§250.1702. When do I accrue decommissioning obligations?

30 C.F.R. § 250.1702

You accrue decommissioning obligations when you do any of the following:
(a)
Drill a well;
(b)
Install a platform, pipeline, or other facility;
(c)
Create an obstruction to other users of the OCS;
(d)
Are or become a lessee or the owner of operating rights of a lease on which there is a well that has not been permanently plugged according to this subpart, a platform, a lease term pipeline, or other facility, or an obstruction;
(e)
Are or become a holder of a pipeline right-of-way grant on which there is a pipeline, platform, other facility, or an obstruction;
(f)
Are or become the holder of a right-of-use and easement grant on which there is a well, pipeline, platform, other facility, or an obstruction; or
(g)
Re-enter a well that was previously plugged according to this subpart.
Notes, amendments, and revision history

Amendments

[76 FR 64462, Oct. 18, 2011, as amended at 88 FR 23580, Apr. 18, 2023]

Authority

Authority: 30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.

Source

Source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.

Amendments

[76 FR 64462, Oct. 18, 2011, as amended at 88 FR 23580, Apr. 18, 2023]