Title VI — Deauthorization and Backlog Prevention

113th Congress · Approved Jun 10, 2014 · 128 Stat. 1193 · Lineage

TITLE VI Deauthorization and Backlog Prevention

SEC. 6001. Deauthorization of Inactive Projects.

(a)
Purposes.— The purposes of this section are—
(1)
to identify $18,000,000,000 in water resources development projects authorized by Congress that are no longer viable for construction due to—
(A)
a lack of local support;
(B)
a lack of available Federal or non-Federal resources; or
(C)
an authorizing purpose that is no longer relevant or feasible;
(2)
to create an expedited and definitive process to deauthorize water resources development projects that are no longer viable for construction; and
(3)
to allow the continued authorization of water resources development projects that are viable for construction.
(b)
Comprehensive Status Reports.— Section 1001(b) of the Water Resources Development Act of 1986 (33 U.S.C. 579a(b)) is amended by adding at the end the following:

“(3) Minimum funding list.—At the end of each fiscal year, the Secretary shall submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives, and make available on a publicly accessible Internet site in a manner that is downloadable, searchable, and sortable, a list of—

“(A) projects or separable elements of projects authorized for construction for which funding has been obligated during the current fiscal year or any of the 6 preceding fiscal years;

“(B) the amount of funding obligated for each such project or separable element per fiscal year;

“(C) the current phase of each such project or separable element of a project; and

“(D) the amount required to complete the current phase of each such project or separable element.

“(4) Comprehensive backlog report.—

“(A) In general.—The Secretary shall compile and publish a complete list of all projects and separable elements of projects of the Corps of Engineers that are authorized for construction but have not been completed.

“(B) Required information.—The Secretary shall include on the list developed under subparagraph (A) for each project and separable element on that list—

“(i) the date of authorization of the project or separable element, including any subsequent modifications to the original authorization;

“(ii) the original budget authority for the project or separable element;

“(iii) a brief description of the project or separable element;

“(iv) the estimated date of completion of the project or separable element;

“(v) the estimated cost of completion of the project or separable element; and

“(vi) any amounts appropriated for the project or separable element that remain unobligated.

“(C) Publication.—

“(i) In general.—Not later than 1 year after the date of enactment of this paragraph, the Secretary shall submit a copy of the list developed under subparagraph (A) to—

“(I) the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives; and

“(II) the Director of the Office of Management and Budget.

“(ii) Public availability.—Beginning on the date the Secretary submits the report to Congress under clause (i), the Secretary shall make a copy of the list available on a publicly accessible Internet site in a manner that is downloadable, searchable, and sortable.”

