§9.11. Mitigation. — Inbound Citations

44 C.F.R. § 9.11

Cited by 13 regulations in release Current.

Citations to 44 U.S.C. § 9.11 as a whole

  • (5) An individual or family shall not be housed in a floodplain or wetland (except in existing resources) unless the Regional Administrator has complied with the provisions of § 9.11 to minimize harm to and within floodplains and wetlands. The following provisions shall be substituted for the provisions of § 9.11(d) for temporary housing units:
    (i) No temporary housing unit may be placed unless it is elevated to the fullest extent practicable up to the base flood elevation and adequately anchored.
    (ii) No temporary housing unit may be placed if such placement is inconsistent with the criteria of the NFIP (44 CFR parts 59 and 60) or any more restrictive Federal, State, or local floodplain management standard. Such standards may require elevation to the base flood elevation in the absence of a variance.
    (iii) Temporary housing units shall be elevated on open works (walls, columns, piers, piles, etc.) rather than on fill where practicable.
    (A) Where appropriate, integrate all of its proposed actions in placing temporary housing units for temporary housing in floodplains into existing flood warning or preparedness plans and ensure that available flood warning time is reflected;
    (B) Provide adequate access and egress to and from the proposed site of the temporary housing unit; and
  • (5) Identify the steps necessary to minimize, restore, preserve and enhance in accordance with § 9.11. For disposals, this analysis shall address all four of these components of mitigation where unimproved property is involved, but shall focus on minimization through elevation or floodproofing and restoration of natural values where improved property is involved;
  • (4) The mitigation responsibilities as set out in § 9.11;
  • (4) The mitigation responsibilities as set out in § 9.11;
  • (1) Under §§ 9.2 and 9.6 through 9.13 and 9.15 where a direction is given to the Agency, it is the responsibility of the Regional Administrator.
  • (d) The Regional Administrator shall apply steps 1, 4, 5, and 8 of the decision-making process (§§ 9.7, 9.10, and 9.11) to repairs under section 406 of the Robert T. Stafford Disaster Relief and Emergency Assistance Act of 1988, Public Law 93-288, as amended, between $18,000 and $91,000. Such $18,000 and $91,000 amounts will be adjusted annually to reflect changes in the Consumer Price Index for All Urban Consumers published by the Department of Labor. For any action which is excepted from the actions listed below (except as otherwise provided in this section regarding other categories of partial or total exclusion), the full 8-step process applies (See § 9.6). The Regional Administrator may also require certain other portions of the decision-making process to be carried out for individual actions as is deemed necessary. Steps 1, 4, 5, and 8 of the decision-making process apply to actions under section 406 of the Stafford Act referenced above except for:
    (1) Actions in a floodway or coastal high hazard area; or
    (2) New construction, substantial improvement, or repairs to address substantial damage of structures or facilities; or
    (3) Facilities or structures which have previously sustained damage from flooding due to a major disaster or emergency or on which a flood insurance claim has been paid; or
  • (b) Except as otherwise provided in § 9.5 regarding categories of partial or total exclusion when proposing an action, the Agency shall apply the 8-step decision-making process. FEMA shall:
    (1) Determine whether the proposed action is located in a floodplain and/or a wetland as established by § 9.7; and whether it has the potential to affect or be affected by a floodplain or wetland (see § 9.7);
    (2) Notify the public at the earliest possible time of the intent to carry out an action in a floodplain or wetland, and involve the affected and interested public in the decision-making process (see § 9.8);
    (3) Identify and evaluate practicable alternatives to locating the proposed action in a floodplain or wetland (including alternative sites, actions, natural features, nature-based approaches, and the “no action” option) (see § 9.9). If a practicable alternative exists outside the floodplain or wetland FEMA must locate the action at the alternative site.
    (4) Identify the potential direct and indirect impacts associated with the occupancy or modification of floodplains and wetlands and the potential direct and indirect support of floodplain and wetland development that could result from the proposed action (see § 9.10);
    (5) Minimize the potential adverse impacts to or within floodplains and wetlands and minimize support of floodplain and wetland development identified under Step 4. Restore and preserve the natural and beneficial values served by floodplains, and preserve and enhance the natural and beneficial values served by wetlands. Integrate nature-based approaches where appropriate (see § 9.11);
