degrees Celsius; and(9) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and EtO use is less than 4 tpy, you are not required to report the information in paragraph (b)(8) of this section if you meet the following requirements:(i) You are complying with the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door; and(ii) The requirements of § 63.363 are met.(10) For each instance, report the date, time, the cause and duration of each deviation. For each deviation the report must include a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to determine the emissions.
-
(4) All excess emissions and monitoring system performance reports and all summary reports, if required per paragraph (e)(5) and (6) of this section, shall be delivered or postmarked within 30 days following the end of each calendar year, or within 30 days following the end of each six month period, if appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all information required in § 63.10(c)(5) through (13) of subpart A of this part as applicable in Table 1 of § 63.560 and information from any calibration tests in which the monitoring equipment is not in compliance with PS 8 or other methods used for accuracy testing of temperature, pressure, or flow monitoring devices. The written report shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. This information will be kept for a minimum of 5 years and made readily available to the Administrator or delegated State authority upon request.
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(3) If measured parameters meet any of the conditions specified in § 63.864(k)(1) or (2), the owner or operator of the affected source must submit a semiannual report describing the excess emissions that occurred. If the total duration of monitoring exceedances for the reporting period is 1 percent or greater of the total reporting period operating time, or the total CMS downtime for the reporting period is 5 percent or greater of the total reporting period operating time, or any violations according to § 63.864(k)(2) occurred, information from both the summary report and the excess emissions and continuous monitoring system performance report must be submitted. This report will be titled “Excess Emissions and Continuous Monitoring System Performance Report” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section, in addition to the information required in § 63.10(c)(5) through (14), as specified in paragraphs (c)(3)(i) through (vi) of this section. Reporting monitoring exceedances does not constitute a violation of the applicable standard unless the violation criteria in § 63.864(k)(2) and (3) are reached.(i) An identification of the date and time identifying each period during which the CMS was inoperative except for zero (low-level) and high-level checks.(ii) An identification of the date and time identifying each period during which the CMS was out of control, as defined in § 63.8(c)(7).(iii) The specific identification of each period of excess emissions and parameter monitoring exceedances as described in paragraphs (c)(3)(iii)(A) through (E) of this section.(A) (1) The total number of 6-minute averages in the reporting period (excluding process unit downtime).(2) [Reserved](3) The number of 6-minute averages in the reporting period that exceeded the relevant opacity limit.(4) The percent of 6-minute averages in the reporting period that exceed the relevant opacity limit.(5) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(B) [Reserved](C) (1) The operating limits established during the performance test for scrubbing liquid flow rate and pressure drop across the scrubber (or alternatively, fan amperage or RPM if used for smelt dissolving tank scrubbers).(2) The number of 3-hour wet scrubber parameter averages below the minimum operating limit established during the performance test, if applicable.(3) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(D) (1) The operating limit established during the performance test.(2) The number of 1-hour and 3-hour temperature averages below the minimum operating limit established during the performance test.(3) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(E) For alternative parameters established according to § 63.864(e)(13) or (14) subject to the requirements of § 63.864(k)(1) and (2):(1) The type of operating parameters monitored for compliance.(2) The operating limits established during the performance test.(3) The number of 3-hour parameter averages outside of the operating limits established during the performance test.(4) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(11)
-
(15) In order to satisfy the requirements of paragraphs (c)(10) through (c)(12) of this section and to avoid duplicative recordkeeping efforts, the owner or operator may use the affected source's startup, shutdown, and malfunction plan or records kept to satisfy the recordkeeping requirements of the startup, shutdown, and malfunction plan specified in § 63.6(e), provided that such plan and records adequately address the requirements of paragraphs (c)(10) through (c)(12).
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13) of subpart A of this part.
-
(b) You must submit an initial compliance report that provides summary, monitoring system performance, and deviation information to the Administrator on April 5, 2027, or once the report template for this subpart has been available on the Compliance and Emissions Data Reporting Interface (CEDRI) website for one year, whichever date is later, to the EPA via CEDRI, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Anything submitted using CEDRI cannot later be claimed CBI. You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim, submit a complete report, including information claimed to be CBI, to the EPA. The CBI report must be generated using the appropriate form on the CEDRI website or an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website. Submit the CBI file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Commercial Sterilization Facilities Sector Lead, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph. All CBI claims must be asserted at the time of submission. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available. Reports of deviations from an operating limit shall include all information required in § 63.10(c)(5) through (13), as applicable in table 6 to this subpart, along with information from any calibration tests in which the monitoring equipment is not in compliance with Performance Specification 19 in appendix B and Procedure 7 in appendix F to part 60 of this chapter or the method used for parameter monitoring device calibration. Reports shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. If your report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces this requirement. When no deviations have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. In addition, the summary report shall include:(i) Date that facility commenced construction or reconstruction;(ii) Hours of commercial sterilization operation over the previous 12 months; and(iv) If you are electing to determine the mass of EtO sent to the control device from the SCV(s) via the procedure in § 63.364(f)(1)(i), you must report the daily EtO use from each applicable chamber for the previous 7 months.(v) If so, indicate the affected sources that are included in each combined emission stream limitation.(vi) If you are electing to comply with a site-wide emission limit, report the daily EtO use over the previous 7 months.(2) If your sterilization facility is demonstrating continuous compliance through periodic performance testing, you must report the following:(i) Control system ID;(ii) Control device ID;(iii) Control device type; and(iv) Recirculation tank ID if an acid-water scrubber is used to meet the emission standard and you elect to comply with the maximum scrubber liquor height limit;(3) You must report the following for each sterilization chamber at your facility:(i) The sterilization chamber ID;(ii) The ID of the control system that the SCV was routed to, if applicable;(iii) The portion of SCV exhaust that was routed to the control system, if applicable;(iv) The ID of the EtO CEMS that was used to monitor SCV emissions, if applicable;(v) The portion of SCV exhaust that was monitored with the EtO CEMS, if applicable;(vi) The ID of the control system that the CEV was routed to, if applicable;(vii) The portion of CEV exhaust that was routed to the control system, if applicable;(viii) The ID of the EtO CEMS that was used to monitor CEV emissions, if applicable;(ix) The portion of CEV exhaust that was monitored with the EtO CEMS, if applicable;(4) If emissions from any room in your facility are subject to an emission standard, you must report the following for each room where there is the potential for EtO emissions:(i) Room ID;(ii) Documentation of emissions occurring within the room, including aeration, EtO storage, EtO dispensing, pre-aeration handling of sterilized material, and post-aeration handling of sterilized material;(iii) The ID of the control system that the room air was routed to, if applicable;(iv) The portion of room air that was routed to the control system, if applicable;(v) The ID of the EtO CEMS that was used to monitor room air emissions, if applicable;(vi) The portion of room air that was monitored with the EtO CEMS, if applicable;(5) If an EtO CEMS was used to demonstrate continuous compliance with an emission standard for more than 30-operating days, you must report the following:(ii) The affected sources that are included in each inlet that is being monitored with EtO CEMS;(v) The daily sum of EtO emissions from each outlet of the control system, along with 30-operating day rolling sums.(vi) For each day, calculate and report the daily mass emission limit that the control system must achieve based on the previous 30 days of data. For control systems with multiple emission streams, and complying with a combined emission stream limitation in § 63.362(i) or a SWEL in § 63.362(j), report the daily 30-operating day mass emission limit as determined in accordance with CES in § 63.362(i)(1)(i) and (i)(2)(i) or with § 63.362(j)(1)(i) and (j)(2)(i), as applicable.(6) If any portion of your facility is required to be operated with PTE, you must report the following:(i) If you are choosing to demonstrate continuous compliance through the use of volumetric flow rate monitoring, you must report the 3-hr rolling average, rolled hourly volumetric flow from each outlet where air from the PTE is sent, in cubic feet per second.(ii) If you are choosing to demonstrate continuous compliance through use of differential pressure monitoring, you must report the 3-hr rolling average, rolled hourly pressure differential reading, in inches water.(7) If you are complying with the requirement to follow the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door, you must provide a certification from your responsible official that this approach is being followed and you are meeting the monitoring requirements at § 63.362(h).(8) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and facility EtO use is less than 4 tpy, you must report the following for each room where there are Group 2 room air emissions:(i) Room ID;(ii) Number of room air changes per hour;(iii) Room temperature, in degrees Celsius; and(9) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and EtO use is less than 4 tpy, you are not required to report the information in paragraph (b)(8) of this section if you meet the following requirements:(i) You are complying with the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door; and(ii) The requirements of § 63.363 are met.(10) For each instance, report the date, time, the cause and duration of each deviation. For each deviation the report must include a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to determine the emissions.
-
(4) All excess emissions and monitoring system performance reports and all summary reports, if required per paragraph (e)(5) and (6) of this section, shall be delivered or postmarked within 30 days following the end of each calendar year, or within 30 days following the end of each six month period, if appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all information required in § 63.10(c)(5) through (13) of subpart A of this part as applicable in Table 1 of § 63.560 and information from any calibration tests in which the monitoring equipment is not in compliance with PS 8 or other methods used for accuracy testing of temperature, pressure, or flow monitoring devices. The written report shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. This information will be kept for a minimum of 5 years and made readily available to the Administrator or delegated State authority upon request.
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(3) If measured parameters meet any of the conditions specified in § 63.864(k)(1) or (2), the owner or operator of the affected source must submit a semiannual report describing the excess emissions that occurred. If the total duration of monitoring exceedances for the reporting period is 1 percent or greater of the total reporting period operating time, or the total CMS downtime for the reporting period is 5 percent or greater of the total reporting period operating time, or any violations according to § 63.864(k)(2) occurred, information from both the summary report and the excess emissions and continuous monitoring system performance report must be submitted. This report will be titled “Excess Emissions and Continuous Monitoring System Performance Report” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section, in addition to the information required in § 63.10(c)(5) through (14), as specified in paragraphs (c)(3)(i) through (vi) of this section. Reporting monitoring exceedances does not constitute a violation of the applicable standard unless the violation criteria in § 63.864(k)(2) and (3) are reached.(i) An identification of the date and time identifying each period during which the CMS was inoperative except for zero (low-level) and high-level checks.(ii) An identification of the date and time identifying each period during which the CMS was out of control, as defined in § 63.8(c)(7).(iii) The specific identification of each period of excess emissions and parameter monitoring exceedances as described in paragraphs (c)(3)(iii)(A) through (E) of this section.(A) (1) The total number of 6-minute averages in the reporting period (excluding process unit downtime).(2) [Reserved](3) The number of 6-minute averages in the reporting period that exceeded the relevant opacity limit.(4) The percent of 6-minute averages in the reporting period that exceed the relevant opacity limit.(5) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(B) [Reserved](C) (1) The operating limits established during the performance test for scrubbing liquid flow rate and pressure drop across the scrubber (or alternatively, fan amperage or RPM if used for smelt dissolving tank scrubbers).(2) The number of 3-hour wet scrubber parameter averages below the minimum operating limit established during the performance test, if applicable.(3) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(D) (1) The operating limit established during the performance test.(2) The number of 1-hour and 3-hour temperature averages below the minimum operating limit established during the performance test.(3) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(E) For alternative parameters established according to § 63.864(e)(13) or (14) subject to the requirements of § 63.864(k)(1) and (2):(1) The type of operating parameters monitored for compliance.(2) The operating limits established during the performance test.(3) The number of 3-hour parameter averages outside of the operating limits established during the performance test.(4) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(12)
-
(15) In order to satisfy the requirements of paragraphs (c)(10) through (c)(12) of this section and to avoid duplicative recordkeeping efforts, the owner or operator may use the affected source's startup, shutdown, and malfunction plan or records kept to satisfy the recordkeeping requirements of the startup, shutdown, and malfunction plan specified in § 63.6(e), provided that such plan and records adequately address the requirements of paragraphs (c)(10) through (c)(12).
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13) of subpart A of this part.
-
(b) You must submit an initial compliance report that provides summary, monitoring system performance, and deviation information to the Administrator on April 5, 2027, or once the report template for this subpart has been available on the Compliance and Emissions Data Reporting Interface (CEDRI) website for one year, whichever date is later, to the EPA via CEDRI, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Anything submitted using CEDRI cannot later be claimed CBI. You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim, submit a complete report, including information claimed to be CBI, to the EPA. The CBI report must be generated using the appropriate form on the CEDRI website or an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website. Submit the CBI file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Commercial Sterilization Facilities Sector Lead, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph. All CBI claims must be asserted at the time of submission. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available. Reports of deviations from an operating limit shall include all information required in § 63.10(c)(5) through (13), as applicable in table 6 to this subpart, along with information from any calibration tests in which the monitoring equipment is not in compliance with Performance Specification 19 in appendix B and Procedure 7 in appendix F to part 60 of this chapter or the method used for parameter monitoring device calibration. Reports shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. If your report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces this requirement. When no deviations have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. In addition, the summary report shall include:(i) Date that facility commenced construction or reconstruction;(ii) Hours of commercial sterilization operation over the previous 12 months; and(iv) If you are electing to determine the mass of EtO sent to the control device from the SCV(s) via the procedure in § 63.364(f)(1)(i), you must report the daily EtO use from each applicable chamber for the previous 7 months.(v) If so, indicate the affected sources that are included in each combined emission stream limitation.(vi) If you are electing to comply with a site-wide emission limit, report the daily EtO use over the previous 7 months.(2) If your sterilization facility is demonstrating continuous compliance through periodic performance testing, you must report the following:(i) Control system ID;(ii) Control device ID;(iii) Control device type; and(iv) Recirculation tank ID if an acid-water scrubber is used to meet the emission standard and you elect to comply with the maximum scrubber liquor height limit;(3) You must report the following for each sterilization chamber at your facility:(i) The sterilization chamber ID;(ii) The ID of the control system that the SCV was routed to, if applicable;(iii) The portion of SCV exhaust that was routed to the control system, if applicable;(iv) The ID of the EtO CEMS that was used to monitor SCV emissions, if applicable;(v) The portion of SCV exhaust that was monitored with the EtO CEMS, if applicable;(vi) The ID of the control system that the CEV was routed to, if applicable;(vii) The portion of CEV exhaust that was routed to the control system, if applicable;(viii) The ID of the EtO CEMS that was used to monitor CEV emissions, if applicable;(ix) The portion of CEV exhaust that was monitored with the EtO CEMS, if applicable;(4) If emissions from any room in your facility are subject to an emission standard, you must report the following for each room where there is the potential for EtO emissions:(i) Room ID;(ii) Documentation of emissions occurring within the room, including aeration, EtO storage, EtO dispensing, pre-aeration handling of sterilized material, and post-aeration handling of sterilized material;(iii) The ID of the control system that the room air was routed to, if applicable;(iv) The portion of room air that was routed to the control system, if applicable;(v) The ID of the EtO CEMS that was used to monitor room air emissions, if applicable;(vi) The portion of room air that was monitored with the EtO CEMS, if applicable;(5) If an EtO CEMS was used to demonstrate continuous compliance with an emission standard for more than 30-operating days, you must report the following:(ii) The affected sources that are included in each inlet that is being monitored with EtO CEMS;(v) The daily sum of EtO emissions from each outlet of the control system, along with 30-operating day rolling sums.(vi) For each day, calculate and report the daily mass emission limit that the control system must achieve based on the previous 30 days of data. For control systems with multiple emission streams, and complying with a combined emission stream limitation in § 63.362(i) or a SWEL in § 63.362(j), report the daily 30-operating day mass emission limit as determined in accordance with CES in § 63.362(i)(1)(i) and (i)(2)(i) or with § 63.362(j)(1)(i) and (j)(2)(i), as applicable.(6) If any portion of your facility is required to be operated with PTE, you must report the following:(i) If you are choosing to demonstrate continuous compliance through the use of volumetric flow rate monitoring, you must report the 3-hr rolling average, rolled hourly volumetric flow from each outlet where air from the PTE is sent, in cubic feet per second.(ii) If you are choosing to demonstrate continuous compliance through use of differential pressure monitoring, you must report the 3-hr rolling average, rolled hourly pressure differential reading, in inches water.(7) If you are complying with the requirement to follow the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door, you must provide a certification from your responsible official that this approach is being followed and you are meeting the monitoring requirements at § 63.362(h).(8) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and facility EtO use is less than 4 tpy, you must report the following for each room where there are Group 2 room air emissions:(i) Room ID;(ii) Number of room air changes per hour;(iii) Room temperature, in degrees Celsius; and(9) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and EtO use is less than 4 tpy, you are not required to report the information in paragraph (b)(8) of this section if you meet the following requirements:(i) You are complying with the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door; and(ii) The requirements of § 63.363 are met.(10) For each instance, report the date, time, the cause and duration of each deviation. For each deviation the report must include a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to determine the emissions.
-
(4) All excess emissions and monitoring system performance reports and all summary reports, if required per paragraph (e)(5) and (6) of this section, shall be delivered or postmarked within 30 days following the end of each calendar year, or within 30 days following the end of each six month period, if appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all information required in § 63.10(c)(5) through (13) of subpart A of this part as applicable in Table 1 of § 63.560 and information from any calibration tests in which the monitoring equipment is not in compliance with PS 8 or other methods used for accuracy testing of temperature, pressure, or flow monitoring devices. The written report shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. This information will be kept for a minimum of 5 years and made readily available to the Administrator or delegated State authority upon request.
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(3) If measured parameters meet any of the conditions specified in § 63.864(k)(1) or (2), the owner or operator of the affected source must submit a semiannual report describing the excess emissions that occurred. If the total duration of monitoring exceedances for the reporting period is 1 percent or greater of the total reporting period operating time, or the total CMS downtime for the reporting period is 5 percent or greater of the total reporting period operating time, or any violations according to § 63.864(k)(2) occurred, information from both the summary report and the excess emissions and continuous monitoring system performance report must be submitted. This report will be titled “Excess Emissions and Continuous Monitoring System Performance Report” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section, in addition to the information required in § 63.10(c)(5) through (14), as specified in paragraphs (c)(3)(i) through (vi) of this section. Reporting monitoring exceedances does not constitute a violation of the applicable standard unless the violation criteria in § 63.864(k)(2) and (3) are reached.(i) An identification of the date and time identifying each period during which the CMS was inoperative except for zero (low-level) and high-level checks.(ii) An identification of the date and time identifying each period during which the CMS was out of control, as defined in § 63.8(c)(7).(iii) The specific identification of each period of excess emissions and parameter monitoring exceedances as described in paragraphs (c)(3)(iii)(A) through (E) of this section.(A) (1) The total number of 6-minute averages in the reporting period (excluding process unit downtime).(2) [Reserved](3) The number of 6-minute averages in the reporting period that exceeded the relevant opacity limit.(4) The percent of 6-minute averages in the reporting period that exceed the relevant opacity limit.(5) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(B) [Reserved](C) (1) The operating limits established during the performance test for scrubbing liquid flow rate and pressure drop across the scrubber (or alternatively, fan amperage or RPM if used for smelt dissolving tank scrubbers).(2) The number of 3-hour wet scrubber parameter averages below the minimum operating limit established during the performance test, if applicable.(3) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(D) (1) The operating limit established during the performance test.(2) The number of 1-hour and 3-hour temperature averages below the minimum operating limit established during the performance test.(3) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(E) For alternative parameters established according to § 63.864(e)(13) or (14) subject to the requirements of § 63.864(k)(1) and (2):(1) The type of operating parameters monitored for compliance.(2) The operating limits established during the performance test.(3) The number of 3-hour parameter averages outside of the operating limits established during the performance test.(4) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(13)
-
(v) All excess emissions and monitoring system performance reports and all summary reports, if required, shall be delivered or postmarked by the 30th day following the end of each calendar half or quarter, as appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all the information required in paragraphs (c)(5) through (c)(13) of this section, in §§ 63.8(c)(7) and 63.8(c)(8), and in the relevant standard, and they shall contain the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances of a parameter have occurred, or a CMS has not been inoperative, out of control, repaired, or adjusted, such information shall be stated in the report.