(c)
Interim Deauthorization List.—
(1)
In general.— The Secretary shall develop an interim deauthorization list that identifies each water resources development project, or separable element of a project, authorized for construction before November 8, 2007, for which—
(A)
construction was not initiated before the date of enactment of this Act; or
(B)
construction was initiated before the date of enactment of this Act, but for which no funds, Federal or non-Federal, were obligated for construction of the project or separable element of the project during the current fiscal year or any of the 6 preceding fiscal years.
(2)
Special rule for projects receiving funds for post-authorization study.— A project or separable element of a project may not be identified on the interim deauthorization list, or the final deauthorization list developed under subsection (d), if the project or separable element received funding for a post-authorization study during the current fiscal year or any of the 6 preceding fiscal years.
(3)
Public comment and consultation.—
(A)
In general.— The Secretary shall solicit comments from the public and the Governors of each applicable State on the interim deauthorization list developed under paragraph (1).
(B)
Comment period.— The public comment period shall be 90 days.
(4)
Submission to congress; publication.— Not later than 90 days after the date of submission of the list required by section 1001(b)(4)(A) of the Water Resources Development Act of 1986 (as added by subsection (b)), the Secretary shall—
(A)
submit the interim deauthorization list to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives; and
(B)
publish the interim deauthorization list in the Federal Register.
(d)
Final Deauthorization List.—
(1)
In general.— The Secretary shall develop a final deauthorization list of each water resources development project, or separable element of a project, described in subsection (c)(1) that is identified pursuant to this subsection.
(2)
Deauthorization amount.—
(A)
In general.— The Secretary shall include on the final deauthorization list projects and separable elements of projects that have, in the aggregate, an estimated Federal cost to complete that is at least $18,000,000,000.
(B)
Determination of federal cost to complete.— For purposes of subparagraph (A), the Federal cost to complete shall take into account any allowances authorized by section 902 of the Water Resources Development Act of 1986 (33 U.S.C. 2280), as applied to the most recent project schedule and cost estimate.
(3)
Identification of projects.—
(A)
Sequencing of projects.—
(i)
In general.— The Secretary shall identify projects and separable elements of projects for inclusion on the final deauthorization list according to the order in which the projects and separable elements of the projects were authorized, beginning with the earliest authorized projects and separable elements of projects and ending once the last project or separable element of a project necessary to meet the aggregate amount under paragraph (2) is identified.
(ii)
Factors to consider.— The Secretary may identify projects and separable elements of projects in an order other than that established by clause (i) if the Secretary determines, on a case-by-case basis, that a project or separable element of a project is critical for interests of the United States, based on the possible impact of the project or separable element of the project on public health and safety, the national economy, or the environment.
(iii)
Consideration of public comments.— In making determinations under clause (ii), the Secretary shall consider any comments received under subsection (c)(3).
(B)
Appendix.— The Secretary shall include as part of the final deauthorization list an appendix that—
(i)
identifies each project or separable element of a project on the interim deauthorization list developed under subsection (c) that is not included on the final deauthorization list; and
(ii)
describes the reasons why the project or separable element is not included.
(4)
Submission to congress; publication.— Not later than 120 days after the date on which the public comment period under subsection (c)(3) expires, the Secretary shall—
(A)
submit the final deauthorization list and the appendix to the final deauthorization list to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives; and
(B)
publish the final deauthorization list and the appendix to the final deauthorization list in the Federal Register.
(e)
Deauthorization; Congressional Review.—
(1)
In general.— After the expiration of the 180-day period beginning on the date of submission of the final deauthorization report under subsection (d), a project or separable element of a project identified in the report is hereby deauthorized, unless Congress passes a joint resolution disapproving the final deauthorization report prior to the end of such period.
(2)
Non-federal contributions.—
(A)
In general.— A project or separable element of a project identified in the final deauthorization report under subsection (d) shall not be deauthorized under this subsection if, before the expiration of the 180-day period referred to in paragraph (1), the non-Federal interest for the project or separable element of the project provides sufficient funds to complete the project or separable element of the project.
(B)
Treatment of projects.— Notwithstanding subparagraph (A), each project and separable element of a project identified in the final deauthorization report shall be treated as deauthorized for purposes of the aggregate deauthorization amount specified in subsection (d)(2).
(f)
General Provisions.—
(1)
Definitions.— In this section:
(A)
Post-authorization study.— The term “post-authorization study” means—
(i)
a feasibility report developed under section 905 of the Water Resources Development Act of 1986 (33 U.S.C. 2282);
(ii)
a feasibility study, as defined in section 105(d) of the Water Resources Development Act of 1986 (33 U.S.C. 2215(d)); or
(iii)
a review conducted under section 216 of the Flood Control Act of 1970 (33 U.S.C. 549a), including an initial appraisal that—
(I)
demonstrates a Federal interest; and
(II)
requires additional analysis for the project or separable element.
(B)
Water resources development project.— The term “water resources development project” includes an environmental infrastructure assistance project or program of the Corps of Engineers.
(2)
Treatment of project modifications.— For purposes of this section, if an authorized water resources development project or separable element of the project has been modified by an Act of Congress, the date of the authorization of the project or separable element shall be deemed to be the date of the most recent such modification.

SEC. 6002. Review of Corps of Engineers Assets.

(a)
Assessment and Inventory.— Not later than 1 year after the date of enactment of this Act, the Secretary shall conduct an assessment of all properties under the control of the Corps of Engineers and develop an inventory of the properties that are not needed for the missions of the Corps of Engineers.
(b)
Criteria.— In conducting the assessment and developing the inventory under subsection (a), the Secretary shall use the following criteria:
(1)
The extent to which the property aligns with the current missions of the Corps of Engineers.
(2)
The economic impact of the property on existing communities in the vicinity of the property.
(3)
The extent to which the utilization rate for the property is being maximized and is consistent with nongovernmental industry standards for the given function or operation.
(4)
The extent to which the reduction or elimination of the property could reduce operation and maintenance costs of the Corps of Engineers.
(5)
The extent to which the reduction or elimination of the property could reduce energy consumption by the Corps of Engineers.
(c)
Notification.— As soon as practicable following completion of the inventory of properties under subsection (a), the Secretary shall provide the inventory to the Administrator of General Services.
(d)
Report to Congress.— Not later than 30 days after the date of the notification under subsection (c), the Secretary shall submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives and make publicly available a report containing the findings of the Secretary with respect to the assessment and inventory required under subsection (a).

SEC. 6003. Backlog Prevention.

(a)
Project Deauthorization.—
(1)
In general.— A water resources development project, or separable element of such a project, authorized for construction by this Act shall not be authorized after the last day of the 7-year period beginning on the date of enactment of this Act unless funds have been obligated for construction of such project during that period.
(2)
Identification of projects.— Not later than 60 days after the expiration of the 7-year period referred to in paragraph (1), the Secretary shall submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a report that identifies the projects deauthorized under paragraph (1).
(b)
Report to Congress.— Not later than 60 days after the expiration of the 12-year period beginning on the date of enactment of this Act, the Secretary shall submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives, and make available to the public, a report that contains—
(1)
a list of any water resources development projects authorized by this Act for which construction has not been completed during that period;
(2)
a description of the reasons the projects were not completed;
(3)
a schedule for the completion of the projects based on expected levels of appropriations; and
(4)
a 5-year and 10-year projection of construction backlog and any recommendations to Congress regarding how to mitigate current problems and the backlog.

