§250.1703. What are the general requirements for decommissioning?
30 C.F.R. § 250.1703
When your facilities are no longer useful for operations, you must:
Get approval from the appropriate District Manager before decommissioning wells and from the Regional Supervisor before decommissioning platforms and pipelines or other facilities;
Permanently plug all wells. Packers and bridge plugs used as qualified mechanical barriers must comply with ANSI/API Specification 11D1 (incorporated by reference, see § 250.198). You must have two independent barriers, one being an ANSI/API Specification 11D1 qualified mechanical barrier, in the exposed center wellbore prior to removing the tree and/or well control equipment;
Remove all platforms and other facilities, except as provided in §§ 250.1725(a) and 250.1730.
Decommission all pipelines;
Clear the seafloor of all obstructions created by your lease, pipeline right-of-way, or right-of-use and easement operations;
Follow all applicable requirements of subpart G of this part; and
Conduct all decommissioning activities in a manner that is safe, does not unreasonably interfere with other uses of the OCS, and does not cause undue or serious harm or damage to the human, marine, or coastal environment.
Notes, amendments, and revision history
Amendments
[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 26037, Apr. 29 2016; 84 FR 21984, May 15, 2019; 88 FR 23580, Apr. 18, 2023; 91 FR 35362, June 10, 2026]
Authority
Authority: 30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
Source
Source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.
Amendments
[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 26037, Apr. 29 2016; 84 FR 21984, May 15, 2019; 88 FR 23580, Apr. 18, 2023; 91 FR 35362, June 10, 2026]