-
(2) The records specified in § 63.10(b)(2) and (c)(1) through (13).
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(D) When a continuous monitoring system is used, the information required in § 63.10(c)(5) through (13) of subpart A of this part.
-
(b) You must submit an initial compliance report that provides summary, monitoring system performance, and deviation information to the Administrator on April 5, 2027, or once the report template for this subpart has been available on the Compliance and Emissions Data Reporting Interface (CEDRI) website for one year, whichever date is later, to the EPA via CEDRI, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Anything submitted using CEDRI cannot later be claimed CBI. You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim, submit a complete report, including information claimed to be CBI, to the EPA. The CBI report must be generated using the appropriate form on the CEDRI website or an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website. Submit the CBI file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Commercial Sterilization Facilities Sector Lead, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph. All CBI claims must be asserted at the time of submission. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available. Reports of deviations from an operating limit shall include all information required in § 63.10(c)(5) through (13), as applicable in table 6 to this subpart, along with information from any calibration tests in which the monitoring equipment is not in compliance with Performance Specification 19 in appendix B and Procedure 7 in appendix F to part 60 of this chapter or the method used for parameter monitoring device calibration. Reports shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. If your report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces this requirement. When no deviations have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. In addition, the summary report shall include:(i) Date that facility commenced construction or reconstruction;(ii) Hours of commercial sterilization operation over the previous 12 months; and(iv) If you are electing to determine the mass of EtO sent to the control device from the SCV(s) via the procedure in § 63.364(f)(1)(i), you must report the daily EtO use from each applicable chamber for the previous 7 months.(v) If so, indicate the affected sources that are included in each combined emission stream limitation.(vi) If you are electing to comply with a site-wide emission limit, report the daily EtO use over the previous 7 months.(2) If your sterilization facility is demonstrating continuous compliance through periodic performance testing, you must report the following:(i) Control system ID;(ii) Control device ID;(iii) Control device type; and(iv) Recirculation tank ID if an acid-water scrubber is used to meet the emission standard and you elect to comply with the maximum scrubber liquor height limit;(3) You must report the following for each sterilization chamber at your facility:(i) The sterilization chamber ID;(ii) The ID of the control system that the SCV was routed to, if applicable;(iii) The portion of SCV exhaust that was routed to the control system, if applicable;(iv) The ID of the EtO CEMS that was used to monitor SCV emissions, if applicable;(v) The portion of SCV exhaust that was monitored with the EtO CEMS, if applicable;(vi) The ID of the control system that the CEV was routed to, if applicable;(vii) The portion of CEV exhaust that was routed to the control system, if applicable;(viii) The ID of the EtO CEMS that was used to monitor CEV emissions, if applicable;(ix) The portion of CEV exhaust that was monitored with the EtO CEMS, if applicable;(4) If emissions from any room in your facility are subject to an emission standard, you must report the following for each room where there is the potential for EtO emissions:(i) Room ID;(ii) Documentation of emissions occurring within the room, including aeration, EtO storage, EtO dispensing, pre-aeration handling of sterilized material, and post-aeration handling of sterilized material;(iii) The ID of the control system that the room air was routed to, if applicable;(iv) The portion of room air that was routed to the control system, if applicable;(v) The ID of the EtO CEMS that was used to monitor room air emissions, if applicable;(vi) The portion of room air that was monitored with the EtO CEMS, if applicable;(5) If an EtO CEMS was used to demonstrate continuous compliance with an emission standard for more than 30-operating days, you must report the following:(ii) The affected sources that are included in each inlet that is being monitored with EtO CEMS;(v) The daily sum of EtO emissions from each outlet of the control system, along with 30-operating day rolling sums.(vi) For each day, calculate and report the daily mass emission limit that the control system must achieve based on the previous 30 days of data. For control systems with multiple emission streams, and complying with a combined emission stream limitation in § 63.362(i) or a SWEL in § 63.362(j), report the daily 30-operating day mass emission limit as determined in accordance with CES in § 63.362(i)(1)(i) and (i)(2)(i) or with § 63.362(j)(1)(i) and (j)(2)(i), as applicable.(6) If any portion of your facility is required to be operated with PTE, you must report the following:(i) If you are choosing to demonstrate continuous compliance through the use of volumetric flow rate monitoring, you must report the 3-hr rolling average, rolled hourly volumetric flow from each outlet where air from the PTE is sent, in cubic feet per second.(ii) If you are choosing to demonstrate continuous compliance through use of differential pressure monitoring, you must report the 3-hr rolling average, rolled hourly pressure differential reading, in inches water.(7) If you are complying with the requirement to follow the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door, you must provide a certification from your responsible official that this approach is being followed and you are meeting the monitoring requirements at § 63.362(h).(8) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and facility EtO use is less than 4 tpy, you must report the following for each room where there are Group 2 room air emissions:(i) Room ID;(ii) Number of room air changes per hour;(iii) Room temperature, in degrees Celsius; and(9) If you own or operate an existing collection of Group 2 room air emissions at an area source facility and EtO use is less than 4 tpy, you are not required to report the information in paragraph (b)(8) of this section if you meet the following requirements:(i) You are complying with the best management practice to limit sterilization chamber concentration of EtO to 1 ppmv prior to opening the sterilization chamber door; and(ii) The requirements of § 63.363 are met.(10) For each instance, report the date, time, the cause and duration of each deviation. For each deviation the report must include a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to determine the emissions.
-
(4) All excess emissions and monitoring system performance reports and all summary reports, if required per paragraph (e)(5) and (6) of this section, shall be delivered or postmarked within 30 days following the end of each calendar year, or within 30 days following the end of each six month period, if appropriate. Written reports of excess emissions or exceedances of process or control system parameters shall include all information required in § 63.10(c)(5) through (13) of subpart A of this part as applicable in Table 1 of § 63.560 and information from any calibration tests in which the monitoring equipment is not in compliance with PS 8 or other methods used for accuracy testing of temperature, pressure, or flow monitoring devices. The written report shall also include the name, title, and signature of the responsible official who is certifying the accuracy of the report. When no excess emissions or exceedances have occurred or monitoring equipment has not been inoperative, repaired, or adjusted, such information shall be stated in the report. This information will be kept for a minimum of 5 years and made readily available to the Administrator or delegated State authority upon request.
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(3) If measured parameters meet any of the conditions specified in § 63.864(k)(1) or (2), the owner or operator of the affected source must submit a semiannual report describing the excess emissions that occurred. If the total duration of monitoring exceedances for the reporting period is 1 percent or greater of the total reporting period operating time, or the total CMS downtime for the reporting period is 5 percent or greater of the total reporting period operating time, or any violations according to § 63.864(k)(2) occurred, information from both the summary report and the excess emissions and continuous monitoring system performance report must be submitted. This report will be titled “Excess Emissions and Continuous Monitoring System Performance Report” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section, in addition to the information required in § 63.10(c)(5) through (14), as specified in paragraphs (c)(3)(i) through (vi) of this section. Reporting monitoring exceedances does not constitute a violation of the applicable standard unless the violation criteria in § 63.864(k)(2) and (3) are reached.(i) An identification of the date and time identifying each period during which the CMS was inoperative except for zero (low-level) and high-level checks.(ii) An identification of the date and time identifying each period during which the CMS was out of control, as defined in § 63.8(c)(7).(iii) The specific identification of each period of excess emissions and parameter monitoring exceedances as described in paragraphs (c)(3)(iii)(A) through (E) of this section.(A) (1) The total number of 6-minute averages in the reporting period (excluding process unit downtime).(2) [Reserved](3) The number of 6-minute averages in the reporting period that exceeded the relevant opacity limit.(4) The percent of 6-minute averages in the reporting period that exceed the relevant opacity limit.(5) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(B) [Reserved](C) (1) The operating limits established during the performance test for scrubbing liquid flow rate and pressure drop across the scrubber (or alternatively, fan amperage or RPM if used for smelt dissolving tank scrubbers).(2) The number of 3-hour wet scrubber parameter averages below the minimum operating limit established during the performance test, if applicable.(3) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(D) (1) The operating limit established during the performance test.(2) The number of 1-hour and 3-hour temperature averages below the minimum operating limit established during the performance test.(3) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(E) For alternative parameters established according to § 63.864(e)(13) or (14) subject to the requirements of § 63.864(k)(1) and (2):(1) The type of operating parameters monitored for compliance.(2) The operating limits established during the performance test.(3) The number of 3-hour parameter averages outside of the operating limits established during the performance test.(4) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(c)(14)
-
(4) The owner or operator of an affected source who elects to install a continuous monitoring system shall maintain records specified in § 63.10(c)(1) through (14).
-
(4) The owner or operator of an affected source who installs a continuous monitoring system to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) shall maintain records specified in § 63.10(c)(1) through (14) of subpart A of this part.
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
(3) If measured parameters meet any of the conditions specified in § 63.864(k)(1) or (2), the owner or operator of the affected source must submit a semiannual report describing the excess emissions that occurred. If the total duration of monitoring exceedances for the reporting period is 1 percent or greater of the total reporting period operating time, or the total CMS downtime for the reporting period is 5 percent or greater of the total reporting period operating time, or any violations according to § 63.864(k)(2) occurred, information from both the summary report and the excess emissions and continuous monitoring system performance report must be submitted. This report will be titled “Excess Emissions and Continuous Monitoring System Performance Report” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section, in addition to the information required in § 63.10(c)(5) through (14), as specified in paragraphs (c)(3)(i) through (vi) of this section. Reporting monitoring exceedances does not constitute a violation of the applicable standard unless the violation criteria in § 63.864(k)(2) and (3) are reached.(i) An identification of the date and time identifying each period during which the CMS was inoperative except for zero (low-level) and high-level checks.(ii) An identification of the date and time identifying each period during which the CMS was out of control, as defined in § 63.8(c)(7).(iii) The specific identification of each period of excess emissions and parameter monitoring exceedances as described in paragraphs (c)(3)(iii)(A) through (E) of this section.(A) (1) The total number of 6-minute averages in the reporting period (excluding process unit downtime).(2) [Reserved](3) The number of 6-minute averages in the reporting period that exceeded the relevant opacity limit.(4) The percent of 6-minute averages in the reporting period that exceed the relevant opacity limit.(5) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(B) [Reserved](C) (1) The operating limits established during the performance test for scrubbing liquid flow rate and pressure drop across the scrubber (or alternatively, fan amperage or RPM if used for smelt dissolving tank scrubbers).(2) The number of 3-hour wet scrubber parameter averages below the minimum operating limit established during the performance test, if applicable.(3) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(D) (1) The operating limit established during the performance test.(2) The number of 1-hour and 3-hour temperature averages below the minimum operating limit established during the performance test.(3) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(E) For alternative parameters established according to § 63.864(e)(13) or (14) subject to the requirements of § 63.864(k)(1) and (2):(1) The type of operating parameters monitored for compliance.(2) The operating limits established during the performance test.(3) The number of 3-hour parameter averages outside of the operating limits established during the performance test.(4) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
Citations to §63.10(d)
-
(1) If your actions were consistent with your SSMP, you must include the information specified in § 63.10(d) in the semiannual compliance report required by paragraph (a) of this section.
-
(1) If your actions were consistent with your SSMP, you must include the information specified in § 63.10(d) in the semiannual compliance report required by paragraph (a) of this section.
-
(a) The owner or operator of an affected source subject to the emissions standards in § 63.362 must fulfill all reporting requirements in § 63.10(a), (d), (e), and (f), according to the applicability in table 6 to this subpart. These reports will be made to the Administrator at the appropriate address identified in § 63.13 or submitted electronically.
-
(1) If your actions were consistent with your startup, shutdown, and malfunction plan, you must include the information specified in § 63.10(d) in the semiannual compliance report required by paragraph (a) of this section.
-
(1) If your actions were consistent with your startup, shutdown, and malfunction plan, you must include the information specified in § 63.10(d) in the semiannual compliance report.
-
(1) If your actions were consistent with your startup, shutdown, and malfunction plan, you must include the information specified in § 63.10(d) in the semiannual compliance report required by paragraph (a) of this section.
-
(1) If your actions were consistent with your SSMP, you must include the information specified in § 63.10(d) in the semiannual compliance report required by paragraph (a) of this section.
-
(iii) The owner or operator of an affected source to which an opacity or visible emission standard in this part applies shall conduct opacity or visible emission observations in accordance with the provisions of this section, record the results of the evaluation of emissions, and report to the Administrator the opacity or visible emission results in accordance with the provisions of § 63.10(d).
-
(2) As required by § 63.10(d), you must report the results of the initial and subsequent performance tests as part of the notification of compliance status required in § 63.9(h). You must verify in the performance test reports that the operating limits for each process have not changed or provide documentation of revised operating limits established according to § 63.605, as applicable. In the notification of compliance status, you must also:(i) Certify to the Administrator annually that you have complied with the evaporative cooling tower requirements specified in § 63.602(c).(ii) Submit analyses and supporting documentation demonstrating conformance with the Office Of Air Quality Planning And Standards (OAQPS), Fabric Filter Bag Leak Detection Guidance (incorporated by reference, see § 63.14) and specifications for bag leak detection systems as part of the notification of compliance status report.(iii) Submit the gypsum dewatering stack and cooling pond management plan specified in § 63.602(e).(iv) If you elect to demonstrate compliance by following the procedures in § 63.605(d)(1)(ii)(B), certify to the Administrator annually that the control devices and processes have not been modified since the date of the performance test from which you obtained the data used to establish the allowable ranges.(v) Each time a gypsum dewatering stack is closed, certify to the Administrator within 90 days of closure, that the final cover of the closed gypsum dewatering stack is a drought resistant vegetative cover that includes a barrier soil layer that will sustain vegetation.
-
(2) As required by § 63.10(d), you must report the results of the initial and subsequent performance tests as part of the notification of compliance status required in § 63.9(h). You must verify in the performance test reports that the operating limits for each process have not changed or provide documentation of revised operating limits established according to § 63.625, as applicable. In the notification of compliance status, you must also:(i) Certify to the Administrator that you have not shipped fresh granular triple superphosphate from an affected facility.(ii) Certify to the Administrator annually that you have complied with the evaporative cooling tower requirements specified in § 63.622(c).(iii) Submit analyses and supporting documentation demonstrating conformance with the Office Of Air Quality Planning And Standards (OAQPS), Fabric Filter Bag Leak Detection Guidance (incorporated by reference, see § 63.14) and specifications for bag leak detection systems as part of the notification of compliance status report.(iv) If you elect to demonstrate compliance by following the procedures in § 63.625(d)(1)(ii)(B), certify to the Administrator annually that the control devices and processes have not been modified since the date of the performance test from which you obtained the data used to establish the allowable ranges.
-
(1) Magnetic tape manufacturing operations that are subject to § 63.703(b) and are not at major sources are not subject to §§ 63.6(e), 63.6(f), 63.6(g), 63.6(i)(4), 63.7, 63.8, 63.9 (c) through (h), 63.10(b)(2), 63.10(c), 63.10(d) (2) through (5), 63.10(e), and 63.11 of subpart A.
-
(d) For each deviation from an emission limitation (emission limit, operating limit, opacity limit, and VE limit) that occurs at an affected source where you are not using a CMS to comply with the emission limitations in this subpart, the compliance report must contain the information specified in paragraphs (c)(1) through (4) and (d)(1) and (2) of this section. The deviations must be reported in accordance with the requirements in § 63.10(d) prior to the relevant compliance date for your source as specified in § 63.7083(g) and the requirements in § 63.10(d)(1) through (4) beginning on the relevant compliance date for your source as specified in § 63.7083(g).(2) Information on the number, duration, and cause of deviations (including unknown cause, if applicable), and the corrective action taken.(3) An estimate of the quantity of each regulated pollutant emitted over a non-opacity or VE emission limit, and a description of the method used to estimate the emissions.
-
(a) . Each owner or operator of a source subject to this subpart shall fulfill all recordkeeping requirements specified in § 63.10(a), (b), (d), and (f), except § 63.10(b)(2)(i), (iv) and (v). Each owner or operator must also record and maintain according to § 63.10(b)(1) the information specified in paragraph (a)(1) through (3) of this section.(1) In the event that an affected unit fails to meet an applicable standard, record the number of failures. For each failure record the date, time, and duration of each failure.(2) For each failure to meet an applicable standard, record and retain a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(3) Record actions taken to minimize emissions in accordance with § 63.743(e), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(1) Except as provided in paragraphs (a)(2) through (5) of this section, each owner or operator subject to this subpart shall fulfill the requirements contained in § 63.9(a) through (e) and (h) through (j), Notification requirements, and § 63.10(a), (b), (d), and (f), Recordkeeping and reporting requirements, of the General Provisions, 40 CFR part 63, subpart A, and that the initial notification for existing sources required in § 63.9(b)(2) shall be submitted not later than September 1, 1997, or as specified in § 63.9(b)(2). In addition to the requirements of § 63.9(h), the notification of compliance status shall include:(i) Information detailing whether the source has operated within the specified ranges of its designated operating parameters.(ii) For each coating line, where averaging will be used along with the types of quantities of coatings the facility expects to use in the first year of operation. Averaging scheme shall be approved by the Administrator or delegated State authority and shall be included as part of the facility's title V or part 70 permit.
-
(a) Each owner or operator of an affected source shall comply with the applicable recordkeeping and reporting requirements in § 63.10 (a), (b), (d), and (f). Any owner that receives approval pursuant to § 63.783(c) to use an add-on control system to control coating emissions shall also comply with the applicable requirements of § 63.10 (c) and (e). A summary of recordkeeping and reporting requirements is provided in Table 3 of this subpart.
Citations to §63.10(d)(1)
-
(j) You must comply with the following requirements of the general provisions in subpart A of this part: §§ 63.1 through 63.5; § 63.6(a), (b), and (c); § 63.9; § 63.10(a), (b)(1), (b)(2)(xiv), (b)(3), (d)(1) and (4), and (f); and §§ 63.13 through 63.16. Requirements of the general provisions not cited in the preceding sentence do not apply to the owner or operator of a new or existing affected source that is classified as a small foundry.
-
(d) For each deviation from an emission limitation (emission limit, operating limit, opacity limit, and VE limit) that occurs at an affected source where you are not using a CMS to comply with the emission limitations in this subpart, the compliance report must contain the information specified in paragraphs (c)(1) through (4) and (d)(1) and (2) of this section. The deviations must be reported in accordance with the requirements in § 63.10(d) prior to the relevant compliance date for your source as specified in § 63.7083(g) and the requirements in § 63.10(d)(1) through (4) beginning on the relevant compliance date for your source as specified in § 63.7083(g).(2) Information on the number, duration, and cause of deviations (including unknown cause, if applicable), and the corrective action taken.(3) An estimate of the quantity of each regulated pollutant emitted over a non-opacity or VE emission limit, and a description of the method used to estimate the emissions.
Citations to §63.10(d)(2)
-
(1) If you own or operate an affected furnace and are required to conduct a performance test, you must submit a Notification of Compliance Status, including the performance test results, before the close of business on the 60th day following the completion of the performance test, according to § 60.8 or § 63.10(d)(2).
-
(5) You must submit a Notification of Compliance Status according to § 63.9(h)(2)(ii). You must submit the Notification of Compliance Status, including the compliance test results, before the close of business on the 60th calendar day following the completion of the compliance test according to § 63.10(d)(2).
-
(1) As required by § 63.10(d)(2), the owner or operator shall report the results of performance tests as part of the notification of compliance status.
-
(2) For each initial compliance demonstration that includes a performance test, you must submit the notification of compliance status, including the performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to § 63.10(d)(2).
-
(2) As required by § 63.10(d)(2), the owner or operator of an affected source must report the results of the initial performance test as part of the notification of compliance status required in § 63.1658(f).