SEC. 6004. Deauthorizations.

(a)
In General.—
(1)
Walnut creek (pacheco creek), california.— The portions of the project for flood protection on Walnut Creek, California, constructed under section 203 of the Flood Control Act of 1960 (Public Law 86–645; 74 Stat. 488), consisting of the Walnut Creek project from Sta 0+00 to Sta 142+00 and the upstream extent of the Walnut Creek project along Pacheco Creek from Sta 0+00 to Sta 73+50 are no longer authorized beginning on the date of enactment of this Act.
(2)
Walnut creek (san ramon creek), california.— The portion of the project for flood protection on Walnut Creek, California, constructed under section 203 of the Flood Control Act of 1960 (Public Law 86–645; 74 Stat. 488), consisting of the culvert constructed by the Department of the Army on San Ramon Creek from Sta 4+27 to Sta 14+27 is no longer authorized beginning on the date of enactment of this Act.
(3)
Eightmile river, connecticut.—
(A)
The portion of the project for navigation, Eightmile River, Connecticut, authorized by the first section of the Act of June 25, 1910 (36 Stat. 633, chapter 382) (commonly known as the “River and Harbor Act of 1910”), that begins at a point of the existing 8-foot channel limit with coordinates N701002.39, E1109247.73, thence running north 2 degrees 19 minutes 57.1 seconds east 265.09 feet to a point N701267.26, E1109258.52, thence running north 7 degrees 47 minutes 19.3 seconds east 322.32 feet to a point N701586.60, E1109302.20, thence running north 90 degrees 0 minutes 0 seconds east 65.61 to a point N701586.60, E1109367.80, thence running south 7 degrees 47 minutes 19.3 seconds west 328.11 feet to a point N701261.52, E1109323.34, thence running south 2 degrees 19 minutes 57.1 seconds west 305.49 feet to an end at a point N700956.28, E1109310.91 on the existing 8-foot channel limit, shall be reduced to a width of 65 feet and the channel realigned to follow the deepest available water.
(B)
The project referred to in subparagraph (A) beginning at a point N701296.72, E1109262.55 and running north 45 degrees 4 minutes 2.8 seconds west 78.09 feet to a point N701341.18, E1109217.98, thence running north 5 degrees 8 minutes 34.6 seconds east 180.14 feet to a point N701520.59, E1109234.13, thence running north 54 degrees 5 minutes 50.1 seconds east 112.57 feet to a point N701568.04, E1109299.66, thence running south 7 degrees 47 minutes 18.4 seconds west 292.58 feet to the point of origin; and the remaining area north of the channel realignment beginning at a point N700956.28, E1109310.91 thence running north 2 degrees 19 minutes 57.1 seconds east 305.49 feet west to a point N701261.52, E1109323.34 north 7 degrees 47 minutes 18.4 seconds east 328.11 feet to a point N701586.60, E1109367.81 thence running north 90 degrees 0 minutes 0 seconds east 7.81 feet to a point N701586.60, E1109375.62 thence running south 5 degrees 8 minutes 34.6 seconds west 626.29 feet to a point N700962.83, E1109319.47 thence south 52 degrees 35 minutes 36.5 seconds 10.79 feet to the point of origin is no longer authorized beginning on the date of enactment of this Act.
(4)
Hillsborough (hillsboro) bay and river, florida.— The portions of the project for navigation, Hillsborough (Hillsboro) Bay and River, Florida, authorized by the Act of March 3, 1899 (30 Stat. 1126; chapter 425), that extend on either side of the Hillsborough River from the Kennedy Boulevard bridge to the mouth of the river that cause the existing channel to exceed 100 feet in width are no longer authorized beginning on the date of enactment of this Act.
(5)
Kahului wastewater reclamation facility, maui, hawaii.— The project authorized pursuant to section 14 of the Flood Control Act of 1946 (33 U.S.C. 701r) to provide shoreline protection for the Kahului Wastewater Reclamation Facility, located on the Island of Maui in the State of Hawaii is no longer authorized beginning on the date of enactment of this Act.
(6)
Lucas-berg pit, illinois waterway and grant calumet river, illinois.— The portion of the project for navigation, Illinois Waterway and Grand Calumet River, Illinois, authorized by the first section of the Act of July 24, 1946 (60 Stat. 636; chapter 595), that consists of the Lucas-Berg Pit confined disposal facility, Illinois is no longer authorized beginning on the date of enactment of this Act.
(7)
Port of iberia, louisiana.— Section 1001(25) of the Water Resources Development Act of 2007 (121 Stat. 1053) is amended by striking “ ; except that” and all that follows before the period at the end.
(8)
Rockland harbor, maine.— The project for navigation, Rockland Harbor, Maine, authorized by the Act of June 3, 1896 (29 Stat. 202; chapter 314), and described as follows is no longer authorized beginning on the date of enactment of this Act:
(A)
Beginning at the point in the 14-foot turning basin limit with coordinates N162,927.61, E826,210.16.
(B)
Thence running north 45 degrees 45 minutes 15.6 seconds east 287.45 feet to a point N163,128.18, E826,416.08.
(C)
