§3273.19. What are the bonding requirements for a site license?

43 C.F.R. § 3273.19

(a)
For an electrical generation facility, the facility operator must submit a surety or personal bond to BLM for at least $100,000 that meets the requirements of subpart 3214.BLM may increase the required bond amount. See subparts 3214 and 3215 for additional details on bonding procedures.
(b)
For a direct use facility, the facility operator must submit a surety or personal bond to BLM that meets the requirements of subpart 3214 in an amount BLM will specify.
(c)
The bond's terms must cover compliance with the requirements of § 3200.4.
(d)
Until BLM approves your bond, do not start construction, testing, or any other activity that would disturb the surface.
Notes, amendments, and revision history

Authority

Authority: 30 U.S.C. 1001-1028; 43 U.S.C. 1701 et seq.; and Pub. L. 109-58.

Source

Source: 72 FR 24400, May 2, 2007, unless otherwise noted.