-
(b) You must submit the notification of compliance status, including the performance test results, the operating limits or ranges as determined during the performance test, and other information specified in § 63.9(h), before the close of business on the 60th calendar day after you complete the performance test according to § 63.10(d)(2).
-
(b) If you use add-on control devices, you must submit reports of performance test results for emission capture systems and add-on control devices no later than 60 days after completing the tests as specified in § 63.10(d)(2). You must submit reports of transfer efficiency tests no later than 60 days after completing the tests as specified in § 63.10(d)(2).
-
(f) You must submit performance test reports as specified in § 63.10(d)(2) if you are using a control device to comply with the emission standard and you have not obtained a waiver from the performance test requirement or you are not exempted from this requirement by § 63.3360(b). Catalyst activity test results are not required to be submitted but must be maintained onsite. Within 60 days after the date of completing each performance test required by this subpart, you must submit the results of the performance test following the procedures specified in paragraphs (f)(1) through (3) of this section. For affected sources that commence construction or reconstruction after September 19, 2019, the performance test reports must be submitted electronically using the procedure in paragraph (h) of this section. For affected sources that commenced construction or reconstruction on or before September 19, 2019, the performance test reports must be submitted electronically using the procedure in paragraph (h) starting July 9, 2021.(1) Submit the results of the performance test to EPA via CEDRI, which can be accessed through EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The data must be submitted in a file format generated through the use of EPA's ERT. Alternatively, you may submit an electronic file consistent with the extensible markup language (XML) schema listed on EPA's ERT website.(2) The results of the performance test must be included as an attachment in the ERT or an alternate electronic file consistent with the XML schema listed on EPA's ERT website. Submit the ERT generated package or alternative file to EPA via CEDRI.(3) If you claim some of the information submitted under paragraph (f)(1) of this section is CBI, you must submit a complete file, including information claimed to be CBI, to EPA. The file must be generated through the use of EPA's ERT or an alternate electronic file consistent with the XML schema listed on EPA's ERT website. Submit the file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Group Leader, Measurement Policy Group, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to EPA via EPA's CDX as described in paragraph (f)(1) of this section.
-
(b) If you use the emission rate with add-on controls option or the control efficiency/outlet concentration option, you must submit reports of performance test results for emission capture systems and add-on control devices no later than 60 days after completing the tests as specified in § 63.10(d)(2).
-
(b) If you use the emission rate with add-on controls option, you must submit reports of performance test results for emission capture systems and add-on control devices no later than 60 days after completing the tests as specified in § 63.10(d)(2).
-
(h) If you use the emission rate with add-on controls option, you must submit reports of performance test results for emission capture systems and add-on control devices no later than 60 days after completing the tests as specified in § 63.10(d)(2).
-
(b) If you use one of the add-on control options in § 63.4291(a) or (c), you must submit reports of performance test results for emission capture systems and add-on control devices no later than 60 days after completing the tests as specified in § 63.10(d)(2).
-
(b) If you use the emission rate with add-on controls option, you must submit reports of performance test results for emission capture systems and add-on control devices no later than 60 days after completing the tests as specified in § 63.10(d)(2).
-
(b) If you use the emission rate with add-on controls option, you must submit reports of performance test results for emission capture systems and add-on control devices no later than 60 days after completing the tests as specified in § 63.10(d)(2).
-
(b) If you use the emission rate with add-on controls option, you must submit reports of performance test results for emission capture systems and add-on control devices no later than 60 days after completing the tests as specified in § 63.10(d)(2).
-
(e) You must submit performance test reports as specified in § 63.10(d)(2) if you are using a control device to comply with the emission standards and you have not obtained a waiver from the performance test requirement.
-
(2) Before January 21, 2021, for each initial compliance demonstration required in tables 6 through 8 to this subpart that includes a performance test conducted according to the requirements in table 5 to this subpart, you must submit the Notification of Compliance Status, including the performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to § 63.10(d)(2). After January 20, 2021, for each initial compliance demonstration required in tables 6 through 8 to this subpart that includes a performance test conducted according to the requirements in table 5 to this subpart, you must submit the Notification of Compliance Status, including the performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to §§ 63.10(d)(2) and 63.6010(h)(1) through (3).
-
(a) You must comply with the notification requirements specified in § 63.9. During the most recent performance test, if you demonstrate compliance with the emission limit while operating your control device outside the previously established operating limit, you must establish a new operating limit based on that most recent performance test and notify the Administrator that the operating limit changed based on data collected during the most recent performance test. When a source is retested and the performance test results are submitted to the Administrator pursuant to paragraph (b)(1) of this section, § 63.7(g)(1), or § 63.10(d)(2), you must indicate whether the operating limit is based on the new performance test or the previously established limit. Upon establishment of a new operating limit, you must thereafter operate under the new operating limit. If the Administrator determines that you did not conduct the compliance test in accordance with the applicable requirements or that the operating limit established during the performance test does not correspond to representative (normal) conditions, you must conduct a new performance test and establish a new operating limit.
-
(a) You must comply with the notification requirements specified in § 63.9. During the most recent performance test, if you demonstrate compliance with the emission limit while operating your control device outside the previously established operating limit, you must establish a new operating limit based on that most recent performance test and notify the Administrator that the operating limit changed based on data collected during the most recent performance test. When a source is retested and the performance test results are submitted to the Administrator pursuant to paragraph (b)(1) of this section, § 63.7(g)(1), or § 63.10(d)(2), you must indicate whether the operating limit is based on the new performance test or the previously established limit. Upon establishment of a new operating limit, you must thereafter operate under the new operating limit. If the Administrator determines that you did not conduct the compliance test in accordance with the applicable requirements or that the operating limit established during the performance test does not correspond to representative (normal) conditions, you must conduct a new performance test and establish a new operating limit.
-
(2) Before February 26, 2025, for each initial compliance demonstration required in table 5 to this subpart that includes a performance test conducted according to the requirements in table 3 to this subpart, you must submit the Notification of Compliance Status, including the performance test results, before the close of business on the 60th day following the completion of the performance test according to § 63.10(d)(2). Beginning on February 26, 2025, for each initial compliance demonstration required in table 5 to this subpart that includes a performance test conducted according to the requirements in table 3 to this subpart, you must submit the Notification of Compliance Status, including a summary of the performance test results, in PDF to the EPA via the Compliance and Emissions Data Reporting Interface (CEDRI), before the close of business on the 60th day following the completion of the performance test following the procedure specified in § 63.9(k), except any Confidential Business Information (CBI) is to be submitted according to paragraphs (h)(2)(i) and (ii) of this section. Do not use CEDRI to submit information you claim as CBI. Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim for some of the information in the report, you must submit a complete file, including information claimed to be CBI, to the EPA following the procedures in paragraphs (h)(2)(i) and (ii) of this section. Clearly mark the part or all of the information that you claim to be CBI. Information not marked as CBI may be authorized for public release without prior notice. Information marked as CBI will not be disclosed except in accordance with procedures set forth in 40 CFR part 2. All CBI claims must be asserted at the time of submission. Anything submitted using CEDRI cannot later be claimed CBI. Furthermore, under CAA section 114(c), emissions data is not entitled to confidential treatment, and the EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available. You must submit the same file submitted to the CBI office with the CBI omitted to the EPA via the EPA's CDX as described earlier in this paragraph (h)(2).(i) The preferred method to receive CBI is for it to be transmitted electronically using email attachments, File Transfer Protocol, or other online file sharing services. Electronic submissions must be transmitted directly to the OAQPS CBI Office at the email address [email protected], and as described in paragraph (h)(2) of this section, should include clear CBI markings and be flagged to the attention of the Reciprocating Internal Combustion Engine Sector Lead. If assistance is needed with submitting large electronic files that exceed the file size limit for email attachments, and if you do not have your own file sharing service, please email [email protected] to request a file transfer link.(ii) If you cannot transmit the file electronically, you may send CBI information through the postal service to the following address: OAQPS Document Control Officer (C404-02), OAQPS, U.S. Environmental Protection Agency, 109 T.W. Alexander Drive, P.O. Box 12055, Research Triangle Park, North Carolina 27711, Attention Reciprocating Internal Combustion Engine Sector Lead. The mailed CBI material should be double wrapped and clearly marked. Any CBI markings should not show through the outer envelope.
-
(2) Performance test reports specified in § 63.10(d)(2) of this part, and
-
(2) For each compliance demonstration required in Table 6 to this subpart that includes a performance test conducted according to the requirements in Table 5 to this subpart, you must submit the Notification of Compliance Status, including the performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to § 63.10(d)(2).
-
(d) For each deviation from an emission limitation (emission limit, operating limit, opacity limit, and VE limit) that occurs at an affected source where you are not using a CMS to comply with the emission limitations in this subpart, the compliance report must contain the information specified in paragraphs (c)(1) through (4) and (d)(1) and (2) of this section. The deviations must be reported in accordance with the requirements in § 63.10(d) prior to the relevant compliance date for your source as specified in § 63.7083(g) and the requirements in § 63.10(d)(1) through (4) beginning on the relevant compliance date for your source as specified in § 63.7083(g).(2) Information on the number, duration, and cause of deviations (including unknown cause, if applicable), and the corrective action taken.(3) An estimate of the quantity of each regulated pollutant emitted over a non-opacity or VE emission limit, and a description of the method used to estimate the emissions.
-
(2) For each initial compliance demonstration that does include a performance test, you must submit the notification of compliance status, including a summary of the performance test results, before the close of business on the 60th calendar day following completion of the performance test according to § 63.10(d)(2).
-
(e) If you are required to conduct an initial compliance demonstration as specified in § 63.7530, you must submit a Notification of Compliance Status according to § 63.9(h)(2)(ii). For the initial compliance demonstration for each boiler or process heater, you must submit the Notification of Compliance Status, including all performance test results and fuel analyses, before the close of business on the 60th day following the completion of all performance test and/or other initial compliance demonstrations for all boiler or process heaters at the facility according to § 63.10(d)(2). The Notification of Compliance Status report must contain all the information specified in paragraphs (e)(1) through (8) of this section, as applicable. If you are not required to conduct an initial compliance demonstration as specified in § 63.7530(a), the Notification of Compliance Status must only contain the information specified in paragraphs (e)(1) and (8) of this section and must be submitted within 60 days of the compliance date specified at § 63.7495(b).(1) A description of the affected unit(s) including identification of which subcategories the unit is in, the design heat input capacity of the unit, a description of the add-on controls used on the unit to comply with this subpart, description of the fuel(s) burned, including whether the fuel(s) were a secondary material determined by you or the EPA through a petition process to be a non-waste under § 241.3 of this chapter, whether the fuel(s) were a secondary material processed from discarded non-hazardous secondary materials within the meaning of § 241.3 of this chapter, and justification for the selection of fuel(s) burned during the compliance demonstration.(2) Summary of the results of all performance tests and fuel analyses, and calculations conducted to demonstrate initial compliance including all established operating limits, and including:(i) Identification of whether you are complying with the PM emission limit or the alternative TSM emission limit.(ii) Identification of whether you are complying with the output-based emission limits or the heat input-based (i.e., lb/MMBtu or ppm) emission limits,(iii) Identification of whether you are complying the arithmetic mean of all valid hours of data from the previous 30 operating days or of the previous 720 hours. This identification shall be specified separately for each operating parameter.(3) A summary of the maximum CO emission levels recorded during the performance test to show that you have met any applicable emission standard in Table 1 or 2 or Tables 11 through 15 to this subpart, if you are not using a CO CEMS to demonstrate compliance.(4) Identification of whether you plan to demonstrate compliance with each applicable emission limit through performance testing, a CEMS, or fuel analysis.(5) Identification of whether you plan to demonstrate compliance by emissions averaging and identification of whether you plan to demonstrate compliance by using efficiency credits through energy conservation:(i) If you plan to demonstrate compliance by emission averaging, report the emission level that was being achieved or the control technology employed on January 31, 2013.(ii) [Reserved](7) If you had a deviation from any emission limit, work practice standard, or operating limit, you must also submit a description of the deviation, the duration of the deviation, and the corrective action taken in the Notification of Compliance Status report.(8) In addition to the information required in § 63.9(h)(2), your notification of compliance status must include the following certification(s) of compliance, as applicable, and signed by a responsible official:(i) “This facility completed the required initial tune-up for all of the boilers and process heaters covered by 40 CFR part 63 subpart DDDDD at this site according to the procedures in § 63.7540(a)(10)(i) through (vi).”(ii) “This facility has had an energy assessment performed according to § 63.7530(e).”(iii) Except for units that burn only natural gas, refinery gas, or other gas 1 fuel, or units that qualify for a statutory exemption as provided in section 129(g)(1) of the Clean Air Act, include the following: “No secondary materials that are solid waste were combusted in any affected unit.”
-
(2) For each initial compliance demonstration that does include a performance test, you must submit the notification of compliance status, including the performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to the requirement specified in § 63.10(d)(2).
-
(2) For each initial compliance demonstration that includes a performance test, you must submit the notification of compliance status, including the summary of performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to § 63.10(d)(2).
-
(1) For each initial compliance demonstration that includes a performance test or design evaluation, you must submit the Notification of Compliance Status, including the performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to § 63.10(d)(2). You must submit the complete design evaluation and supporting documentation.
-
(2) For each initial compliance demonstration that does include a performance test, you must submit the Notification of Compliance Status, including the performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to § 63.10(d)(2). The Notification of Compliance Status must contain the information in § 63.9(h)(2)(ii)(A) through (G). The site-specific monitoring plan required in § 63.8242(a)(3) must also be submitted.
-
(4) Performance test reports specified in § 63.10(d)(2) of this part.
-
(e) If you are required to conduct a performance test, design evaluation, opacity observation, visible emission observation, or other compliance demonstration as specified in Table 3 or 4 to this subpart, you must submit a Notification of Compliance Status according to § 63.9(h)(2)(ii). You must submit the Notification of Compliance Status, including the performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to § 63.10(d)(2). On and after September 9, 2020, you must submit all subsequent Notification of Compliance Status reports to EPA via the Compliance and Emissions Data Reporting Interface (CEDRI), which can be accessed through EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). If you claim some of the information required to be submitted via CEDRI is confidential business information (CBI), then submit a complete report, including information claimed to be CBI, to EPA. Submit the file on a compact disc, flash drive, or other commonly used electronic storage medium and clearly mark the medium as CBI. Mail the electronic medium to U.S. EPA/OAQPS/CORE CBI Office, Attention: Group Leader, Measurement Policy Group, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same file with the CBI omitted must be submitted to EPA via EPA's CDX as described earlier in this paragraph (e). You may assert a claim of EPA system outage or force majeure for failure to timely comply with the reporting requirement in this paragraph (e) provided you meet the requirements outlined in § 63.8693(h) or (i), as applicable.
-
(f) If you own or operate a flame lamination affected source, submit a Notification of Compliance Status according to § 63.9(h)(2)(ii) that includes the results of the performance test conducted according to the requirements in Table 3 to this subpart. You must submit the notification before the close of business on the 60th calendar day following the completion of the performance test according to § 63.10(d)(2).
-
(2) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, for each initial compliance demonstration that does include a performance test, you must submit the notification of compliance status, including the performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to § 63.10(d)(2). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, for each initial compliance demonstration that does include a performance test, you must submit the notification of compliance status, including the performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to § 63.10(d)(2). If the performance test results have been submitted electronically in accordance with § 63.9641(f), the process unit(s) tested, the pollutant(s) tested, and the date that such performance test was conducted may be submitted in the notification of compliance status report in lieu of the performance test results. The performance test results must be submitted to the Compliance and Emissions Data Reporting Interface (CEDRI) by the date the notification of compliance status report is submitted.
-
(2) For each initial compliance demonstration that does include a performance test, you must submit the notification of compliance status, including the performance test results, before the close of business on the 60th calendar day following the completion of the performance test according to § 63.10(d)(2).
Citations to §63.10(d)(3)
-
(2) As required by § 63.10(d)(3), the owner or operator of an affected source shall report the opacity results from tests required by § 63.1349.
-
(d) For each deviation from an emission limitation (emission limit, operating limit, opacity limit, and VE limit) that occurs at an affected source where you are not using a CMS to comply with the emission limitations in this subpart, the compliance report must contain the information specified in paragraphs (c)(1) through (4) and (d)(1) and (2) of this section. The deviations must be reported in accordance with the requirements in § 63.10(d) prior to the relevant compliance date for your source as specified in § 63.7083(g) and the requirements in § 63.10(d)(1) through (4) beginning on the relevant compliance date for your source as specified in § 63.7083(g).(2) Information on the number, duration, and cause of deviations (including unknown cause, if applicable), and the corrective action taken.(3) An estimate of the quantity of each regulated pollutant emitted over a non-opacity or VE emission limit, and a description of the method used to estimate the emissions.
Citations to §63.10(d)(4)
-
(j) You must comply with the following requirements of the general provisions in subpart A of this part: §§ 63.1 through 63.5; § 63.6(a), (b), and (c); § 63.9; § 63.10(a), (b)(1), (b)(2)(xiv), (b)(3), (d)(1) and (4), and (f); and §§ 63.13 through 63.16. Requirements of the general provisions not cited in the preceding sentence do not apply to the owner or operator of a new or existing affected source that is classified as a small foundry.
-
(2) Beginning August 3, 2026, submit the compliance progress report required under § 63.10(d)(4) and the periodic startup, shutdown, and malfunction reports required under § 63.10(d)(5)(i) as a portable document format (PDF) uploads according to § 63.1211(g).
-
(3) As required by § 63.10(d)(4), the owner or operator of an affected source who is required to submit progress reports as a condition of receiving an extension of compliance under § 63.6(i) shall submit such reports by the dates specified in the written extension of compliance.
-
(d) For each deviation from an emission limitation (emission limit, operating limit, opacity limit, and VE limit) that occurs at an affected source where you are not using a CMS to comply with the emission limitations in this subpart, the compliance report must contain the information specified in paragraphs (c)(1) through (4) and (d)(1) and (2) of this section. The deviations must be reported in accordance with the requirements in § 63.10(d) prior to the relevant compliance date for your source as specified in § 63.7083(g) and the requirements in § 63.10(d)(1) through (4) beginning on the relevant compliance date for your source as specified in § 63.7083(g).(2) Information on the number, duration, and cause of deviations (including unknown cause, if applicable), and the corrective action taken.(3) An estimate of the quantity of each regulated pollutant emitted over a non-opacity or VE emission limit, and a description of the method used to estimate the emissions.
Citations to §63.10(d)(5)
-
(1) Reports of start-up, shutdown, and malfunction required by § 63.10(d)(5). The start-up, shutdown and malfunction reports may be submitted on the same schedule as the Periodic Reports required under paragraph (c) of this section instead of the schedule specified in § 63.10(d)(5). For each source as defined in § 63.101, on and after July 15, 2027, this paragraph no longer applies.
-
(d) Before August 28, 2019, for existing drying and curing ovens and drying and curing ovens constructed or reconstructed after May 26, 2000 and before April 7, 2018, if you have a startup, shutdown, or malfunction during the semiannual reporting period, you must submit the reports specified § 63.10(d)(5). No startup, shutdown, or malfunction plan is required for any affected source that commences construction or reconstruction after April 6, 2018.
-
(k) For affected sources that commenced construction or reconstruction before September 19, 2019, you must submit SSM reports as specified in § 63.10(d)(5), except that the provisions in subpart A of this part pertaining to startups, shutdowns, and malfunctions do not apply unless a control device is used to comply with this subpart. On and after, July 9, 2021, and for affected sources that commence construction or reconstruction after September 19, 2019, this section is no longer relevant.(1) If actions taken by an owner or operator during a startup, shutdown, or malfunction of an affected source (including actions taken to correct a malfunction) are not consistent with the procedures specified in the affected source's SSMP required by § 63.6(e)(3), the owner or operator must state such information in the report. The startup, shutdown, or malfunction report must consist of a letter containing the name, title, and signature of the responsible official who is certifying its accuracy and must be submitted to the Administrator.(2) Separate startup, shutdown, and malfunction reports are not required if the information is included in the report specified in paragraph (c)(2)(vi) of this section.