Thence running south 13 degrees 17 minutes 53.3 seconds east 129.11 feet to a point N163,002.53, E826,445.77.
(D)
Thence running south 45 degrees 45 minutes 18.4 seconds west 221.05 feet to a point N162,848.30, E826,287.42.
(E)
Thence running north 44 degrees 14 minutes 59.5 seconds west 110.73 feet to the point of origin.
(9)
Thomaston harbor, georges river, maine.— The portion of the project for navigation, Georges River, Maine (Thomaston Harbor), authorized by the first section of the Act of June 3, 1896 (29 Stat. 215, chapter 314), and modified by section 317 of the Water Resources Development Act of 2000 (Public Law 106–541; 114 Stat. 2604), that lies northwesterly of a line commencing at point N87,220.51, E321,065.80 thence running northeasterly about 125 feet to a point N87,338.71, E321,106.46 is no longer authorized beginning on the date of enactment of this Act.
(10)
Corsica river, queen anne’s county, maryland.— The portion of the project for improving the Corsica River, Maryland, authorized by the first section of the Act of July 25, 1912 (37 Stat. 205; chapter 253), and described as follows is no longer authorized beginning on the date of enactment of this Act: Approximately 2,000 feet of the eastern section of the project channel extending from—
(A)
centerline station 0+000 (coordinates N506350.60, E1575013.60); to
(B)
station 2+000 (coordinates N508012.39, E1574720.18).
(11)
Goose creek, somerset county, maryland.— The project for navigation, Goose Creek, Somerset County, Maryland, carried out pursuant to section 107 of the Rivers and Harbor Act of 1960 (33 U.S.C. 577), is realigned as follows: Beginning at Goose Creek Channel Geometry Centerline of the 60-foot-wide main navigational ship channel, Centerline Station No. 0+00, coordinates North 157851.80, East 1636954.70, as stated and depicted on the Condition Survey Goose Creek, Sheet 1 of 1, prepared by the United States Army Corps of Engineers, Baltimore District, July 2003; thence departing the aforementioned centerline traveling the following courses and distances: S. 64 degrees 49 minutes 06 seconds E., 1583.82 feet to a point, on the outline of said 60-foot-wide channel thence binding on said out-line the following four courses and distances: S. 63 degrees 26 minutes 06 seconds E., 1460.05 feet to a point, thence; N. 50 degrees 38 minutes 26 seconds E., 973.28 feet to a point, thence; N. 26 degrees 13 minutes 09 seconds W., 240.39 feet to a point on the Left Toe of the 60-foot-wide main navigational channel at computed Centerline Station No. 42+57.54, coordinates North 157357.84, East 1640340.23. Geometry Left Toe of the 60-foot-wide main navigational ship channel, Left Toe Station No. 0+00, coordinates North 157879.00, East 1636967.40, as stated and depicted on the Condition Survey Goose Creek, Sheet 1 of 1, prepared by the United States Army Corps of Engineers, Baltimore District, August 2010; thence departing the aforementioned centerline traveling the following courses and distances: S. 64 degrees 49 minutes 12 seconds E., 1583.91 feet to a point, on the outline of said 60-foot-wide channel thence binding on said out-line the following eight courses and distances: S. 63 degrees 25 minutes 38 seconds E., 1366.25 feet to a point, thence; N. 83 degrees 36 minutes 24 seconds E., 125.85 feet to a point, thence; N. 50 degrees 38 minutes 26 seconds E., 805.19 feet to a point, thence; N. 12 degrees 12 minutes 29 seconds E., 78.33 feet to a point thence; N. 26 degrees 13 minutes 28 seconds W., 46.66 feet to a point thence; S. 63 degrees 45 minutes 41 seconds W., 54.96 feet to a point thence; N. 26 degrees 13 minutes 24 seconds W., 119.94 feet to a point on the Left Toe of the 60-foot-wide main navigational channel at computed Centerline Station No. 41+81.10, coordinates North 157320.30, East 1640264.00. Geometry Right Toe of the 60-foot-wide main navigational ship channel, Right Toe Station No. 0+00, coordinates North 157824.70, East 1636941.90, as stated and depicted on the Condition Survey Goose Creek, Sheet 1 of 1, prepared by the United States Army Corps of Engineers, Baltimore District, August 2010; thence departing the aforementioned centerline traveling the following courses and distances: S. 64 degrees 49 minutes 06 seconds E., 1583.82 feet to a point, on the outline of said 60-foot-wide channel thence binding on said out-line the following six courses and distances: S. 63 degrees 25 minutes 47 seconds E., 1478.79 feet to a point, thence; N. 50 degrees 38 minutes 26 seconds E., 1016.69 feet to a point, thence; N. 26 degrees 14 minutes 49 seconds W., 144.26 feet to a point, thence; N. 63 degrees 54 minutes 03 seconds E., 55.01 feet to a point thence; N. 26 degrees 12 minutes 08 seconds W., 120.03 feet to a point a point on the Right Toe of the 60-foot-wide main navigational channel at computed Centerline Station No. 43+98.61, coordinates North 157395.40, East 1640416.50.
(12)