    (6) Reevaluate the proposed action to determine first, if it is still practicable in light of its exposure to flood hazards, the extent to which it will aggravate hazards to others, and its potential to disrupt floodplain and wetland values; and second, if alternatives preliminarily rejected at Step 3 are practicable in light of the information gained in Steps 4 and 5. FEMA shall not act in a floodplain or wetland unless it is the only practicable location (see § 9.9);
    (7) Prepare and provide the public with a finding and public explanation of any final decision that the floodplain or wetland is the only practicable alternative (see § 9.12); and
    (8) Review the implementation and post-implementation phases of the proposed action to ensure that the requirements stated in § 9.11 are fully implemented. Oversight responsibility shall be integrated into existing processes.
  • (1) The Agency shall obtain enough information so that it can fulfill the requirements in this part to:
    (i) Avoid Federal action in floodplain and wetland locations unless they are the only practicable alternatives; and
    (2) In all cases, FEMA shall determine whether the proposed action is located in a floodplain or wetland. Information about the floodplain as established by paragraph (c) of this section and the location of floodways and coastal high hazard areas may also be needed to comply with this part, especially § 9.11.
    (3) The following additional current and future flooding characteristics may be identified by the Regional Administrator as applicable:
    (i) Velocity of floodwater;
    (ii) Rate of rise of floodwater;
    (iii) Duration of flooding;
    (iv) Available warning and evacuation time and routes;
    (A) Levees;
    (B) Erosion;
    (C) Subsidence;
    (D) Sink holes;
    (E) Ice jams;
    (F) Debris load;
    (G) Pollutants;
    (H) Wave heights;
    (I) Groundwater flooding;
  • (e) Upon determination of the impact of the proposed action to or within the floodplain or wetland and of what measures are necessary to comply with the requirement to minimize harm to and within floodplains and wetlands (§ 9.11), FEMA shall:
    (i) The action is still practicable at a floodplain or wetland site, considering the flood risk and the ensuing disruption of natural values;
    (ii) The floodplain or wetland site is the only practicable alternative;
    (iii) The scope of the action can be limited to increase the practicability of previously rejected non-floodplain or wetland sites and alternative actions; and
    (2) Take no action in a floodplain unless the importance of the floodplain site clearly outweighs the requirements to:
    (i) Avoid direct or indirect support of floodplain development;
    (ii) Reduce the risk of flood loss;
    (iii) Minimize the impact of floods on human safety, health and welfare; and
    (3) Take no action in a wetland unless the importance of the wetland site clearly outweighs the requirements to:
    (i) Avoid the destruction or modification of the wetlands;
    (ii) Avoid direct or indirect support of new construction in wetlands;
    (iii) Minimize the destruction, loss or degradation of wetlands; and
    (4) In carrying out this balancing process, give the factors in paragraphs (e)(2) and (3) of this section great weight.
    (5) Choose the “no action” alternative where there are no practicable alternative actions or sites and where the floodplain or wetland is not itself a practicable alternative. In making the assessment of whether a floodplain or wetland location is itself a practicable alternative, the practicability of the floodplain or wetland location shall be balanced against the practicability of not carrying out the action at all. That is, even if there is no practicable alternative outside of the floodplain or wetland, the floodplain or wetland itself must be a practicable location in order for the action to be carried out there. To be a practicable location, the importance of carrying out the action must clearly outweigh the requirements of the Orders listed in paragraphs (e)(2) and (e)(3) of this section. Unless the importance of carrying out the action clearly outweighs those requirements, the “no action” alternative shall be selected.

Citations to §9.11(c)

Citations to §9.11(d)

  • (5) An individual or family shall not be housed in a floodplain or wetland (except in existing resources) unless the Regional Administrator has complied with the provisions of § 9.11 to minimize harm to and within floodplains and wetlands. The following provisions shall be substituted for the provisions of § 9.11(d) for temporary housing units:
    (i) No temporary housing unit may be placed unless it is elevated to the fullest extent practicable up to the base flood elevation and adequately anchored.
    (ii) No temporary housing unit may be placed if such placement is inconsistent with the criteria of the NFIP (44 CFR parts 59 and 60) or any more restrictive Federal, State, or local floodplain management standard. Such standards may require elevation to the base flood elevation in the absence of a variance.
    (iii) Temporary housing units shall be elevated on open works (walls, columns, piers, piles, etc.) rather than on fill where practicable.
    (A) Where appropriate, integrate all of its proposed actions in placing temporary housing units for temporary housing in floodplains into existing flood warning or preparedness plans and ensure that available flood warning time is reflected;