-
(1) If your actions were consistent with your startup, shutdown, and malfunction plan (SSMP), you must include the information specified in § 63.10(d)(5) in the semiannual compliance report required by paragraph (a) of this section.
-
(1) If your actions were consistent with your SSMP, you must include the information specified in § 63.10(d)(5) in the semiannual compliance report required by paragraph (a) of this section.
-
(f) Before August 24, 2020, you must submit start-up, shutdown, and malfunction reports as specified in § 63.10(d)(5) if you use a control device to comply with this subpart.(1) Before August 24, 2020, if your actions during a start-up, shutdown, or malfunction of an affected source (including actions taken to correct a malfunction) are not completely consistent with the procedures specified in the source's start-up, shutdown, and malfunction plan specified in § 63.6 (e)(3) and required before August 24, 2020, you must state such information in the report. The start-up, shutdown, or malfunction report will consist of a letter containing the name, title, and signature of the responsible official who is certifying its accuracy, that will be submitted to the Administrator. Separate start-up, shutdown, or malfunction reports are not required if the information is included in the report specified in paragraph (g) of this section. The start-up, shutdown, and malfunction plan and start-up, shutdown, and malfunction report are no longer required on and after August 24, 2020.(2) [Reserved]
-
(iii) When actions taken by the owner or operator during a startup or shutdown (and the startup or shutdown causes the source to exceed any applicable emission limitation in the relevant emission standards), or malfunction (including actions taken to correct a malfunction) are consistent with the procedures specified in the affected source's startup, shutdown, and malfunction plan, the owner or operator must keep records for that event which demonstrate that the procedures specified in the plan were followed. These records may take the form of a “checklist,” or other effective form of recordkeeping that confirms conformance with the startup, shutdown, and malfunction plan and describes the actions taken for that event. In addition, the owner or operator must keep records of these events as specified in paragraph 63.10(b), including records of the occurrence and duration of each startup or shutdown (if the startup or shutdown causes the source to exceed any applicable emission limitation in the relevant emission standards), or malfunction of operation and each malfunction of the air pollution control and monitoring equipment. Furthermore, the owner or operator shall confirm that actions taken during the relevant reporting period during periods of startup, shutdown, and malfunction were consistent with the affected source's startup, shutdown and malfunction plan in the semiannual (or more frequent) startup, shutdown, and malfunction report required in § 63.10(d)(5).
-
(5) If you had a startup, shutdown, or malfunction during the reporting period and you took actions consistent with your SSMP, your periodic compliance report must include the information in § 63.10(d)(5) for each startup, shutdown, and malfunction.
Citations to §63.10(d)(5)(i)
-
(2) Beginning August 3, 2026, submit the compliance progress report required under § 63.10(d)(4) and the periodic startup, shutdown, and malfunction reports required under § 63.10(d)(5)(i) as a portable document format (PDF) uploads according to § 63.1211(g).
-
(4) Before November 12, 2024, if you had a startup, shutdown or malfunction during the reporting period and you took actions consistent with your startup, shutdown, and malfunction plan, the compliance report must include the information in § 63.10(d)(5)(i). On or after November 12, 2024, you are not required to have a startup, shutdown, and malfunction plan and you are not required to include in your report the information in § 63.10(d)(5)(i).
-
(5) Except as specified in paragraph (c)(11) of this section, if you had a SSM during the reporting period and you took actions consistent with your SSM plan, the Compliance report must include the information described in § 63.10(d)(5)(i).
-
(ii) For the purposes of this subpart, the semiannual start-up, shutdown, and malfunction reports shall be submitted on the same schedule as the Periodic Reports required under paragraph (e)(6) of this section instead of the schedule specified in § 63.10(d)(5)(i). The reports shall include the information specified in § 63.10(d)(5)(i). On and after July 15, 2027, this paragraph no longer applies.
-
(4) Before December 30, 2020, for each existing source (and for each new or reconstructed source for which construction or reconstruction commenced on or before September 9, 2019), if you had a startup, shutdown, or malfunction during the reporting period and you took actions consistent with your SSM plan, the compliance report must include the information in § 63.10(d)(5)(i). After December 29, 2020, you are no longer required to report the information in § 63.10(d)(5)(i). No SSM plan is required for any new or reconstruction source for which construction or reconstruction commenced after September 9, 2019.
-
(4) Before January 21, 2021, if you had a startup, shutdown and malfunction during the reporting period and you took actions consistent with your startup, shutdown, and malfunction plan, the compliance report must include the information in § 63.10(d)(5)(i). After January 20, 2021, a startup, shutdown, and malfunction plan is not required.
-
(4) Prior to the relevant compliance date for your source as specified in § 63.7083(g), if you had a startup, shutdown or malfunction during the reporting period and you took actions consistent with your SSMP, the compliance report must include the information in § 63.10(d)(5)(i).
-
(4) For existing sources and for new or reconstructed sources for which construction or reconstruction commenced on or before August 16, 2019, before January 11, 2021, if you had a startup, shutdown, or malfunction during the reporting period and you took actions consistent with your startup, shutdown, and malfunction plan, the compliance report must include the information in § 63.10(d)(5)(i). A startup, shutdown, and malfunction plan and the information in § 63.10(d)(5)(i) is not required after January 11, 2021.
-
(4) If your initial startup date was on or before September 3, 2019, then until January 6, 2021, if you had a startup, shutdown, or malfunction during the reporting period and you took actions consistent with your SSMP, the compliance report must include the information in § 63.10(d)(5)(i). If your initial startup date is after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, an SSMP and the information in § 63.10(d)(5)(i) is not required.
-
(4) Before September 9, 2020, if you had a startup, shutdown, or malfunction during the reporting period and you took actions consistent with your SSMP, the compliance report must include the information in § 63.10(d)(5)(i). On and after September 9, 2020, this paragraph (c)(4) no longer applies.
-
(4) For existing sources and for new or reconstructed sources for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, before October 13, 2020, if you had a startup, shutdown, or malfunction during the reporting period and you took actions consistent with your startup, shutdown, and malfunction plan, the compliance report must include the information in § 63.10(d)(5)(i). A startup, shutdown, and malfunction plan and the information in § 63.10(d)(5)(i) is not required after October 13, 2020.
-
(6) For affected sources prior to December 1, 2020, if you had an SSM of a control device or associated monitoring equipment during the reporting period and you took actions consistent with your SSMP, the compliance report must include the information in paragraphs § 63.10(d)(5)(i).
-
(4) For existing sources and for new or reconstructed sources for which construction or reconstruction commenced after October 18, 2002, but before May 4, 2018, before August 7, 2019, if you had a startup, shutdown, or malfunction during the reporting period and you took actions consistent with your startup, shutdown, and malfunction plan, the compliance report must include the information in § 63.10(d)(5)(i). A startup, shutdown, and malfunction plan is not required for such sources on and after August 7, 2019.
-
(4) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, if you had a startup, shutdown, or malfunction during the reporting period and you took actions consistent with your startup, shutdown, and malfunction plan, the compliance report must include the information in § 63.10(d)(5)(i). A startup, shutdown, and malfunction plan and the information in § 63.10(d)(5)(i) is not required after January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and is not required after July 28, 2020, for affected sources that commenced construction or reconstruction after September 25, 2019.
-
(4) Before May 19, 2022, if you had a startup, shutdown, or malfunction during the reporting period, and you took actions consistent with your SSMP and OM&M plan, the compliance report must include the information specified in § 63.10(d)(5)(i). On or after May 19, 2022, if you had a deviation from any emission limitations (emission limit, operating limit, or work practice standard) during the reporting period that apply to you, and you took actions consistent with your OM&M plan, the compliance report must include the information specified in (d) and (e) of this section.
-
(4) If you had a startup, shutdown, or malfunction during the reporting period and you took actions consistent with your startup, shutdown, and malfunction plan, the compliance report must include the information in § 63.10(d)(5)(i).
Citations to §63.10(d)(5)(ii)
-
(2) Before November 12, 2024, you must submit an immediate startup, shutdown, and malfunction report if you had a startup, shutdown, or malfunction during the reporting period that is not consistent with your startup, shutdown, and malfunction plan. You must report the actions taken for the event by fax or telephone within 2 working days after starting actions inconsistent with the plan. You must submit the information in § 63.10(d)(5)(ii) by letter within 7 working days after the end of the event unless you have made alternative arrangements with the delegated authority. On or after November 12, 2024, you must report any deviation from an applicable standard in §§ 63.1444, 63.1445, and 63.1446 as part of your semiannual compliance report and include the information required in paragraph (c) of this section. In an event of an emergency situation, you must report the emergency and the actions taken for the event by email or telephone within 2 working days of the time when emissions limitations were exceeded due to the emergency (or an alternate timeframe acceptable to the delegated authority). For the purposes of complying with this paragraph (a)(2), an emergency situation is any situation arising from sudden and reasonably unforeseeable events beyond the control of the facility owner or operator that requires immediate corrective action to restore normal operation, and that causes the affected source to exceed an applicable emissions limitation under this subpart, due to unavoidable increases in emissions attributable to the emergency. An emergency must not include noncompliance to the extent it is caused by improperly designed equipment, lack of preventive maintenance, careless or improper operation, or operator error. You must submit the report within 7 working days after the end of the event unless you have made alternative arrangements with the delegated authority. This report must contain a description of the emergency, any steps take to mitigate the emissions and corrective actions taken.
-
(ii) You must submit a letter to the Administrator within 7 working days after the end of the event, unless you have made alternative arrangements with the Administrator as specified in § 63.10(d)(5)(ii). The letter must contain the information specified in § 63.10(d)(5)(ii).
-
(ii) You must submit a letter to the Administrator within 7 working days after the end of the event, unless you have made alternative arrangements with the Administrator as specified in § 63.10(d)(5)(ii). The letter must contain the information specified in § 63.10(d)(5)(ii).
-
(ii) You must submit a letter to the Administrator within 7 working days after the end of the event, unless you have made alternative arrangements with the Administrator as specified in § 63.10(d)(5)(ii). The letter must contain the information specified in § 63.10(d)(5)(ii).
-
(ii) You must submit a letter to the Administrator within 7 working days after the end of the event, unless you have made alternative arrangements with the Administrator as specified in § 63.10(d)(5)(ii). The letter must contain the information specified in § 63.10(d)(5)(ii).
-
(ii) You must submit a letter to the Administrator within 7 working days after the end of the event, unless you have made alternative arrangements with the Administrator as specified in § 63.10(d)(5)(ii). The letter must contain the information specified in § 63.10(d)(5)(ii).
-
(ii) You must submit a letter to the Administrator within 7 working days after the end of the event, unless you have made alternative arrangements with the Administrator as specified in § 63.10(d)(5)(ii). The letter must contain the information specified in § 63.10(d)(5)(ii).
-
(ii) You must submit a letter to the Administrator within 7 working days after the end of the event, unless you have made alternative arrangements with the Administrator as specified in § 63.10(d)(5)(ii). The letter must contain the information specified in § 63.10(d)(5)(ii).
-
(ii) You must submit a letter to the Administrator within 7 working days after the end of the event, unless you have made alternative arrangements with the Administrator as specified in § 63.10(d)(5)(ii). The letter must contain the information specified in § 63.10(d)(5)(ii).
-
(2) You must submit an Immediate Startup, Shutdown, and Malfunction Report if you had a startup, shutdown, or malfunction during the reporting period that is not consistent with your SSMP. Your report must contain actions taken during the event. You must submit this report by fax or telephone within 2 working days after starting actions inconsistent with you SSMP. You are required to follow up this report with a report specifying the information in § 63.10(d)(5)(ii) by letter within 7 working days after the end of the event unless you have made alternative arrangements with your permitting authority.
-
(c) If your initial startup was on or before September 3, 2019, then until January 6, 2021, if you had a startup, shutdown, or malfunction during the semiannual reporting period that was not consistent with your SSMP, you must submit an immediate startup, shutdown and malfunction report according to the requirements of § 63.10(d)(5)(ii). If your initial startup date is after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, an immediate startup, shutdown, and malfunction report is not required.
-
(2) A follow-up report containing the information listed in § 63.10(d)(5)(ii) must be submitted within 7 working days after the end of the event unless you have made alternative reporting arrangements with the permitting authority.
-
(e) Prior to December 1, 2020, if you had an SSM of a control device or associated monitoring equipment during the semiannual reporting period that was not consistent with your SSMP, you must submit an immediate SSM report according to the requirements in § 63.10(d)(5)(ii).
-
(d) For existing sources and for new or reconstructed sources which commenced construction or reconstruction after October 18, 2002, but before May 4, 2018, before August 7, 2019, if you had a startup, shutdown, or malfunction during the semiannual reporting period that was not consistent with your startup, shutdown, and malfunction plan, you must submit an immediate startup, shutdown, and malfunction report according to the requirements in § 63.10(d)(5)(ii). An immediate startup, shutdown, and malfunction report is not required for such sources on and after August 7, 2019.
-
(c) Beginning on January 25, 2021, submit all subsequent compliance reports to the EPA via CEDRI, which can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as confidential business information (CBI). Anything submitted using CEDRI cannot later be claimed to be CBI. You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/compliance-and-emissions-data-reporting-interface-cedri) for this subpart. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Although we do not expect persons to assert a claim of CBI, if persons wish to assert a CBI claim, submit a complete report, including information claimed to be CBI, to the EPA. The report must be generated using the appropriate form on the CEDRI website. Clearly mark the part or all of the information that you claim to be CBI. Information not marked as CBI may be authorized for public release without prior notice. Information marked as CBI will not be disclosed except in accordance with procedures set forth in 40 CFR part 2. Submit the file following the procedures in paragraph (c)(1) or (2) of this section. The same file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph (c). All CBI claims must be asserted at the time of submission. Furthermore, under CAA section 114(c) emissions data is not entitled to confidential treatment, and EPA is required to make emissions data available to the public. Thus, emissions data will not be protected as CBI and will be made publicly available. On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, if you had a startup, shutdown, or malfunction during the reporting period that is not consistent with your startup, shutdown, and malfunction plan you must submit an immediate startup, shutdown and malfunction report according to the requirements in § 63.10(d)(5)(ii). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, an immediate startup, shutdown, and malfunction report is not required.(1) The preferred method to receive CBI is for it to be transmitted electronically using email attachments, File Transfer Protocol, or other online file sharing services. Electronic submissions must be transmitted directly to the OAQPS CBI Office at the email address [email protected], and as described above, should include clear CBI markings and be flagged to the attention of the Taconite Iron Ore Processing Sector Lead. If assistance is needed with submitting large electronic files that exceed the file size limit for email attachments, and if you do not have your own file sharing service, please email [email protected] to request a file transfer link.(2) If you cannot transmit the file electronically, you may send CBI information through the postal service to the following address: U.S. EPA, Attn: OAQPS Document Control Officer and Taconite Iron Ore Processing Sector Lead, Mail Drop: C404-02, 109 T.W. Alexander Drive, P.O. Box 12055, RTP, NC 27711. The mailed CBI material should be double wrapped and clearly marked. Any CBI markings should not show through the outer envelope.
-
(c) If you had a startup, shutdown, or malfunction during the semiannual reporting period that was not consistent with your startup, shutdown, and malfunction plan, you must submit an immediate startup, shutdown, and malfunction report according to the requirements in § 63.10(d)(5)(ii).
Citations to §63.10(d)(f)
-
(j) You must comply with the following requirements of the general provisions in subpart A of this part: §§ 63.1 through 63.5; § 63.6(a), (b), and (c); § 63.9; § 63.10(a), (b)(1), (b)(2)(xiv), (b)(3), (d)(1) and (4), and (f); and §§ 63.13 through 63.16. Requirements of the general provisions not cited in the preceding sentence do not apply to the owner or operator of a new or existing affected source that is classified as a small foundry.
Citations to §63.10(e)
-
(4) Approval of major change to recordkeeping and reporting under § 63.10(e) and as defined in § 63.90.
-
(3) You must submit semiannual compliance reports to the Administrator for the control of contaminants from scrap according to the requirements in § 63.10(e). The report must clearly identify any deviation from the requirements in paragraphs (a) and (b) of this section and the corrective action taken. You must identify which compliance option in paragraph (b) of this section applies to each scrap provider, contract, or shipment.
-
(4) If you operate a bag leak detection system for a fabric filter or a CPMS for a wet scrubber, submit annual reports according to the requirements in § 63.10(e) and include summary information on the number, duration, and cause (including unknown cause, if applicable) for monitor downtime incidents (other than downtime associated with zero and span or other calibration checks, if applicable).
-
(a) The owner or operator of an affected source subject to the emissions standards in § 63.362 must fulfill all reporting requirements in § 63.10(a), (d), (e), and (f), according to the applicability in table 6 to this subpart. These reports will be made to the Administrator at the appropriate address identified in § 63.13 or submitted electronically.
-
(d) If your facility has an add-on control device, you must submit semiannual compliance reports and quarterly excess emission reports as specified in § 63.10(e). The contents of the reports are specified in § 63.10(e).
-
(ii) If an application for a waiver of a subsequent performance test is made, the application may accompany any required compliance progress report, compliance status report, or excess emissions and continuous monitoring system performance report such as those required under [§ 63.6(i), § 63.9(h), and § 63.10(e) or specified in a relevant standard or in the source's title V permit], but it shall be submitted at least 60 days before the performance test if the site-specific test plan required under paragraph (c) of this section is not submitted.
-
(i) Excess emissions and continuous monitoring system performance report and summary reports shall be submitted as required by § 63.10(e).(1) The owner or operator of an affected source subject to § 63.704 shall include deviations of monitored values from the operating parameter values required by § 63.704(c) in the reports. In the case of exceedances, the report must also contain a description and timing of the steps taken to address the cause of the exceedance.(2) The owner or operator of an affected source subject to § 63.703(c)(5) shall report the HAP content of each batch of coating applied as the monitored operating parameter value in the reports.(3) The owner or operator of an affected source subject to § 63.703(e)(1)(ii) and maintaining a minimum freeboard ratio of 75 percent shall report violations of the standard (freeboard ratio is less than 75 percent) in the reports.(4) The owner or operator of an affected source subject to § 63.704(c)(10) of this subpart shall include records of any time period and duration of time that flow was diverted from the control device, as well as the results of monthly inspections required by § 63.704(c)(10)(ii), (iii), and (iv) in the reports.(5) The owner or operator of an affected source complying with § 63.703(c) by performing a material balance calculation in accordance with § 63.705(c)(1) shall report any exceedances of the standard, as demonstrated through the calculation, in the reports.
-
(4) Approval of major change to recordkeeping and reporting under § 63.10(e) and as defined in § 63.90.
-
(a) Each owner or operator of an affected source shall comply with the applicable recordkeeping and reporting requirements in § 63.10 (a), (b), (d), and (f). Any owner that receives approval pursuant to § 63.783(c) to use an add-on control system to control coating emissions shall also comply with the applicable requirements of § 63.10 (c) and (e). A summary of recordkeeping and reporting requirements is provided in Table 3 of this subpart.