Lower thoroughfare, deal island, maryland.— The portion of the project for navigation, Lower Thoroughfare, Maryland, authorized by the Act of June 25, 1910 (36 Stat. 639, chapter 382) (commonly known as the “River and Harbor Act of 1910”), that begins at Lower Thoroughfare Channel Geometry Centerline of the 60-foot-wide main navigational ship channel, Centerline Station No. 44+88, coordinates North 170435.62, East 1614588.93, as stated and depicted on the Condition Survey Lower Thoroughfare, Deal Island, Sheet 1 of 3, prepared by the United States Army Corps of Engineers, Baltimore District, August 2010; thence departing the aforementioned centerline traveling the following courses and distances: S. 42 degrees 20 minutes 44 seconds W., 30.00 feet to a point, on the outline of said 60-foot-wide channel thence binding on said out-line the following four courses and distances: N. 64 degrees 08 minutes 55 seconds W., 53.85 feet to a point, thence; N. 42 degrees 20 minutes 43 seconds W., 250.08 feet to a point, thence; N. 47 degrees 39 minutes 03 seconds E., 20.00 feet to a point, thence; S. 42 degrees 20 minutes 44 seconds E., 300.07 feet to a point binding on the Left Toe of the 60-foot-wide main navigational channel at computed Centerline Station No. 43+92.67, coordinates North 170415.41, 1614566.76; thence; continuing with the aforementioned centerline the following courses and distances: S. 42 degrees 20 minutes 42 seconds W., 30.00 feet to a point, on the outline of said 60-foot-wide channel thence binding on said out-line the following four courses and distances: N. 20 degrees 32 minutes 06 seconds W., 53.85 feet to a point, thence; N. 42 degrees 20 minutes 49 seconds W., 250.08 feet to a point, thence; S. 47 degrees 39 minutes 03 seconds W., 20.00 feet to a point, thence; S. 42 degrees 20 minutes 46 seconds E., 300.08 feet to a point binding on the Left Toe of the 60-foot-wide main navigational channel at computed Centerline Station No. 43+92.67, coordinates North 170415.41, 1614566.76 is no longer authorized beginning on the date of enactment of this Act.
(13)
Gloucester harbor and annisquam river, massachusetts.— The portions of the project for navigation, Gloucester Harbor and Annisquam River, Massachusetts, authorized by section 2 of the Act of March 2, 1945 (59 Stat. 12; chapter 19), consisting of an 8-foot anchorage area in Lobster Cove, and described as follows are no longer authorized beginning on the date of enactment of this Act:
(A)
Beginning at a bend along the easterly limit of the existing project, N3063230.31, E878283.77, thence running northwesterly about 339 feet to a point, N3063478.86, E878053.83, thence running northwesterly about 281 feet to a bend on the easterly limit of the existing project, N3063731.88, E877932.54, thence running southeasterly about 612 feet along the easterly limit of the existing project to the point of origin.
(B)
Beginning at a bend along the easterly limit of the existing project, N3064065.80, E878031.45, thence running northwesterly about 621 feet to a point, N3064687.05, E878031.13, thence running southwesterly about 122 feet to a point, N3064686.98, E877908.85, thence running southeasterly about 624 feet to a point, N3064063.31, E877909.17, thence running southwesterly about 512 feet to a point, N3063684.73, E877564.56, thence running about 741 feet to a point along the westerly limit of the existing project, N3063273.98, E876947.77, thence running northeasterly about 533 feet to a bend along the westerly limit of the existing project, N3063585.62, E877380.63, thence running about 147 feet northeasterly to a bend along the westerly limit of the project, N3063671.29, E877499.63, thence running northeasterly about 233 feet to a bend along the westerly limit of the existing project, N3063840.60, E877660.29, thence running about 339 feet northeasterly to a bend along the westerly limit of the existing project, N3064120.34, E877852.55, thence running about 573 feet to a bend along the westerly limit of the existing project, N3064692.98, E877865.04, thence running about 113 feet to a bend along the northerly limit of the existing project, N3064739.51, E877968.31, thence running 145 feet southeasterly to a bend along the northerly limit of the existing project, N3064711.19, E878110.69, thence running about 650 feet along the easterly limit of the existing project to the point of origin.
(14)
Clatsop county diking district no. 10, karlson island, oregon.— The Diking District No. 10, Karlson Island portion of the project for raising and improving existing levees in Clatsop County, Oregon, authorized by section 5 of the Act of June 22, 1936 (49 Stat. 1590) is no longer authorized beginning on the date of enactment of this Act.
(15)
Numberg dike no. 34 leveed area, clatsop county diking district no. 13, clatsop county, oregon (walluski-youngs).— The Numberg Dike No. 34 leveed area, Clatsop County Diking District, No. 13, Walluski River and Youngs River dikes, portion of the project for raising and improving existing levees in Clatsop County, Oregon, authorized by section 5 of the Act of June 22, 1936 (49 Stat. 1590) is no longer authorized beginning on the date of enactment of this Act.
(16)