-
(4) Owners or operators of an affected source subject to the provisions of § 63.802 (a)(1) or (b)(1) that comply through the procedures established in § 63.804 (a)(3) or (d)(3) shall demonstrate continuous compliance by installing, calibrating, maintaining, and operating the appropriate monitoring equipment according to manufacturer's specifications. The owner or operator shall also submit the excess emissions and continuous monitoring system performance report and summary report required by § 63.807(d) and § 63.10(e) of subpart A.(i) Where a capture/control device is used, a device to monitor each site-specific operating parameter established in accordance with § 63.804(f)(6)(i) is required.(ii) Where an incinerator is used, a temperature monitoring device equipped with a continuous recorder is required.(A) Where a thermal incinerator is used, a temperature monitoring device shall be installed in the firebox or in the ductwork immediately downstream of the firebox in a position before any substantial heat exchange occurs.(B) Where a catalytic incinerator equipped with a fixed catalyst bed is used, temperature monitoring devices shall be installed in the gas stream immediately before and after the catalyst bed.(C) Where a catalytic incinerator equipped with a fluidized catalyst bed is used, a temperature monitoring device shall be installed in the gas stream immediately before the bed. In addition, a pressure monitoring device shall be installed to determine the pressure drop across the catalyst bed. The pressure drop shall be measured monthly at a constant flow rate.(iii) Where a carbon adsorber is used one of the following is required:(A) An integrating stream flow monitoring device having an accuracy of ±10 percent, capable of recording the total regeneration stream mass flow for each regeneration cycle; and a carbon bed temperature monitoring device, having an accuracy of ±1 percent of the temperature being monitored or ±0.5 °C, whichever is greater, and capable of recording the carbon bed temperature after each regeneration and within 15 minutes of completing any cooling cycle;(B) An organic monitoring device, equipped with a continuous recorder, to indicate the concentration level of organic compounds exiting the carbon adsorber; or(C) Any other monitoring device that has been approved by the Administrator in accordance with § 63.804(f)(4)(iv)(D).(iv) Owners or operators of an affected source shall not operate the capture or control device at a daily average value greater than or less than (as appropriate) the operating parameter values. The daily average value shall be calculated as the average of all values for a monitored parameter recorded during the operating day.(v) Owners or operators of an affected source that are complying through the use of a catalytic incinerator equipped with a fluidized catalyst bed shall maintain a constant pressure drop, measured monthly, across the catalyst bed.(vi) An owner or operator who uses a control device not listed in § 63.804(f)(4) shall submit, for the Administrator's approval, a description of the device, test data verifying performance, and appropriate site-specific operating parameters that will be monitored to demonstrate continuous compliance with the standard.
-
(d) The owner or operator of an affected source demonstrating compliance in accordance with § 63.804(g)(4), (6), and (h)(2) of this subpart shall submit the excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e) of subpart A. The report shall include the monitored operating parameter values required by § 63.804(g) (4) and (6). If the source experiences excess emissions, the report shall be submitted quarterly for at least 1 year after the excess emissions occur and until a request to reduce reporting frequency is approved, as indicated in § 63.10(e)(3)(C). If no excess emissions occur, the report shall be submitted semiannually.
Citations to §63.10(e)(1)
-
-
-
-
-
(7) Ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i) and the requirements of § 63.11585.
-
-
-
-
-
-
-
-
(3) Before January 21, 2021, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 20, 2021, the owner or operator shall keep these written procedures on record for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, the owner or operator shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan required under § 63.8(d)(2); and
-
-
(3) As required by § 63.10(e)(1), you must submit an excess emissions report for any exceedance of an emission or operating parameter limit if the total duration of the exceedances for the reporting period is 1 percent of the total operating time for the reporting period or greater. The report must contain the information specified in § 63.10 and paragraph (b)(4) of this section. When exceedances of an emission limit or operating parameter have not occurred, you must include such information in the report. You must submit the report semiannually and the report must be delivered or postmarked by the 30th day following the end of the calendar half. If exceedances are reported, you must submit the excess emissions report quarterly until a request to reduce reporting frequency is approved as described in § 63.10(e)(3).
-
-
-
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
-
(3) Ongoing recordkeeping and reporting procedures in accordance with §§ 63.8693 and 63.8694 and the general requirements of § 63.10(e)(1) and (e)(2)(i).
-
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
Citations to §63.10(e)(2)
-
(6) As required by § 63.10(e)(2), the owner or operator shall submit a written report of the results of the performance evaluation for the continuous monitoring system required by § 63.8(e). The owner or operator shall submit the report simultaneously with the results of the performance test.
Citations to §63.10(e)(2)(i)
-
-
-
-
-
(7) Ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i) and the requirements of § 63.11585.
-
-
-
-
-
-
(3) Before January 21, 2021, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 20, 2021, the owner or operator shall keep these written procedures on record for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, the owner or operator shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action should be included in the plan required under § 63.8(d)(2); and
-
-
-
-
-
(6) Ongoing recordkeeping and reporting procedures in accordance the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (2)(i).
-
-
(6) On or before January 11, 2021, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced on or before August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i). After January 11, 2021 for each such source, and after July 13, 2020 for new and reconstructed sources for which construction or reconstruction commenced after August 16, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i);
-
(3) If your initial startup was on or before September 3, 2019, then until January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). If your initial startup was after September 3, 2019, then as of July 10, 2020, and for all sources after January 6, 2021, you must address ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
-
(3) Ongoing recordkeeping and reporting procedures in accordance with §§ 63.8693 and 63.8694 and the general requirements of § 63.10(e)(1) and (e)(2)(i).
-
-
(6) Before October 13, 2020, for each existing source, and for each new or reconstructed source for which construction or reconstruction commenced after April 17, 2003, but before February 5, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c) and (e)(1) and (e)(2)(i). After October 13, 2020 for each such source, and after April 15, 2020 for new and reconstructed sources for which construction or reconstruction commenced after February 4, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14) and (e)(1) and (e)(2)(i).
-
(6) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c), (e)(1), and (e)(2)(i). After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, ongoing recordkeeping and reporting procedures in accordance with the general requirements of § 63.10(c)(1) through (14), (e)(1), and (e)(2)(i).
-
Citations to §63.10(e)(2)(ii)
-
(ii) Affected sources within Texas shall comply with the Federal requirements of 40 CFR part 63—subpart A—General Provisions, adopted by reference by the Texas Commission on Environmental Quality (TCEQ), with the exception of § 63.5(e)(2)(i), § 63.6(i)(12)(i), § 63.6(i)(13)(i) and (ii), § 63.8(e)(5)(ii), § 63.9(i)(3), and § 63.10(e)(2)(ii). The TCEQ has adopted alternative provisions for the cited exceptions above and affected sources in Texas that are subject to the requirements of Subpart A shall comply with the requirements established at Texas Administrative Code, Title 30, Part 1, Chapter 113, Subchapter C, section 113.100.
Citations to §63.10(e)(3)
-
(d) If you own or operate a new affected source, you must report any deviation from the requirements of this subpart in the semiannual report required by 40 CFR 63.10(e)(3).
-
(ii) You must install, maintain, and operate a pressure drop monitoring device to measure the differential pressure drop across the fabric filter during all times when the process is operating. The pressure drop must be recorded at least once per day. If a pressure drop is observed outside of the normal operational ranges as specified by the manufacturer, you must record the incident and take immediate corrective actions. You must also record the corrective actions taken. You must submit a monitoring system performance report in accordance with § 63.10(e)(3).
-
(c) Beginning on February 23, 2024, or once the report template for this subpart has been available on the CEDRI website for one year, whichever date is later, you must submit a report of excess emissions and monitoring systems performance report and summary report according to §§ 63.9(k) and 63.10(e)(3) to the Administrator semiannually. Report the number of failures to meet an applicable standard in this part. For each instance, report the date, time, cause, and duration of each failure. For each failure, the report must include a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, and a description of the method used to estimate the emissions. You must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) or an alternate electronic file consistent with the XML schema listed on the CEDRI website for this subpart. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports, the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Submit all reports to the EPA via CEDRI, which can be accessed through the EPA's CDX (https://cdx.epa.gov/). The EPA will make all the information submitted through CEDRI available to the public without further notice to you. Do not use CEDRI to submit information you claim as CBI. Anything submitted using CEDRI cannot later be claimed CBI. The report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. Although we do not expect persons to assert a claim of CBI, if you wish to assert a CBI claim, follow the requirements specified in paragraph (b)(3) of this section. The same file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph (c).
-
(e) A semiannual report as required by § 63.10(e)(3) of the general provisions in subpart A of this part if measured emissions exceed the applicable standard or a monitored parameter varies from the level established during performance testing. The report must contain the information specified in § 63.10(c) of the general provisions, as well as the relevant records required by § 63.1192(b) of this subpart.
-
(b) When submitting the excess emissions and continuous monitoring system performance report and summary report required in § 63.10(e)(3), you must also include the information specified in paragraphs (b)(1) through (12) of this section, as applicable. This report is referred to in this subpart as your compliance report.(1) You must include a copy of the inspection record specified in § 63.11990(b)(2) for each storage vessel when a defect, failure, or leak is detected. You must also include a copy of the applicable information specified in § 63.1039(b)(5) through (8) of subpart UU of this part for each pressure vessel.(2) You must include the information specified in § 63.1039(b) for equipment leaks, except for releases from pressure relief devices. For any releases from pressure relief devices, you must submit the report specified in paragraph (c)(7) of this section instead of the information specified in § 63.1039(b)(4) of subpart UU of this part.(3) You must include the information specified in paragraphs (b)(3)(i) through (vi) of this section for heat exchange systems.(iii) A summary of the monitoring data that indicate a leak, including the number of leaks determined to be equal to or greater than the leak definition.(iv) If applicable, the date a leak was identified, the date the source of the leak was identified and the date of repair.(v) If applicable, a summary of each delayed repair, including the original date and reason for the delay and the date of repair, if repaired during the reporting period.(vi) If applicable, an estimate of total VOC or vinyl chloride emissions for each delayed repair over the reporting period.(4) You must include the records specified in paragraphs (b)(4)(i) through (iii) of this section, as applicable, for process vents, resin strippers, and wastewater.(i) For each deviation from an emission limit or operating limit where a CEMS or CPMS is being used to comply with the process vent emission limits in Table 1 or 2 to this subpart, you must include the information in paragraphs (b)(4)(i)(A) through (E) of this section.(A) For CEMS, the 3-hour block average value calculated for any period when the value is higher than an emission limit in Table 1 or 2 to this subpart or when the value does not meet the data availability requirements defined in § 63.11890(c).(B) For CPMS, the average value calculated for any day (based on the data averaging periods for compliance specified in Table 5 to this subpart) that does not meet your operating limit established according to § 63.11935(d) or that does not meet the data availability requirements specified in § 63.11890(c).(C) The cause for the calculated emission level or operating parameter level to not meet the established emission limit or operating limit.(D) For deviations caused by lack of monitoring data, the duration of periods when monitoring data were not collected.(E) Operating logs of batch process operations for each day during which the deviation occurred, including a description of the operating scenario(s) during the deviation.(ii) Include each new operating scenario that has been operated since the time period covered by the last compliance report and has not been submitted in the notification of compliance status report or a previous compliance report. For each new operating scenario, you must provide verification that the operating conditions for any associated control or treatment device have not been exceeded and constitute proper operation for the new operating scenario. You must provide any required calculations and engineering analyses that have been performed for the new operating scenario. For the purposes of this paragraph (b)(4)(ii), a revised operating scenario for an existing process is considered to be a new operating scenario when one or more of the data elements listed in § 63.11990(e)(4) have changed.(iii) You must document process changes, or changes made to any of the information submitted in the notification of compliance status report or a previous compliance report, that is not within the scope of an existing operating scenario, in the compliance report. The notification must include all of the information in paragraphs (b)(4)(iii)(A) through (C) of this section.(B) Revisions to any of the information reported in the original notification of compliance status report as provided in paragraph (a) of this section.(C) Information required by the notification of compliance status report, as provided in paragraph (a) of this section, for changes involving the addition of processes, components, or equipment at the affected source.(5) You must submit the applicable information specified in paragraphs (b)(5)(i) through (iii) of this section for process vents.(i) For catalytic thermal oxidizers for which you have selected the alternative monitoring specified in § 63.11940(b)(3), results of the annual catalyst sampling and inspections required by § 63.11940(b)(3)(i) and (ii) including any subsequent corrective actions taken.(ii) For regenerative adsorbers, results of the adsorber bed outlet volatile organic compounds concentration measurements specified in § 63.11940(d)(7).(iii) For non-regenerative adsorbers, results of the adsorber bed outlet volatile organic compounds concentration measurements specified in § 63.11940(e)(2).(6) You must include the records specified in § 63.11990(j) for other emission sources.(7) For resin stripper operations, you must include results of daily vinyl chloride and monthly total non-vinyl chloride organic HAP concentration results for each resin type produced within the PVCPU that did not meet the stripped resin emission limits in Table 1 or 2 to this subpart, as applicable.(8) You must include the information specified in paragraphs (b)(8)(i) and (ii) of this section for your wastewater streams.(i) Results of daily vinyl chloride and monthly total non-vinyl chloride organic HAP concentration results for each process wastewater stream discharged from the affected source that did not meet the process wastewater emission limits in Tables 1 or 2 to this subpart.(ii) If you must comply with § 63.11965, then you must include any other applicable information that is required by the reporting requirements specified in § 63.146.(9) For closed vent systems subject to the requirements of § 63.11930, you must include the information specified in paragraphs (b)(9)(i) through (iv) of this section, as applicable.(i) As applicable, records as specified in § 63.11930(g)(1)(i) for all times when flow was detected in the bypass line, the vent stream was diverted from the control device, or the flow indicator was not operating.(ii) As applicable, records as specified in § 63.11930(g)(1)(ii) for all occurrences of all periods when a bypass of the system was indicated (the seal mechanism is broken, the bypass line valve position has changed, or the key for a lock-and-key type lock has been checked out, and records of any car-seal that has been broken).(iii) Records of all times when monitoring of the system was not performed as specified in § 63.11930(d) and (e), or repairs were not performed as specified in § 63.11930(f), or records were not kept as specified in § 63.11930(g)(2).(iv) Records of each time an alarm on a closed vent system operating in vacuum service is triggered as specified in § 63.11930(h) including the cause for the alarm and the corrective action taken.(10) Closed vent system in vacuum service, bypass deviation, or pressure vessel closure device deviation report. If any pressure vessel closure device or closed vent system that contains a bypass has directly discharged to the atmosphere, or any closed vent system that is designed to be in vacuum service and is operating and but not in vacuum service, as specified in § 63.11910(c)(4), § 63.11930(c) or § 63.11930(h), you must submit to the Administrator the following information:(iii) An estimate of the quantity of vinyl chloride and total HAP emitted during the discharge and the method used for determining this quantity.(v) The measures adopted to prevent future such discharges(11) If you seek to assert an affirmative defense, as provided in § 63.11895, then you must submit a written report as specified in § 63.11895(b) to demonstrate, with all necessary supporting documentation, that you have met the requirements set forth in § 63.11895(a).(12) Information required by this subpart, which is submitted with a Title V periodic report, does not need to be included in a subsequent compliance report required by this subpart or subpart referenced by this subpart. The Title V report must be referenced in the compliance report required by this subpart.
-
(A) (1) During malfunctions, the automatic waste feed cutoff requirements of § 63.1206(c)(3) continue to apply, except for paragraphs (c)(3)(v) and (vi) of this section. If you exceed an emission standard under this subpart monitored by a CEMS or COMs or operating limit specified under § 63.1209, the automatic waste feed cutoff system must immediately and automatically cutoff the hazardous waste feed, except as provided by paragraph (c)(3)(viii) of this section. If the malfunction itself prevents immediate and automatic cutoff of the hazardous waste feed, however, you must cease feeding hazardous waste as quickly as possible.(2) Although the automatic waste feed cutoff requirements continue to apply during a malfunction, an exceedance of an emission standard monitored by a CEMS or COMS or operating limit specified under § 63.1209 after a malfunction has occurred is not a violation of this subpart if:(i) You took the actions to minimize the frequency and severity of the malfunction prescribed in the startup, shutdown, and malfunction plan prior to the malfunction; and(ii) You take the corrective measures prescribed in the startup, shutdown, and malfunction plan in response to the malfunction.(3) Excessive exceedances during malfunctions. For each set of 10 exceedances of an emission standard or operating requirement while hazardous waste remains in the combustion chamber (i.e., when the hazardous waste residence time has not transpired since the hazardous waste feed was cutoff) during a 60-day block period, you must:(i) Within 45 days of the 10th exceedance, complete an investigation of the cause of each exceedance and evaluation of approaches to minimize the frequency, duration, and severity of each exceedance, and revise the startup, shutdown, and malfunction plan as warranted by the evaluation to minimize the frequency, duration, and severity of each exceedance; and(ii) Record the results of the investigation and evaluation in the operating record, and include a summary of the investigation and evaluation, and any changes to the startup, shutdown, and malfunction plan, in the excess emissions report required under § 63.10(e)(3).
-
(3) Beginning June 3, 2027, or once the report template for this subpart has been available on the CEDRI website for one year, whichever date is later, submit the excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e)(3), including the information required by paragraph (a)(1) of this section, according to § 63.1211(g). When the report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirements in § 63.10(e)(3)(v), (e)(3)(vi)(L), and (e)(3)(vi)(M) of subpart A of this part to submit the date of the report and the name, title, and signature of the responsible official who is certifying the accuracy of the report.
-
(i) The information required under § 63.10(e)(3). For the purposes of this subpart and the information required under § 63.10(e)(3), excursions (as defined in § 63.1283(d)(6)) shall be considered excess emissions.
-
(8) As required by § 63.10(e)(3), the owner or operator of an affected source equipped with a continuous emission monitor shall submit an excess emissions and continuous monitoring system performance report for any event when the continuous monitoring system data indicate the source is not in compliance with the applicable emission limitation or operating parameter limit.
-
(ii) Quarterly reports shall be submitted when the monitoring data are used to comply with the alternative standards in § 63.1362(b)(6) or (c)(4) and the source experiences excess emissions. Once an affected source reports excess emissions, the affected source shall follow a quarterly reporting format until a request to reduce reporting frequency is approved. If an owner or operator submits a request to reduce the frequency of reporting, the provisions in § 63.10(e)(3) (ii) and (iii) of subpart A of this part shall apply, except that the term “excess emissions and continuous monitoring system performance report and/or summary report” shall mean “Periodic report” for the purposes of this section.