East fork of trinity river, texas.— The portion of the project for flood protection on the East Fork of the Trinity River, Texas, authorized by section 203 of the Flood Control Act of 1962 (76 Stat. 1185), that consists of the 2 levees identified as Kaufman County Levees K5E and K5W is no longer authorized beginning on the date of enactment of this Act.
(17)
Burnham canal, wisconsin.— The portion of the project for navigation, Milwaukee Harbor Project, Milwaukee, Wisconsin, known as the Burnham Canal, authorized by the first section of the Act of March 3, 1843 (5 Stat. 619; chapter 85), and described as follows is no longer authorized beginning on the date of enactment of this Act:
(A)
Beginning at channel point #415a N381768.648, E2524554.836, a distance of about 170.58 feet.
(B)
Thence running south 53 degrees 43 minutes 41 seconds west to channel point #417 N381667.728, E2524417.311, a distance of about 35.01 feet.
(C)
Thence running south 34 degrees 10 minutes 40 seconds west to channel point #501 N381638.761, E2524397.639, a distance of about 139.25 feet.
(D)
Thence running south 34 degrees 10 minutes 48 seconds west to channel point #503 N381523.557, E2524319.406, a distance of about 235.98 feet.
(E)
Thence running south 32 degrees 59 minutes 13 seconds west to channel point #505 N381325.615, E2524190.925, a distance of about 431.29 feet.
(F)
Thence running south 32 degrees 36 minutes 05 seconds west to channel point #509 N380962.276, E2523958.547, a distance of about 614.52 feet.
(G)
Thence running south 89 degrees 05 minutes 00 seconds west to channel point #511 N380952.445, E2523344.107, a distance of about 74.68 feet.
(H)
Thence running north 89 degrees 04 minutes 59 seconds west to channel point #512 N381027.13, E2523342.91, a distance of about 533.84 feet.
(I)
Thence running north 89 degrees 05 minutes 00 seconds east to channel point #510 N381035.67, E2523876.69, a distance of about 47.86 feet.
(J)
Thence running north 61 degrees 02 minutes 07 seconds east to channel point #508 N381058.84, E2523918.56, a distance of about 308.55 feet.
(K)
Thence running north 36 degrees 15 minutes 29 seconds east to channel point #506 N381307.65, E2524101.05, a distance of about 199.98 feet.
(L)
Thence running north 32 degrees 59 minutes 12 seconds east to channel point #504 N381475.40, E2524209.93, a distance of about 195.14 feet.
(M)
Thence running north 26 degrees 17 minutes 22 seconds east to channel point #502 N381650.36, E2524296.36, a distance of about 81.82 feet.
(N)
Thence running north 88 degrees 51 minutes 05 seconds west to channel point #419 N381732.17, E2524294.72, a distance of about 262.65 feet.
(O)
Thence running north 82 degrees 01 minutes 02 seconds east to channel point #415a, the point of origin.
(18)
Manitowoc harbor, wisconsin.— The portion of the project for navigation, Manitowoc River, Manitowoc, Wisconsin, authorized by the Act of August 30, 1852 (10 Stat. 58; chapter 104), and described as follows is no longer authorized beginning on the date of enactment of this Act: The triangular area bound by—
(A)
44.09893383N and 087.66854912W;
(B)
44.09900535N and 087.66864372W; and
(C)
44.09857884N and 087.66913123W.
(b)
Seward Waterfront, Seward, Alaska.—
(1)
In general.— Subject to paragraph (2), the portion of the project for navigation, Seward Harbor, Alaska, identified as Tract H, Seward Original Townsite, Waterfront Park Replat, Plat No 2012–4, Seward Recording District, shall not be subject to navigation servitude beginning on the date of enactment of this Act.
(2)
Entry by federal government.— The Federal Government may enter upon the property referred to in paragraph (1) to carry out any required operation and maintenance of the general navigation features of the project referred to in paragraph (1).
(c)
Port of Hood River, Oregon.—
(1)
Extinguishment of portions of existing flowage easement.— With respect to the properties described in paragraph (2), beginning on the date of enactment of this Act, the flowage easement identified as Tract 1200E–6 on the Easement Deed recorded as Instrument No. 740320 is extinguished above elevation 79.39 feet (NGVD 29) the Ordinary High Water Line.
(2)
Affected properties.— The properties referred to in paragraph (1), as recorded in Hood River County, Oregon, are as follows:
(A)
Instrument Number 2010–1235.
(B)
Instrument Number 2010–02366.
(C)
Instrument Number 2010–02367.
(D)
Parcel 2 of Partition Plat #2011–12P.
(E)
Parcel 1 of Partition Plat 2005–26P.
(3)
Federal liabilities; cultural, environmental, and other regulatory reviews.—
(A)
Federal liability.— The United States shall not be liable for any injury caused by the extinguishment of the easement under this subsection.
(B)
Cultural and environmental regulatory actions.— Nothing in this subsection establishes any cultural or environmental regulation relating to the properties described in paragraph (2).
(4)
Effect on other rights.— Nothing in this subsection affects any remaining right or interest of the Corps of Engineers in the properties described in paragraph (2).