-
(b) The owner or operator of a major or area source must submit semiannual reports according to the requirements in § 63.10(e)(3). Except, the owner or operator must submit the semiannual reports within 60 days after the end of each 6-month period instead of within 30 days after the calendar half as specified in § 63.10(e)(3)(v). When no deviations of parameters have occurred, the owner or operator must submit a report stating that no excess emissions occurred during the reporting period.(1) A report must be submitted if any of these conditions occur during a 6-month reporting period:(i) The corrective action specified in the OM&M plan for a bag leak detection system alarm was not initiated within 1 hour.(ii) The corrective action specified in the OM&M plan for a continuous opacity monitoring deviation was not initiated within 1 hour.(iii) The corrective action specified in the OM&M plan for visible emissions from an aluminum scrap shredder was not initiated within 1 hour.(iv) An excursion of a compliant process or operating parameter value or range (e.g., lime injection rate or screw feeder setting, total reactive chlorine flux injection rate, afterburner operating temperature, fabric filter inlet temperature, definition of acceptable scrap, or other approved operating parameter).(v) [Reserved](vi) An affected source (including an emission unit in a secondary aluminum processing unit) was not operated according to the requirements of this subpart.(vii) A deviation from the 3-day, 24-hour rolling average emission limit for a secondary aluminum processing unit.(2) Each report must include each of these certifications, as applicable:(i) “Only unpainted aluminum chips were used as feedstock in any thermal chip dryer during this reporting period.”(ii) “Only dross and salt flux were used as the charge materials in any dross-only furnace during this reporting period.”(iii) “Each furnace was operated such that the level of molten metal remained above the top of the passage between the sidewell and hearth during reactive fluxing, and reactive flux, except for cover flux, was added only to the sidewell or to a furnace hearth equipped with an add-on air pollution control device for PM, HCl, and D/F emissions during this reporting period.”(iv) For each group 1 melting/holding furnace without add-on air pollution control devices and using pollution prevention measures that processes only clean charge material: “Each group 1 furnace without add-on air pollution control devices subject to emission limits in § 63.1505(i)(2) processed only clean charge during this reporting period.”(v) “Only clean charge materials were processed in any group 2 furnace during this reporting period, and no fluxing was performed or all fluxing performed was conducted using only nonreactive, non-HAP-containing/non-HAP-generating fluxing gases or agents, except for cover fluxes, during this reporting period.”(vi) “Only nonreactive, non-HAP-containing, non-HAP-generating flux gases, agents, or materials were used at any time during this reporting period.”(vii) For each affected source choosing to demonstrate compliance during periods of startup and shutdown in accordance with § 63.1513(f)(1): “During each startup and shutdown, no flux and no feed/charge were added to the emission unit, and electricity, propane or natural gas were used as the sole source of heat or the emission unit was not heated.”(3) The owner or operator must submit the results of any performance test conducted during the reporting period, including one complete report documenting test methods and procedures, process operation, and monitoring parameter ranges or values for each test method used for a particular type of emission point tested.(i) Within 60 days after the date of completing each performance test (as defined in § 63.2) required by this subpart, you must submit the results of the performance tests, including any associated fuel analyses, following the procedure specified in either paragraph (b)(3)(i)(A) or (B) of this section.(A) For data collected using test methods supported by the EPA's Electronic Reporting Tool (ERT) as listed on the EPA's ERT Web site (https://www3.epa.gov/ttn/chiefert/ert_info.html), you must submit the results of the performance test to the EPA via the Compliance and Emissions Data Reporting Interface (CEDRI). (CEDRI can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/).) Performance test data must be submitted in a file format generated through the use of the EPA's ERT or an alternate electronic file format consistent with the extensible markup language (XML) schema listed on the EPA's ERT Web site. If you claim that some of the performance test information being submitted is confidential business information (CBI), you must submit a complete file generated through the use of the EPA's ERT or an alternate electronic file consistent with the XML schema listed on the EPA's ERT Web site, including information claimed to be CBI, on a compact disc, flash drive, or other commonly used electronic storage media to the EPA. The electronic media must be clearly marked as CBI and mailed to U.S. EPA/OAQPS/CORE CBI Office, Attention: Group Leader, Measurement Policy Group, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same ERT or alternate file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph.(B) For data collected using test methods that are not supported by the EPA's ERT as listed on the EPA's ERT Web site, you must submit the results of the performance test to the Administrator at the appropriate address listed in § 63.13.(ii) [Reserved](4) A malfunction report that is required under paragraph (d) of this section shall be submitted simultaneously with the semiannual excess emissions/summary report required by paragraph (b) of this section.
-
(1) You must submit reports no less frequently than specified under § 63.10(e)(3) of the General Provisions.
-
(i) The owner or operator must submit reports pursuant to § 63.10(e)(3) that are associated with excess emissions events such as the excursion of the scrubber pressure drop limit per paragraph (b)(2) of this section. These reports are to be submitted on a quarterly basis, unless the owner or operator can satisfy the requirements in § 63.10(e)(3) to reduce the frequency to a semiannual basis.
-
(1) Unless the Administrator has agreed to a different schedule for submitting reports under § 63.10(a), you must deliver or postmark each semiannual compliance report no later than 30 days following the end of each semiannual reporting period. The first semiannual reporting period begins on the compliance date for your affected source and ends on June 30 or December 31, whichever date immediately follows your compliance date. Each subsequent semiannual reporting period for which you must submit a semiannual compliance report begins on July 1 or January 1 and ends 6 calendar months later. Before March 1, 2019, as required by § 63.10(e)(3), you must begin submitting quarterly compliance reports if you deviate from the emission limits in § 63.2983 or the operating limits in § 63.2984. After February 28, 2019, you are not required to submit quarterly compliance reports. If you deviate from the emission limits in § 63.2983 or the operating limits in § 63.2984 in the quarter prior to February 28, 2019, you must include this information in the report for the first full semiannual reporting period following February 28, 2019.
-
(3) Each owner or operator of a bulk gasoline terminal or pipeline breakout station subject to the provisions of this subpart shall submit an excess emissions report to the Administrator in accordance with § 63.10(e)(3), whether or not a CMS is installed at the facility. The following occurrences are excess emissions events under this subpart, and the following information shall be included in the excess emissions report, as applicable:(i) Each exceedance or failure to maintain, as appropriate, the monitored operating parameter value determined under § 63.425(b)(3). The report shall include the monitoring data for the days on which exceedances or failures to maintain have occurred, and a description and timing of the steps taken to repair or perform maintenance on the vapor collection and processing systems or the CMS.(ii) Each instance of a nonvapor-tight gasoline cargo tank loading at the facility in which the owner or operator failed to take steps to assure that such cargo tank would not be reloaded at the facility before vapor tightness documentation for that cargo tank was obtained.(iii) Each reloading of a nonvapor-tight gasoline cargo tank at the facility before vapor tightness documentation for that cargo tank is obtained by the facility in accordance with § 63.422(c).(iv) For each occurrence of an equipment leak for which no repair attempt was made within 5 days or for which repair was not completed within 15 days after detection:(A) The date on which the leak was detected;(B) The date of each attempt to repair the leak;(C) The reasons for the delay of repair; and
-
(c) The owner or operator of each bleaching system complying with § 63.440(d)(3)(ii)(B) shall certify in the report specified under § 63.10(e)(3) of subpart A of this part that the daily application rates of chlorine and hypochlorite for that bleaching system have not increased as specified in § 63.440(d)(3)(ii)(B) until the requirements of § 63.440(d)(3)(ii)(A) are met.
-
(a) The owner or operator of any affected BLR source, as well as the owner or operator of any affected WSR source that is subject to the emission limit for process vents, storage tanks, and wastewater systems and/or is subject to the dioxins and furans emission limit for process vents, shall comply with the reporting requirements of applicable paragraphs of § 63.10, as specified in the General Provisions applicability table in this subpart. The owner or operator shall also submit to the Administrator, as part of the quarterly excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e)(3), the following recorded information. On and after July 15, 2027 or once the reporting template for this subpart has been available on the CEDRI website for 1 year, whichever date is later, owners and operators must submit all subsequent reports following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Polymers and Resins Sector Lead. Owners and operators must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports under § 63.9(i) and § 63.10(a), the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. If a report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirements in § 63.10(e)(3)(v), § 63.10(e)(3)(vi)(L), and § 63.10(e)(3)(vi)(M) to submit the date of the report and the name, title, and signature of the responsible official who is certifying the accuracy of the report.(1) Reports of monitoring data, including 15-minute monitoring values as well as daily average values or per-unit operation average values, as applicable, of monitored parameters for all operating days or unit operations when the average values were outside the ranges established in the Notification of Compliance Status or operating permit, including reports specified in paragraph (a)(4) of this section.(2) Reports of the duration of periods when monitoring data is not collected for each excursion caused by insufficient monitoring data, including reports specified in paragraph (a)(4) of this section. An excursion means any of the three cases listed in paragraph (a)(2)(i) or (a)(2)(ii) of this section. For a control device where multiple parameters are monitored, if one or more of the parameters meets the excursion criteria in paragraph (a)(2)(i) or (a)(2)(ii) of this section, this is considered a single excursion for the control device. In the report, include the identification of the source, start date, start time, duration in hours, and monitored parameter(s) meeting the excursion criteria.(i) When the period of control device operation is 4 hours or greater in an operating day and monitoring data are insufficient to constitute a valid hour of data, as defined in paragraph (a)(2)(iii) of this section, for at least 75 percent of the operating hours.(ii) When the period of control device operation is less than 4 hours in an operating day and more than one of the hours during the period of operation does not constitute a valid hour of data due to insufficient monitoring data.(iii) Monitoring data are insufficient to constitute a valid hour of data, as used in paragraphs (a)(2)(i) and (ii) of this section, if measured values are unavailable for any of the 15-minute periods within the hour.(3) Whenever a process change, as defined in § 63.115(e), is made that causes the emission rate from a de minimis emission point to become a process vent with an emission rate of one pound per year or greater, the owner or operator shall submit a report within 180 calendar days after the process change. The report may be submitted as part of the next summary report required under § 63.10(e)(3). The report shall include:(i) A description of the process change; and(4) For each existing, new, or reconstructed affected BLR and WSR source, beginning no later than the compliance dates specified in § 63.521(c), for each excursion that is not an excused excursion, the report must include a list of the affected sources or equipment, the monitored parameter, an estimate of the quantity in pounds of each regulated pollutant emitted over any emission limit, a description of the method used to estimate the emissions, the cause of the excursion (including unknown cause, if applicable), as applicable, and the corrective action taken. Include the start date, start time, and duration in hours of each excursion.(5) For pressure relief device subject to § 63.527(f), report each pressure release to the atmosphere, including pressure relief device identification name or number, the start date, start time, and duration (in minutes) of the pressure release; and an estimate of the mass quantity in pounds of each organic HAP released.(6) For heat exchangers subject to § 63.104 of subpart F of this part, the information specified in § 63.104(f)(2) of subpart F of this part.
-
(1) You must submit reports no less frequent than specified under § 63.10(e)(3) of the General Provisions.
-
(3) As required by § 63.10(e)(3), you must submit an excess emissions report for any exceedance of an emission limit, work practice standard, or operating parameter limit if the total duration of the exceedances for the reporting period is 1 percent of the total operating time for the reporting period or greater. The report must contain the information specified in § 63.10 and paragraph (b)(4) of this section. When exceedances of an emission limit or operating parameter have not occurred, you must include such information in the report. You must submit the report semiannually and the report must be delivered or postmarked by the 30th day following the end of the calendar half. If you report exceedances, you must submit the excess emissions report quarterly until a request to reduce reporting frequency is approved as described in § 63.10(e)(3)(ii).
-
(a) Anyone who owns or operates a stationary combustion turbine which must meet the emission limitation for formaldehyde must submit a semiannual compliance report according to Table 6 of this subpart. The semiannual compliance report must contain the information described in paragraphs (a)(1) through (5) of this section. The semiannual compliance report, including the excess emissions and monitoring system performance reports of § 63.10(e)(3), must be submitted by the dates specified in paragraphs (b)(1) through (5) of this section, unless the Administrator has approved a different schedule. After September 8, 2020, or once the reporting template has been available on the Compliance and Emissions Data Reporting Interface (CEDRI) website for 180 days, whichever date is later, you must submit all subsequent reports to the EPA following the procedure specified in paragraph (g) of this section.(2) Statement by a responsible official, with that official's name, title, and signature, certifying the accuracy of the content of the report.(4) Before September 8, 2020, for each deviation from an emission limitation, the compliance report must contain the information in paragraphs (a)(4)(i) through (iii) of this section.(ii) Information on the number, duration, and cause of deviations (including unknown cause, if applicable), as applicable, and the corrective action taken.(iii) Information on the number, duration, and cause for monitor downtime incidents (including unknown cause, if applicable, other than downtime associated with zero and span and other daily calibration checks).(5) Report the information specified in paragraphs (a)(5)(i) through (iv) of this section.(i) For each instance, report the start date, start time, duration, and cause of each deviation, and the corrective action taken.(ii) For each deviation, the report must include a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, a description of the method used to estimate the emissions.(iii) Information on the number, duration, and cause for monitor downtime incidents (including unknown cause, if applicable, other than downtime associated with zero and span and other daily calibration checks), as applicable, and the corrective action taken.
-
(3) As required by § 63.10(e)(1), you must submit an excess emissions report for any exceedance of an emission or operating parameter limit if the total duration of the exceedances for the reporting period is 1 percent of the total operating time for the reporting period or greater. The report must contain the information specified in § 63.10 and paragraph (b)(4) of this section. When exceedances of an emission limit or operating parameter have not occurred, you must include such information in the report. You must submit the report semiannually and the report must be delivered or postmarked by the 30th day following the end of the calendar half. If exceedances are reported, you must submit the excess emissions report quarterly until a request to reduce reporting frequency is approved as described in § 63.10(e)(3).
-
(4) A summary report specified in § 63.10(e)(3) shall be submitted on a semiannual basis (i.e., once every 6-month period). The summary report must include a description of all deviations as defined in §§ 63.683(f) and 63.695(e) that have occurred during the 6-month reporting period. For each deviation caused when the daily average value of a monitored operating parameter is less than the minimum operating parameter limit (or, if applicable, greater than the maximum operating parameter limit), the report must include the daily average values of the monitored parameter, the applicable operating parameter limit, and the date and duration of the period that the deviation occurred. For each deviation caused by lack of monitoring data, the report must include the date and duration of period when the monitoring data were not collected and the reason why the data were not collected.
-
(2) In the excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e)(3), include parameter or CEM data to demonstrate compliance or noncompliance with the alternate outlet HAP concentration established in accordance with §§ 63.703(i) and 63.704(b)(11)(ii) once the limit is approved.
-
(i) The information required under § 63.10(e)(3). For the purposes of this subpart and the information required under § 63.10(e)(3), excursions (as defined in § 63.773(d)(6)) shall be considered excess emissions.
-
(8) The owner or operator of a CMS that is out of control as defined in paragraph (c)(7) of this section shall submit all information concerning out-of-control periods, including start and end dates and hours and descriptions of corrective actions taken, in the excess emissions and continuous monitoring system performance report required in § 63.10(e)(3).
-
(6) A summary report specified in § 63.10(e)(3) of this part shall be submitted on a semi-annual basis (i.e., once every 6-month period). These summary reports are required even if the affected source does not have any control devices or does not take the performance of any control devices into account in demonstrating compliance with the emission limitations in § 63.824 or § 63.825. In addition to a report of operating parameter exceedances as required by § 63.10(e)(3)(i), the summary report shall include, as applicable:(i) Exceedances of the standards in §§ 63.824-63.825.(ii) Exceedances of either of the criteria of § 63.820(a)(2).(iii) Exceedances of the criterion of § 63.821(b)(1) and the criterion of § 63.821(b)(2) in the same month.(iv) Exceedances of the criterion of § 63.821(a)(2)(ii)(A).(v) The number, duration, and a brief description for each type of malfunction which occurred during the reporting period and which caused or may have caused any applicable emission limitation to be exceeded. The report must also include a description of actions taken by an owner or operator during a malfunction of an affected source to minimize emissions in accordance with § 63.823(b), including actions taken to correct a malfunction.
-
(1) As required by § 63.10(e)(3), the owner or operator must submit a report (or a summary report) if measured emissions are in excess of the applicable standard. The report must contain the information specified in § 63.10(e)(3)(v) and be submitted semiannually unless quarterly reports are required as a result of excess emissions.
Citations to §63.10(e)(3)(C)
-
(d) The owner or operator of an affected source demonstrating compliance in accordance with § 63.804(g)(4), (6), and (h)(2) of this subpart shall submit the excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e) of subpart A. The report shall include the monitored operating parameter values required by § 63.804(g) (4) and (6). If the source experiences excess emissions, the report shall be submitted quarterly for at least 1 year after the excess emissions occur and until a request to reduce reporting frequency is approved, as indicated in § 63.10(e)(3)(C). If no excess emissions occur, the report shall be submitted semiannually.
Citations to §63.10(e)(3)(i)
-
(6) A summary report specified in § 63.10(e)(3) of this part shall be submitted on a semi-annual basis (i.e., once every 6-month period). These summary reports are required even if the affected source does not have any control devices or does not take the performance of any control devices into account in demonstrating compliance with the emission limitations in § 63.824 or § 63.825. In addition to a report of operating parameter exceedances as required by § 63.10(e)(3)(i), the summary report shall include, as applicable:(i) Exceedances of the standards in §§ 63.824-63.825.(ii) Exceedances of either of the criteria of § 63.820(a)(2).(iii) Exceedances of the criterion of § 63.821(b)(1) and the criterion of § 63.821(b)(2) in the same month.(iv) Exceedances of the criterion of § 63.821(a)(2)(ii)(A).(v) The number, duration, and a brief description for each type of malfunction which occurred during the reporting period and which caused or may have caused any applicable emission limitation to be exceeded. The report must also include a description of actions taken by an owner or operator during a malfunction of an affected source to minimize emissions in accordance with § 63.823(b), including actions taken to correct a malfunction.
Citations to §63.10(e)(3)(ii)
-
(ii) Quarterly reports shall be submitted when the source experiences an exceedance of a temperature limit monitored according to the provisions of § 63.1258(b)(1)(iii) or an exceedance of the outlet concentration monitored according to the provisions of § 63.1258(b)(1)(x) or (b)(5). Once an affected source reports quarterly, the affected source shall follow a quarterly reporting format until a request to reduce reporting frequency is approved. If an owner or operator submits a request to reduce the frequency of reporting, the provisions in § 63.10(e)(3)(ii) and (iii) shall apply, except that the phrase “excess emissions and continuous monitoring system performance report and/or summary report” shall mean “Periodic report” for the purposes of this section.
-
(3) As required by § 63.10(e)(3), you must submit an excess emissions report for any exceedance of an emission limit, work practice standard, or operating parameter limit if the total duration of the exceedances for the reporting period is 1 percent of the total operating time for the reporting period or greater. The report must contain the information specified in § 63.10 and paragraph (b)(4) of this section. When exceedances of an emission limit or operating parameter have not occurred, you must include such information in the report. You must submit the report semiannually and the report must be delivered or postmarked by the 30th day following the end of the calendar half. If you report exceedances, you must submit the excess emissions report quarterly until a request to reduce reporting frequency is approved as described in § 63.10(e)(3)(ii).
Citations to §63.10(e)(3)(iii)
-
(ii) Quarterly reports shall be submitted when the source experiences an exceedance of a temperature limit monitored according to the provisions of § 63.1258(b)(1)(iii) or an exceedance of the outlet concentration monitored according to the provisions of § 63.1258(b)(1)(x) or (b)(5). Once an affected source reports quarterly, the affected source shall follow a quarterly reporting format until a request to reduce reporting frequency is approved. If an owner or operator submits a request to reduce the frequency of reporting, the provisions in § 63.10(e)(3)(ii) and (iii) shall apply, except that the phrase “excess emissions and continuous monitoring system performance report and/or summary report” shall mean “Periodic report” for the purposes of this section.
-
(4) You may reduce the frequency of submittal of the deviation notification report if the agency responsible for these NESHAP does not object as provided in § 63.10(e)(3)(iii).
Citations to §63.10(e)(3)(v)
-
(d) You must submit semiannual compliance reports that contain the information specified in paragraphs (d)(1) through (12) of this section, as applicable. All reports must contain the company name and address (including county), as well as the beginning and ending dates of the reporting period. For periods where no events described by paragraphs (d)(1) through (12) of this section occur, a statement must be included in the report pursuant to § 63.10(e)(3)(v). Beginning on April 1, 2029, or once the report template for this subpart has been available on the CEDRI website for one year, whichever date is later, submit all subsequent reports using the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart and following the procedure specified in § 63.9(k). The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated State agency or other authority has approved a different schedule for submission of reports, the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted.(1) Before April 1, 2029 you must clearly identify any deviation from the requirements of this subpart. Beginning on April 1, 2029, for each deviation, you must report the start date, start time, duration in hours, cause, a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit, a description of the method used to estimate the emissions, actions taken to minimize emissions, and any corrective action taken to return the affected unit to its normal or usual manner of operation.(2) Except as specified in paragraph (d)(11) of this section, you must include the information specified in § 63.104(f)(2) each time you invoke the delay of repair provisions for a heat exchange system with a cooling water flow rate equal to or greater than 8,000 gal/min.(3) You must provide the following information for each delay of leak repair beyond 15 days for any process equipment, storage tank, surge control vessel, bottoms receiver, and each delay of leak repair beyond 45 days for any heat exchange system with a cooling water flow rate less than 8,000 gal/min: information on the date the leak was identified, the reason for the delay in repair, and the date the leak was repaired.(4) You must report each process change that affects a compliance determination and submit a new certification of compliance with the applicable requirements in accordance with the procedures specified in paragraph (b) of this section.(5) If you comply with the alternative standard, as specified in table 2 or 3 to this subpart, report the information required in § 63.1258(b)(5).(6) Report any changes in the overlapping provisions with which you comply.(7) Report any transfer of liquids that are reactive or resinous materials, as defined in § 63.11502(b), and not included in the NOCS.(8) If a malfunction occurred during the reporting period, the report must include the number of instances of malfunctions that caused emissions in excess of a standard. For each malfunction that caused emissions in excess of a standard, the report must include a list of the affected sources or equipment, an estimate of the volume of each regulated pollutant emitted over the standard, and a description of the method used to estimate the emissions. The report must also include a description of actions you took during a malfunction of an affected source to minimize emissions in accordance with § 63.11495(d), including actions taken to correct a malfunction. On and after April 1, 2029, malfunctions are reported as deviations under paragraph (d)(1) of this section and this paragraph (d)(8) no longer applies.(9) For each CMPU complying with the provisions of § 63.11495(a)(6), report the information listed in paragraphs (d)(9)(i) through (vi) of this section.(i) The number of components for which leaks were detected, the total number of components monitored, and the number of components for which leaks were not repaired, identifying the number of those that are determined nonrepairable, and totaled by component type.(ii) The facts that explain any delay of repairs and, where appropriate, why a CMPU shutdown was technically infeasible.(iii) For pressure relief devices subject to the requirements in § 63.11495(a)(6)(iv) include the information specified in paragraphs (d)(9)(iii)(A) through (C) of this section.(A) For pressure relief devices in organic HAP gas or vapor service, pursuant to § 63.165(e)(1), report the instrument readings and dates for all readings of 500 ppm or greater.(B) For pressure relief devices in organic HAP gas or vapor service, pursuant to § 63.165(e)(2), report the instrument readings and dates of instrument reading conducted.(C) For pressure relief devices in organic HAP service subject to § 63.165(e)(3), report each pressure release to the atmosphere, including pressure relief device identification name or number, the start date, start time, and duration (in minutes) of the pressure release; an estimate of the mass quantity in pounds of each organic HAP released; the results of any root cause analysis and corrective action analysis completed during the reporting period, including the corrective actions implemented during the reporting period; and, if applicable, the implementation schedule for planned corrective actions to be implemented subsequent to the reporting period.(iv) For bypass lines subject to the requirements in § 63.172(j) as specified in § 63.11495(a)(6)(ix), include the start date, start time, duration in hours, estimate of the volume of gas in standard cubic feet, the concentration of organic HAP in the gas in parts per million by volume and the resulting mass emissions of organic HAP in pounds that bypass a control device. For periods when the flow indicator is not operating, report the start date, start time, and duration in hours.(v) If applicable, the compliance option selected under § 63.172(n) as specified in § 63.11495(a)(6)(ix).(vi) If you elect to meet the requirements in § 63.178(b) as specified in § 63.11495(a)(6)(xi), include the information listed in paragraphs (d)(9)(vi)(A) through (E) of this section.(A) Batch product process equipment train identification;(B) The number of pressure tests conducted;(C) The number of pressure tests where the equipment train failed the pressure test;(D) The facts that explain any delay of repairs; and(E) The results of all monitoring to determine compliance with § 63.172(f).(10) For bypass lines subject to the requirements § 63.11495(e), report the start date, start time, duration in hours, estimate of the volume of gas in standard cubic feet, the concentration of organic HAP in the gas in ppmv and the resulting mass emissions of organic HAP in pounds that bypass a control device. For periods when the flow indicator is not operating, report the start date, start time, and duration in hours.(11) If you are subject to the requirements specified in item 1.c of table 8 to this subpart (for heat exchange systems with a cooling water flow rate greater than or equal to 8,000 gal/min), then you must submit the information specified in § 63.104(f)(2)(vi) instead of the heat exchange system information specified in paragraphs (d)(2) and (3) of this section.(12) If you are subject to the requirements specified in § 63.11497(e) and obtain an instrument reading greater than 500 ppmv when monitoring a pressure vessel in accordance with § 63.11497(e)(2), report an identification of the pressure vessel and a copy of the records specified in paragraph (c)(4)(vii)(B) of this section.
-
(f) A semiannual report stating that no excess emissions or deviations of monitored parameters occurred during the reporting period as required by § 63.10(e)(3)(v) of the general provisions in subpart A of this part if no deviations have occurred.
-
(3) Beginning June 3, 2027, or once the report template for this subpart has been available on the CEDRI website for one year, whichever date is later, submit the excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e)(3), including the information required by paragraph (a)(1) of this section, according to § 63.1211(g). When the report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirements in § 63.10(e)(3)(v), (e)(3)(vi)(L), and (e)(3)(vi)(M) of subpart A of this part to submit the date of the report and the name, title, and signature of the responsible official who is certifying the accuracy of the report.
-
(e) As required by § 63.10(e)(3)(v) of this part, the owner or operator shall report semiannually if measured emissions are in excess of the applicable standard or a monitored parameter deviates from the levels established during the performance test. The report shall contain the information specified in § 63.10(c) of this part as well as the additional records required by the recordkeeping requirements of paragraph (d) of this section. When no deviations have occurred, the owner or operator shall submit a report stating that no excess emissions occurred during the reporting period.
-
(b) The owner or operator of a major or area source must submit semiannual reports according to the requirements in § 63.10(e)(3). Except, the owner or operator must submit the semiannual reports within 60 days after the end of each 6-month period instead of within 30 days after the calendar half as specified in § 63.10(e)(3)(v). When no deviations of parameters have occurred, the owner or operator must submit a report stating that no excess emissions occurred during the reporting period.(1) A report must be submitted if any of these conditions occur during a 6-month reporting period:(i) The corrective action specified in the OM&M plan for a bag leak detection system alarm was not initiated within 1 hour.(ii) The corrective action specified in the OM&M plan for a continuous opacity monitoring deviation was not initiated within 1 hour.(iii) The corrective action specified in the OM&M plan for visible emissions from an aluminum scrap shredder was not initiated within 1 hour.(iv) An excursion of a compliant process or operating parameter value or range (e.g., lime injection rate or screw feeder setting, total reactive chlorine flux injection rate, afterburner operating temperature, fabric filter inlet temperature, definition of acceptable scrap, or other approved operating parameter).(v) [Reserved](vi) An affected source (including an emission unit in a secondary aluminum processing unit) was not operated according to the requirements of this subpart.(vii) A deviation from the 3-day, 24-hour rolling average emission limit for a secondary aluminum processing unit.(2) Each report must include each of these certifications, as applicable:(i) “Only unpainted aluminum chips were used as feedstock in any thermal chip dryer during this reporting period.”(ii) “Only dross and salt flux were used as the charge materials in any dross-only furnace during this reporting period.”(iii) “Each furnace was operated such that the level of molten metal remained above the top of the passage between the sidewell and hearth during reactive fluxing, and reactive flux, except for cover flux, was added only to the sidewell or to a furnace hearth equipped with an add-on air pollution control device for PM, HCl, and D/F emissions during this reporting period.”(iv) For each group 1 melting/holding furnace without add-on air pollution control devices and using pollution prevention measures that processes only clean charge material: “Each group 1 furnace without add-on air pollution control devices subject to emission limits in § 63.1505(i)(2) processed only clean charge during this reporting period.”(v) “Only clean charge materials were processed in any group 2 furnace during this reporting period, and no fluxing was performed or all fluxing performed was conducted using only nonreactive, non-HAP-containing/non-HAP-generating fluxing gases or agents, except for cover fluxes, during this reporting period.”(vi) “Only nonreactive, non-HAP-containing, non-HAP-generating flux gases, agents, or materials were used at any time during this reporting period.”(vii) For each affected source choosing to demonstrate compliance during periods of startup and shutdown in accordance with § 63.1513(f)(1): “During each startup and shutdown, no flux and no feed/charge were added to the emission unit, and electricity, propane or natural gas were used as the sole source of heat or the emission unit was not heated.”(3) The owner or operator must submit the results of any performance test conducted during the reporting period, including one complete report documenting test methods and procedures, process operation, and monitoring parameter ranges or values for each test method used for a particular type of emission point tested.(i) Within 60 days after the date of completing each performance test (as defined in § 63.2) required by this subpart, you must submit the results of the performance tests, including any associated fuel analyses, following the procedure specified in either paragraph (b)(3)(i)(A) or (B) of this section.(A) For data collected using test methods supported by the EPA's Electronic Reporting Tool (ERT) as listed on the EPA's ERT Web site (https://www3.epa.gov/ttn/chiefert/ert_info.html), you must submit the results of the performance test to the EPA via the Compliance and Emissions Data Reporting Interface (CEDRI). (CEDRI can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/).) Performance test data must be submitted in a file format generated through the use of the EPA's ERT or an alternate electronic file format consistent with the extensible markup language (XML) schema listed on the EPA's ERT Web site. If you claim that some of the performance test information being submitted is confidential business information (CBI), you must submit a complete file generated through the use of the EPA's ERT or an alternate electronic file consistent with the XML schema listed on the EPA's ERT Web site, including information claimed to be CBI, on a compact disc, flash drive, or other commonly used electronic storage media to the EPA. The electronic media must be clearly marked as CBI and mailed to U.S. EPA/OAQPS/CORE CBI Office, Attention: Group Leader, Measurement Policy Group, MD C404-02, 4930 Old Page Rd., Durham, NC 27703. The same ERT or alternate file with the CBI omitted must be submitted to the EPA via the EPA's CDX as described earlier in this paragraph.(B) For data collected using test methods that are not supported by the EPA's ERT as listed on the EPA's ERT Web site, you must submit the results of the performance test to the Administrator at the appropriate address listed in § 63.13.(ii) [Reserved](4) A malfunction report that is required under paragraph (d) of this section shall be submitted simultaneously with the semiannual excess emissions/summary report required by paragraph (b) of this section.
-
(a) The owner or operator of any affected BLR source, as well as the owner or operator of any affected WSR source that is subject to the emission limit for process vents, storage tanks, and wastewater systems and/or is subject to the dioxins and furans emission limit for process vents, shall comply with the reporting requirements of applicable paragraphs of § 63.10, as specified in the General Provisions applicability table in this subpart. The owner or operator shall also submit to the Administrator, as part of the quarterly excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e)(3), the following recorded information. On and after July 15, 2027 or once the reporting template for this subpart has been available on the CEDRI website for 1 year, whichever date is later, owners and operators must submit all subsequent reports following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Polymers and Resins Sector Lead. Owners and operators must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports under § 63.9(i) and § 63.10(a), the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. If a report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirements in § 63.10(e)(3)(v), § 63.10(e)(3)(vi)(L), and § 63.10(e)(3)(vi)(M) to submit the date of the report and the name, title, and signature of the responsible official who is certifying the accuracy of the report.(1) Reports of monitoring data, including 15-minute monitoring values as well as daily average values or per-unit operation average values, as applicable, of monitored parameters for all operating days or unit operations when the average values were outside the ranges established in the Notification of Compliance Status or operating permit, including reports specified in paragraph (a)(4) of this section.(2) Reports of the duration of periods when monitoring data is not collected for each excursion caused by insufficient monitoring data, including reports specified in paragraph (a)(4) of this section. An excursion means any of the three cases listed in paragraph (a)(2)(i) or (a)(2)(ii) of this section. For a control device where multiple parameters are monitored, if one or more of the parameters meets the excursion criteria in paragraph (a)(2)(i) or (a)(2)(ii) of this section, this is considered a single excursion for the control device. In the report, include the identification of the source, start date, start time, duration in hours, and monitored parameter(s) meeting the excursion criteria.(i) When the period of control device operation is 4 hours or greater in an operating day and monitoring data are insufficient to constitute a valid hour of data, as defined in paragraph (a)(2)(iii) of this section, for at least 75 percent of the operating hours.(ii) When the period of control device operation is less than 4 hours in an operating day and more than one of the hours during the period of operation does not constitute a valid hour of data due to insufficient monitoring data.(iii) Monitoring data are insufficient to constitute a valid hour of data, as used in paragraphs (a)(2)(i) and (ii) of this section, if measured values are unavailable for any of the 15-minute periods within the hour.(3) Whenever a process change, as defined in § 63.115(e), is made that causes the emission rate from a de minimis emission point to become a process vent with an emission rate of one pound per year or greater, the owner or operator shall submit a report within 180 calendar days after the process change. The report may be submitted as part of the next summary report required under § 63.10(e)(3). The report shall include:(i) A description of the process change; and(4) For each existing, new, or reconstructed affected BLR and WSR source, beginning no later than the compliance dates specified in § 63.521(c), for each excursion that is not an excused excursion, the report must include a list of the affected sources or equipment, the monitored parameter, an estimate of the quantity in pounds of each regulated pollutant emitted over any emission limit, a description of the method used to estimate the emissions, the cause of the excursion (including unknown cause, if applicable), as applicable, and the corrective action taken. Include the start date, start time, and duration in hours of each excursion.(5) For pressure relief device subject to § 63.527(f), report each pressure release to the atmosphere, including pressure relief device identification name or number, the start date, start time, and duration (in minutes) of the pressure release; and an estimate of the mass quantity in pounds of each organic HAP released.(6) For heat exchangers subject to § 63.104 of subpart F of this part, the information specified in § 63.104(f)(2) of subpart F of this part.
-
(1) As required by § 63.10(e)(3), the owner or operator must submit a report (or a summary report) if measured emissions are in excess of the applicable standard. The report must contain the information specified in § 63.10(e)(3)(v) and be submitted semiannually unless quarterly reports are required as a result of excess emissions.
-
(c) The owner or operator must submit semiannual excess emissions reports containing the information specified in paragraphs (c)(1) through (5) of this section. The owner or operator must submit semiannual excess emission reports and summary reports following the procedure specified in paragraph (d)(2) of this section as specified in § 63.10(e)(3)(v).(1) If the total duration of excess emissions or process control system parameter exceedances for the reporting period is less than 1 percent of the total reporting period operating time, and CMS downtime is less than 5 percent of the total reporting period operating time, only the summary report is required to be submitted. This report will be titled “Summary Report—Gaseous and Opacity Excess Emissions and Continuous Monitoring System Performance” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section.(iii) An identification of each process unit with the corresponding air pollution control device, being included in the semiannual report, including the pollutants monitored at each process unit, and the total operating time for each process unit.(v) An identification of the monitoring equipment used for each process unit and the corresponding model number.(vii) An emission data summary, including the total duration of excess emissions (recorded in minutes for opacity and hours for gases), the duration of excess emissions expressed as a percent of operating time, the number of averaging periods recorded as excess emissions, and reason for the excess emissions (e.g., startup/shutdown, control equipment problems, other known reasons, or other unknown reasons).(viii) A CMS performance summary, including the total duration of CMS downtime during the reporting period (recorded in minutes for opacity and hours for gases), the total duration of CMS downtime expressed as a percent of the total source operating time during that reporting period, and a breakdown of the total CMS downtime during the reporting period (e.g., monitoring equipment malfunction, non-monitoring equipment malfunction, quality assurance, quality control calibrations, other known causes, or other unknown causes).(x) This will state that, based on information and belief formed after reasonable inquiry, the statements and information in the document are true, accurate, and complete.(2) [Reserved](3) If measured parameters meet any of the conditions specified in § 63.864(k)(1) or (2), the owner or operator of the affected source must submit a semiannual report describing the excess emissions that occurred. If the total duration of monitoring exceedances for the reporting period is 1 percent or greater of the total reporting period operating time, or the total CMS downtime for the reporting period is 5 percent or greater of the total reporting period operating time, or any violations according to § 63.864(k)(2) occurred, information from both the summary report and the excess emissions and continuous monitoring system performance report must be submitted. This report will be titled “Excess Emissions and Continuous Monitoring System Performance Report” and must contain the information specified in paragraphs (c)(1)(i) through (x) of this section, in addition to the information required in § 63.10(c)(5) through (14), as specified in paragraphs (c)(3)(i) through (vi) of this section. Reporting monitoring exceedances does not constitute a violation of the applicable standard unless the violation criteria in § 63.864(k)(2) and (3) are reached.(i) An identification of the date and time identifying each period during which the CMS was inoperative except for zero (low-level) and high-level checks.(ii) An identification of the date and time identifying each period during which the CMS was out of control, as defined in § 63.8(c)(7).(iii) The specific identification of each period of excess emissions and parameter monitoring exceedances as described in paragraphs (c)(3)(iii)(A) through (E) of this section.(A) (1) The total number of 6-minute averages in the reporting period (excluding process unit downtime).(2) [Reserved](3) The number of 6-minute averages in the reporting period that exceeded the relevant opacity limit.(4) The percent of 6-minute averages in the reporting period that exceed the relevant opacity limit.(5) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(B) [Reserved](C) (1) The operating limits established during the performance test for scrubbing liquid flow rate and pressure drop across the scrubber (or alternatively, fan amperage or RPM if used for smelt dissolving tank scrubbers).(2) The number of 3-hour wet scrubber parameter averages below the minimum operating limit established during the performance test, if applicable.(3) An identification of each exceedance by start and end time, date, and cause of exceedance (including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(D) (1) The operating limit established during the performance test.(2) The number of 1-hour and 3-hour temperature averages below the minimum operating limit established during the performance test.(3) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(E) For alternative parameters established according to § 63.864(e)(13) or (14) subject to the requirements of § 63.864(k)(1) and (2):(1) The type of operating parameters monitored for compliance.(2) The operating limits established during the performance test.(3) The number of 3-hour parameter averages outside of the operating limits established during the performance test.(4) An identification of each exceedance by start and end time, date, and cause of exceedance including startup/shutdown, control equipment problems, process problems, other known causes, or other unknown causes).(4) If a source fails to meet an applicable standard, including any emission limit in § 63.862 or any opacity or CPMS operating limit in § 63.864, report such events in the semiannual excess emissions report. Report the number of failures to meet an applicable standard. For each instance, report the date, time and duration of each failure. For each failure, the report must include a list of the affected sources or equipment, and for any failure to meet an emission limit under § 63.862, provide an estimate of the quantity of each regulated pollutant emitted over the emission limit, and a description of the method used to estimate the emissions.(5) The owner or operator of an affected source or process unit subject to the requirements of this subpart and subpart S of this part may combine excess emissions and/or summary reports for the mill.
Citations to §63.10(e)(3)(vi)
-
(d) For EGUs whose owners or operators rely on a CMS to comply with an emissions or operating limit, the semiannual compliance reports described in paragraph (c) of this section must include the excess emissions and monitor downtime summary report described in 40 CFR 63.10(e)(3)(vi). However, starting with the first calendar quarter of 2024, reporting of the information under 40 CFR 63.10(e)(3)(vi) (and under paragraph (e)(3)(v), if the applicable excess emissions and/or monitor downtime threshold is exceeded) is discontinued for all CMS, and you must, instead, include in the quarterly compliance reports described in paragraph (g) of this section the applicable data elements in section 13 of appendix E to this subpart for any “deviation” (as defined in 40 CFR 63.10042 and elsewhere in this subpart) that occurred during the calendar quarter. If there were no deviations, you must include a statement to that effect in the quarterly compliance report.