SEC. 6005. Land Conveyances.

(a)
Oakland Inner Harbor Tidal Canal, California.— Section 3182(b)(1) of the Water Resources Development Act of 2007 (Public Law 110–114; 121 Stat. 1165) is amended—
(1)
in subparagraph (A) by inserting “ , or to a multicounty public entity that is eligible to hold title to real property” after “ To the city of Oakland”; and
(2)
in subparagraphs (B) and (C) by inserting “ multicounty public entity or other” before “ public entity”.
(b)
St. Charles County, Missouri, Land Exchange.—
(1)
Definitions.— In this subsection:
(A)
Federal land.— The term “Federal land” means approximately 84 acres of land, as identified by the Secretary, that is a portion of the approximately 227 acres of land leased from the Corps of Engineers by Ameren Corporation for the Portage Des Sioux Power Plant in St. Charles County, Missouri (Lease No. DA-23-065–CIVENG–64–651, Pool 26).
(B)
Non-federal land.— The term “non-Federal land” means the approximately 68 acres of land owned by Ameren Corporation in Jersey County, Illinois, contained within the north half of section 23, township 6 north, range 11 west of the third principal meridian.
(2)
Land exchange.— On conveyance by Ameren Corporation to the United States of all right, title, and interest in and to the non-Federal land, the Secretary shall convey to Ameren Corporation all right, title, and interest of the United States in and to the Federal land.
(3)
Specific conditions.—
(A)
Deeds.—
(i)
Deed to non-federal land.— The Secretary may only accept conveyance of the non-Federal land by warranty deed, as determined acceptable by the Secretary.
(ii)
Deed to federal land.— The Secretary shall convey the Federal land to Ameren Corporation by quitclaim deed.
(B)
Cash payment.— If the appraised fair market value of the Federal land, as determined by the Secretary, exceeds the appraised fair market value of the non-Federal land, as determined by the Secretary, Ameren Corporation shall make a cash payment to the United States reflecting the difference in the appraised fair market values.
(c)
Tulsa Port of Catoosa, Rogers County, Oklahoma, Land Exchange.—
(1)
Definitions.— In this subsection:
(A)
Federal land.— The term “Federal land” means the approximately 87 acres of land situated in Rogers County, Oklahoma, contained within United States Tracts 413 and 427 and acquired for the McClellan-Kerr Arkansas Navigation System.
(B)
Non-federal land.— The term “non-Federal land” means the approximately 34 acres of land situated in Rogers County, Oklahoma, and owned by the Tulsa Port of Catoosa that lie immediately south and east of the Federal land.
(2)
Land exchange.— On conveyance by the Tulsa Port of Catoosa to the United States of all right, title, and interest in and to the non-Federal land, the Secretary shall convey to the Tulsa Port of Catoosa all right, title, and interest of the United States in and to the Federal land.
(3)
Specific conditions.—
(A)
Deeds.—
(i)
Deed to non-federal land.— The Secretary may only accept conveyance of the non-Federal land by warranty deed, as determined acceptable by the Secretary.
(ii)
Deed to federal land.— The Secretary shall convey the Federal land to the Tulsa Port of Catoosa by quitclaim deed and subject to any reservations, terms, and conditions the Secretary determines necessary to allow the United States to operate and maintain the McClellan-Kerr Arkansas River Navigation System.
(iii)
Cash payment.— If the appraised fair market value of the Federal land, as determined by the Secretary, exceeds the appraised fair market value of the non-Federal land, as determined by the Secretary, the Tulsa Port of Catoosa shall make a cash payment to the United States reflecting the difference in the appraised fair market values.
(d)
Hammond Boat Basin, Warrenton, Oregon.—
(1)
Definitions.— In this subsection:
(A)
City.— The term “City” means the city of Warrenton, located in Clatsop County, Oregon.
(B)
Map.— The term “map” means the map contained in Exhibit A of Department of the Army Lease No. DACW57–1–88–0033 (or a successor instrument).
(2)
Conveyance authority.— Subject to the provisions of this subsection, the Secretary shall convey to the City by quitclaim deed, and without consideration, all right, title, and interest of the United States in and to the parcel of land described in paragraph (3).
(3)
Description of land.—
(A)
In general.— Except as provided in subparagraph (B), the land referred to in paragraph (2) is the parcel totaling approximately 59 acres located in the City, together with any improvements thereon, including the Hammond Marina (as described in the map).
(B)
Exclusion.— The land referred to in paragraph (2) shall not include the site provided for the fisheries research support facility of the National Marine Fisheries Service.
(C)
Availability of map.— The map shall be on file in the Portland District Office of the Corps of Engineers.
(4)
Terms and conditions.— As a condition of the conveyance under this subsection, the Secretary may impose a requirement that the City assume full responsibility for operating and maintaining the channel and the breakwater.
(5)
Reversion.— If the Secretary determines that the land conveyed under this subsection ceases to be owned by the public, all right, title, and interest in and to the land shall revert, at the discretion of the Secretary, to the United States.
(6)
Deauthorization.— After the land is conveyed under this subsection, the land shall no longer be a portion of the project for navigation, Hammond Small Boat Basin, Oregon, authorized by section 107 of the Rivers and Harbor Act of 1960 (33 U.S.C. 577).
(e)
Craney Island Dredged Material Management Area, Portsmouth, Virginia.—
(1)
In general.— Subject to the conditions described in this subsection, the Secretary may convey to the Commonwealth of Virginia, by quitclaim deed and without consideration, all right, title, and interest of the United States in and to 2 parcels of land situated within the project for navigation, Craney Island Eastward Expansion, Norfolk Harbor and Channels, Hampton Roads, Virginia, authorized by section 1001(45) of the Water Resources Development Act of 2007 (Public Law 110–114; 121 Stat. 1057), together with any improvements thereon.
(2)
Lands to be conveyed.—
(A)
In general.— The 2 parcels of land to be conveyed under this subsection include a parcel consisting of approximately 307.82 acres of land and a parcel consisting of approximately 13.33 acres of land, both located along the eastern side of the Craney Island Dredged Material Management Area in Portsmouth, Virginia.
(B)
Use.— The 2 parcels of land described in subparagraph (A) may be used by the Commonwealth of Virginia exclusively for the purpose of port expansion, including the provision of road and rail access and the construction of a shipping container terminal.
(3)
Reversion.— If the Secretary determines that the land conveyed under this subsection ceases to be owned by the public or is used for any purpose that is inconsistent with paragraph (2), all right, title, and interest in and to the land shall revert, at the discretion of the Secretary, to the United States.
(f)
City of Asotin, Washington.—
(1)
In general.— The Secretary shall convey to the city of Asotin, Asotin County, Washington, without monetary consideration, all right, title, and interest of the United States in and to the land described in paragraph (3).
(2)
Reversion.— If the land transferred under this subsection ceases at any time to be used for a public purpose, the land shall revert to the United States.
(3)
Description.— The land to be conveyed to the city of Asotin, Washington, under this subsection are—
(A)
the public ball fields designated as Tracts 1503, 1605, 1607, 1609, 1611, 1613, 1615, 1620, 1623, 1624, 1625, 1626, and 1631; and
(B)
other leased areas designated as Tracts 1506, 1522, 1523, 1524, 1525, 1526, 1527, 1529, 1530, 1531, and 1563.
(g)
Generally Applicable Provisions.—
(1)
Survey to obtain legal description.— The exact acreage and the legal description of any real property to be conveyed under this section shall be determined by a survey that is satisfactory to the Secretary.
(2)
Applicability of property screening provisions.— Section 2696 of title 10, United States Code, shall not apply to any conveyance under this section.
(3)
Additional terms and conditions.— The Secretary may require that any conveyance under this section be subject to such additional terms and conditions as the Secretary considers necessary and appropriate to protect the interests of the United States.
(4)
Costs of conveyance.— An entity to which a conveyance is made under this section shall be responsible for all reasonable and necessary costs, including real estate transaction and environmental documentation costs, associated with the conveyance.
(5)
Liability.— An entity to which a conveyance is made under this section shall hold the United States harmless from any liability with respect to activities carried out, on or after the date of the conveyance, on the real property conveyed. The United States shall remain responsible for any liability with respect to activities carried out, before such date, on the real property conveyed.
(h)
Release of Use Restrictions.— Notwithstanding any other provision of law, the Tennessee Valley Authority shall, without monetary consideration, grant releases from real estate restrictions established pursuant to section 4(k)(b) of the Tennessee Valley Authority Act of 1933 (16 U.S.C. 831c(k)(b)) with respect to tracts of land identified in section 4(k)(b) of that Act, subject to the condition that such releases shall be granted in a manner consistent with applicable Tennessee Valley Authority policies.