-
(9) The owner or operator shall submit a summary report semiannually within 60 days of the reporting period to the EPA via the Compliance and Emissions Data Reporting Interface (CEDRI). (CEDRI can be accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov/). You must use the appropriate electronic report in CEDRI for this subpart. Instead of using the electronic report in CEDRI for this subpart, you may submit an alternate electronic file consistent with the extensible markup language (XML) schema listed on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/compliance-and-emissions-data-reporting-interface-cedri), once the XML schema is available. If the reporting form specific to this subpart is not available in CEDRI at the time that the report is due, you must submit the report the Administrator at the appropriate address listed in § 63.13. You must begin submitting reports via CEDRI no later than 90 days after the form becomes available in CEDRI. The excess emissions and summary reports must be submitted no later than 60 days after the end of the reporting period, regardless of the method in which the reports are submitted. The report must contain the information specified in § 63.10(e)(3)(vi). In addition, the summary report shall include:(i) All exceedances of maximum control device inlet gas temperature limits specified in § 63.1346(a) and (b);(ii) Notification of any failure to calibrate thermocouples and other temperature sensors as required under § 63.1350(g)(1)(iii) of this subpart; and(iii) Notification of any failure to maintain the activated carbon injection rate, and the activated carbon injection carrier gas flow rate or pressure drop, as applicable, as required under § 63.1346(c)(2).(iv) Notification of failure to conduct any combustion system component inspections conducted within the reporting period as required under § 63.1347(a)(3).(v) Any and all failures to comply with any provision of the operation and maintenance plan developed in accordance with § 63.1347(a).(vi) For each PM CPMS, HCl, Hg, and THC CEMS, SO2 CEMS, or Hg sorbent trap monitoring system, within 60 days after the reporting periods, you must report all of the calculated 30-operating day rolling average values derived from the CPMS, CEMS, CMS, or Hg sorbent trap monitoring systems.(vii) In response to each violation of an emissions standard or established operating parameter limit, the date, duration and description of each violation and the specific actions taken for each violation including inspections, corrective actions and repeat performance tests and the results of those actions.
-
(5) If the total duration of excess emissions or control system parameter exceedances for the reporting period is less than 5 percent of the total operating time for the reporting period, and CMS downtime for the reporting period is less than 10 percent of the total operating time for the reporting period, only the summary report of § 63.10(e)(3)(vi) of subpart A of this part shall be submitted, and the full excess emissions and continuous monitoring system performance report of paragraph (e)(4) of this section need not be submitted unless required by the Administrator.
-
(5) You must submit a summary report containing the information specified in § 63.10(e)(3)(vi). You must submit the summary report semiannually and the report must be delivered or postmarked by the 30th day following the end of the calendar half.
-
(5) You must submit a summary report containing the information specified in § 63.10(e)(3)(vi). You must submit the summary report semiannually and the report must be delivered or postmarked by the 30th day following the end of the calendar half.
-
(d) For each deviation from an emission limitation occurring at an affected source where you are using a continuous monitoring system (CMS) to comply with the emission limitation in this subpart, you must include the information in paragraphs (c)(1) through (6) of this section and the following information in paragraphs (d)(1) through (9) of this section and § 63.10(e)(3)(vi). This includes periods of startup, shutdown, and malfunction.(3) The date, time, and duration that each CMS was out-of-control, including the information in § 63.8(c)(8).(4) The date and time that each deviation started and stopped, and whether each deviation occurred during a period of startup, shutdown, or malfunction or during another period.(5) A summary of the total duration of the deviation during the reporting period and the total duration as a percent of the total source operating time during that reporting period.(6) A breakdown of the total duration of the deviations during the reporting period into those that are due to startup, shutdown, control equipment problems, process problems, other known causes, and other unknown causes.(7) A summary of the total duration of CMS downtime during the reporting period, and the total duration of CMS downtime as a percent of the total source operating time during that reporting period.
Citations to §63.10(e)(3)(vi)(A)
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
Citations to §63.10(e)(3)(vi)(B)
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
Citations to §63.10(e)(3)(vi)(C)
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
Citations to §63.10(e)(3)(vi)(D)
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
Citations to §63.10(e)(3)(vi)(E)
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
Citations to §63.10(e)(3)(vi)(F)
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
Citations to §63.10(e)(3)(vi)(G)
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
Citations to §63.10(e)(3)(vi)(H)
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
Citations to §63.10(e)(3)(vi)(I)
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
Citations to §63.10(e)(3)(vi)(J)
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
Citations to §63.10(e)(3)(vi)(K)
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
Citations to §63.10(e)(3)(vi)(L)
-
(3) Beginning June 3, 2027, or once the report template for this subpart has been available on the CEDRI website for one year, whichever date is later, submit the excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e)(3), including the information required by paragraph (a)(1) of this section, according to § 63.1211(g). When the report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirements in § 63.10(e)(3)(v), (e)(3)(vi)(L), and (e)(3)(vi)(M) of subpart A of this part to submit the date of the report and the name, title, and signature of the responsible official who is certifying the accuracy of the report.
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
-
(a) The owner or operator of any affected BLR source, as well as the owner or operator of any affected WSR source that is subject to the emission limit for process vents, storage tanks, and wastewater systems and/or is subject to the dioxins and furans emission limit for process vents, shall comply with the reporting requirements of applicable paragraphs of § 63.10, as specified in the General Provisions applicability table in this subpart. The owner or operator shall also submit to the Administrator, as part of the quarterly excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e)(3), the following recorded information. On and after July 15, 2027 or once the reporting template for this subpart has been available on the CEDRI website for 1 year, whichever date is later, owners and operators must submit all subsequent reports following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Polymers and Resins Sector Lead. Owners and operators must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports under § 63.9(i) and § 63.10(a), the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. If a report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirements in § 63.10(e)(3)(v), § 63.10(e)(3)(vi)(L), and § 63.10(e)(3)(vi)(M) to submit the date of the report and the name, title, and signature of the responsible official who is certifying the accuracy of the report.(1) Reports of monitoring data, including 15-minute monitoring values as well as daily average values or per-unit operation average values, as applicable, of monitored parameters for all operating days or unit operations when the average values were outside the ranges established in the Notification of Compliance Status or operating permit, including reports specified in paragraph (a)(4) of this section.(2) Reports of the duration of periods when monitoring data is not collected for each excursion caused by insufficient monitoring data, including reports specified in paragraph (a)(4) of this section. An excursion means any of the three cases listed in paragraph (a)(2)(i) or (a)(2)(ii) of this section. For a control device where multiple parameters are monitored, if one or more of the parameters meets the excursion criteria in paragraph (a)(2)(i) or (a)(2)(ii) of this section, this is considered a single excursion for the control device. In the report, include the identification of the source, start date, start time, duration in hours, and monitored parameter(s) meeting the excursion criteria.(i) When the period of control device operation is 4 hours or greater in an operating day and monitoring data are insufficient to constitute a valid hour of data, as defined in paragraph (a)(2)(iii) of this section, for at least 75 percent of the operating hours.(ii) When the period of control device operation is less than 4 hours in an operating day and more than one of the hours during the period of operation does not constitute a valid hour of data due to insufficient monitoring data.(iii) Monitoring data are insufficient to constitute a valid hour of data, as used in paragraphs (a)(2)(i) and (ii) of this section, if measured values are unavailable for any of the 15-minute periods within the hour.(3) Whenever a process change, as defined in § 63.115(e), is made that causes the emission rate from a de minimis emission point to become a process vent with an emission rate of one pound per year or greater, the owner or operator shall submit a report within 180 calendar days after the process change. The report may be submitted as part of the next summary report required under § 63.10(e)(3). The report shall include:(i) A description of the process change; and(4) For each existing, new, or reconstructed affected BLR and WSR source, beginning no later than the compliance dates specified in § 63.521(c), for each excursion that is not an excused excursion, the report must include a list of the affected sources or equipment, the monitored parameter, an estimate of the quantity in pounds of each regulated pollutant emitted over any emission limit, a description of the method used to estimate the emissions, the cause of the excursion (including unknown cause, if applicable), as applicable, and the corrective action taken. Include the start date, start time, and duration in hours of each excursion.(5) For pressure relief device subject to § 63.527(f), report each pressure release to the atmosphere, including pressure relief device identification name or number, the start date, start time, and duration (in minutes) of the pressure release; and an estimate of the mass quantity in pounds of each organic HAP released.(6) For heat exchangers subject to § 63.104 of subpart F of this part, the information specified in § 63.104(f)(2) of subpart F of this part.
Citations to §63.10(e)(3)(vi)(M)
-
(3) Beginning June 3, 2027, or once the report template for this subpart has been available on the CEDRI website for one year, whichever date is later, submit the excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e)(3), including the information required by paragraph (a)(1) of this section, according to § 63.1211(g). When the report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirements in § 63.10(e)(3)(v), (e)(3)(vi)(L), and (e)(3)(vi)(M) of subpart A of this part to submit the date of the report and the name, title, and signature of the responsible official who is certifying the accuracy of the report.
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (I) and (K) through (M). For each continuous monitoring system, the Periodic report must also include the information in § 63.10(e)(3)(vi)(J).
-
(i) Each Periodic report must include the information in § 63.10(e)(3)(vi)(A) through (M) of subpart A of this part, as applicable.
-
(a) The owner or operator of any affected BLR source, as well as the owner or operator of any affected WSR source that is subject to the emission limit for process vents, storage tanks, and wastewater systems and/or is subject to the dioxins and furans emission limit for process vents, shall comply with the reporting requirements of applicable paragraphs of § 63.10, as specified in the General Provisions applicability table in this subpart. The owner or operator shall also submit to the Administrator, as part of the quarterly excess emissions and continuous monitoring system performance report and summary report required by § 63.10(e)(3), the following recorded information. On and after July 15, 2027 or once the reporting template for this subpart has been available on the CEDRI website for 1 year, whichever date is later, owners and operators must submit all subsequent reports following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Polymers and Resins Sector Lead. Owners and operators must use the appropriate electronic report template on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for this subpart. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated state agency or other authority has approved a different schedule for submission of reports under § 63.9(i) and § 63.10(a), the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted. If a report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirements in § 63.10(e)(3)(v), § 63.10(e)(3)(vi)(L), and § 63.10(e)(3)(vi)(M) to submit the date of the report and the name, title, and signature of the responsible official who is certifying the accuracy of the report.(1) Reports of monitoring data, including 15-minute monitoring values as well as daily average values or per-unit operation average values, as applicable, of monitored parameters for all operating days or unit operations when the average values were outside the ranges established in the Notification of Compliance Status or operating permit, including reports specified in paragraph (a)(4) of this section.(2) Reports of the duration of periods when monitoring data is not collected for each excursion caused by insufficient monitoring data, including reports specified in paragraph (a)(4) of this section. An excursion means any of the three cases listed in paragraph (a)(2)(i) or (a)(2)(ii) of this section. For a control device where multiple parameters are monitored, if one or more of the parameters meets the excursion criteria in paragraph (a)(2)(i) or (a)(2)(ii) of this section, this is considered a single excursion for the control device. In the report, include the identification of the source, start date, start time, duration in hours, and monitored parameter(s) meeting the excursion criteria.(i) When the period of control device operation is 4 hours or greater in an operating day and monitoring data are insufficient to constitute a valid hour of data, as defined in paragraph (a)(2)(iii) of this section, for at least 75 percent of the operating hours.(ii) When the period of control device operation is less than 4 hours in an operating day and more than one of the hours during the period of operation does not constitute a valid hour of data due to insufficient monitoring data.(iii) Monitoring data are insufficient to constitute a valid hour of data, as used in paragraphs (a)(2)(i) and (ii) of this section, if measured values are unavailable for any of the 15-minute periods within the hour.(3) Whenever a process change, as defined in § 63.115(e), is made that causes the emission rate from a de minimis emission point to become a process vent with an emission rate of one pound per year or greater, the owner or operator shall submit a report within 180 calendar days after the process change. The report may be submitted as part of the next summary report required under § 63.10(e)(3). The report shall include:(i) A description of the process change; and(4) For each existing, new, or reconstructed affected BLR and WSR source, beginning no later than the compliance dates specified in § 63.521(c), for each excursion that is not an excused excursion, the report must include a list of the affected sources or equipment, the monitored parameter, an estimate of the quantity in pounds of each regulated pollutant emitted over any emission limit, a description of the method used to estimate the emissions, the cause of the excursion (including unknown cause, if applicable), as applicable, and the corrective action taken. Include the start date, start time, and duration in hours of each excursion.(5) For pressure relief device subject to § 63.527(f), report each pressure release to the atmosphere, including pressure relief device identification name or number, the start date, start time, and duration (in minutes) of the pressure release; and an estimate of the mass quantity in pounds of each organic HAP released.(6) For heat exchangers subject to § 63.104 of subpart F of this part, the information specified in § 63.104(f)(2) of subpart F of this part.
Citations to §63.10(e)(4)
-
(i) The owner or operator of an affected source required to use a continuous opacity monitoring system (COMS) shall record the monitoring data produced during a performance test required under § 63.7 and shall furnish the Administrator a written report of the monitoring results in accordance with the provisions of § 63.10(e)(4).
Citations to §63.10(f)
-
(v) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(v) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(5) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(5) Approval of a major change to recordkeeping/reporting under 40 CFR 63.10(f). A “major change to recordkeeping/reporting” is defined in 40 CFR 63.90.
-
(5) Approval of a major change to recordkeeping and reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(5) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(3) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(5) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(5) Approval of a major change to recordkeeping/reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(4) Approval of a major change to recordkeeping/ reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.As required in § 63.11157(a), you must comply with the requirements of the General Provisions (40 CFR part 63, subpart A) as shown in the following table.
-
(5) Approval of a major change to recordkeeping/reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(5) Approval of major change to recordkeeping and reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(4) Approval of a major change to recordkeeping/ reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.As required in § 63.11397(a), you must comply with the requirements of the NESHAP General Provisions (40 CFR part 63, subpart A) as shown in the following table.
-
(4) Approval of a major change to recordkeeping/reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(4) Approval of a major change to recordkeeping/reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.As required in § 63.11409, you must install and operate capture systems and comply with the applicable emissions limit for each emissions source shown in the following table.
-
(4) Approval of a major change to recordkeeping/reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(4) Approval of a major change to recordkeeping/reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(4) Approval of a major change to recordkeeping/reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(4) Approval of a major change to recordkeeping/reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of a major change to recordkeeping/reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(4) Approval of a major change to recordkeeping/reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(5) Approval of a major change to recordkeeping and reporting under § 63.10(f), of the General Provisions of this part. A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(5) Approval of a major change to recordkeeping and reporting under § 63.10(f), of the General Provisions of this part. A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(5) Approval of a major change to recordkeeping and reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(5) Approval of a waiver of recordkeeping or reporting requirements under § 63.10(f), or another major change to recordkeeping/reporting. A “major change to recordkeeping/reporting” is defined in § 63.90(a).
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of a major change to recordkeeping/reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90. As required in § 63.11432, you must comply with the requirements of the NESHAP General Provisions (40 CFR part 63, subpart A) as shown in the following table.
-
(5) Approval of a major change to recordkeeping and reporting under § 63.10(f). A “major change to recordkeeping/reporting” is defined in § 63.90.
-
(7) If the owner or operator has been granted a waiver from recordkeeping or reporting requirements under § 63.10(f) of subpart A of this part, any information demonstrating whether a source is meeting the requirements for a waiver of recordkeeping or reporting requirements;
-
(5) Approval of a waiver of recordkeeping or reporting requirements under § 63.10(f), or another major change to recordkeeping/reporting. A “major change to recordkeeping/reporting” is defined in § 63.90(a).
-
(6) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under §§ 63.10(f) and 63.1211(a) through (c), as defined under § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(9) The owner or operator of an affected source granted a waiver under § 63.10(f) shall maintain the information, if any, specified by the Administrator as a condition of the waiver of recordkeeping or reporting requirements.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(2) The owner or operator of an affected source granted a waiver under § 63.10(f) shall maintain any information demonstrating whether an affected source is meeting the requirements for a waiver of recordkeeping or reporting requirements.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(9) The owner or operator of an affected source granted a waiver of recordkeeping or reporting requirements under the General Provisions' recordkeeping and reporting requirements in § 63.10(f) shall maintain the information, if any, specified by the Administrator as a condition of the waiver of recordkeeping or reporting requirements.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(5) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(e) You may apply to the Administrator for a waiver of recordkeeping and reporting requirements by complying with the requirements of § 63.10(f). Electronic reporting to the EPA cannot be waived.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90 and as required in this subpart.
-
(viii) If the owner or operator has been granted a waiver from recordkeeping or reporting requirements under § 63.10(f), any information demonstrating whether a source is meeting the requirements for a waiver of recordkeeping or reporting requirements;
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting as specified in § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(5) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) The authority under § 63.10(f) to approve major alternatives (as defined in § 63.90) to recordkeeping, notification, and reporting requirements in §§ 63.2998 through 63.3000 is not delegated.
-
(5) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(15) Any information demonstrating whether a source is meeting the requirements for a waiver of recordkeeping or reporting requirements, if the source has been granted a waiver under § 63.10(f); and
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(a) The owner or operator of an affected source subject to the emissions standards in § 63.362 must fulfill all reporting requirements in § 63.10(a), (d), (e), and (f), according to the applicability in table 6 to this subpart. These reports will be made to the Administrator at the appropriate address identified in § 63.13 or submitted electronically.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(9) The owner or operator of an affected source granted a waiver under § 63.10(f) shall maintain the information, if any, specified by the Administrator as a condition of the waiver of recordkeeping or reporting requirements.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in §§ 63.5180 and 63.5190.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Under § 63.10(f), the authority to approve major alternatives to the reporting and recordkeeping requirements listed in §§ 63.5764, 63.5767, and 63.5770 is not delegated. A “major alternative” is defined in § 63.90.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Waiver or approval of requests under § 63.10(f) for alternative requirements or major changes to the recordkeeping and reporting requirements specified in this subpart, as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Waiver or approval of requests under § 63.10(f) for alternative requirements or major changes to the recordkeeping and reporting requirements specified in this subpart, as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(6) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(5) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(a) . Each owner or operator of a source subject to this subpart shall fulfill all recordkeeping requirements specified in § 63.10(a), (b), (d), and (f), except § 63.10(b)(2)(i), (iv) and (v). Each owner or operator must also record and maintain according to § 63.10(b)(1) the information specified in paragraph (a)(1) through (3) of this section.(1) In the event that an affected unit fails to meet an applicable standard, record the number of failures. For each failure record the date, time, and duration of each failure.(2) For each failure to meet an applicable standard, record and retain a list of the affected sources or equipment, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.(3) Record actions taken to minimize emissions in accordance with § 63.743(e), and any corrective actions taken to return the affected unit to its normal or usual manner of operation.
-
(1) Except as provided in paragraphs (a)(2) through (5) of this section, each owner or operator subject to this subpart shall fulfill the requirements contained in § 63.9(a) through (e) and (h) through (j), Notification requirements, and § 63.10(a), (b), (d), and (f), Recordkeeping and reporting requirements, of the General Provisions, 40 CFR part 63, subpart A, and that the initial notification for existing sources required in § 63.9(b)(2) shall be submitted not later than September 1, 1997, or as specified in § 63.9(b)(2). In addition to the requirements of § 63.9(h), the notification of compliance status shall include:(i) Information detailing whether the source has operated within the specified ranges of its designated operating parameters.(ii) For each coating line, where averaging will be used along with the types of quantities of coatings the facility expects to use in the first year of operation. Averaging scheme shall be approved by the Administrator or delegated State authority and shall be included as part of the facility's title V or part 70 permit.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(a) Each owner or operator of an affected source shall comply with the applicable recordkeeping and reporting requirements in § 63.10 (a), (b), (d), and (f). Any owner that receives approval pursuant to § 63.783(c) to use an add-on control system to control coating emissions shall also comply with the applicable requirements of § 63.10 (c) and (e). A summary of recordkeeping and reporting requirements is provided in Table 3 of this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(5) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of a major change to recordkeeping/reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(N) Section 63.10(f), Approval of Minor Alternatives to Recordkeeping and Reporting
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.
-
(4) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(5) Approval of major changes to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.
-
(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f) and as defined in § 63.90.