Procedures and timeframes for identifying and repairing components from which leaks are detected, including:
(B)
Timeframes for inspecting and repairing leaking components that are difficult-to-monitor, unsafe-to-monitor, or require source shutdown, to be no later than the next required monitoring event, as noted in
paragraphs (c)(1)(v)(B)(1) through (3) of this section:
(1) If using Method 21, fugitive emissions components that cannot be monitored without elevating the monitoring personnel more than 2 meters above the surface may be designated as difficult-to-monitor and must meet the specifications in paragraphs (c)(1)(v)(B)(1)(i) through (iv) of this section:
(i) For all fugitive emissions components designated difficult-to-monitor, a written plan must be developed and incorporated into the fugitive emissions monitoring plan.
(ii) The plan must include the identification and location of each fugitive emissions component designated difficult-to-monitor.
(iii) The plan must include an explanation of why each fugitive emissions component designated as difficult-to-monitor is difficult-to-monitor.
(iv) The plan must include a schedule for monitoring the difficult-to-monitor fugitive emissions components at least once per calendar year and a schedule for repairing such fugitive emissions components according to paragraph (c)(1)(v)(B)(3) of this section;
(2) Fugitive emissions components that cannot be monitored because monitoring personnel would be exposed to an immediate danger while conducting a monitoring survey may be designated as unsafe-to-monitor and must meet the specification in paragraphs (c)(1)(v)(B)(2)(i) through (iv) of this section:
(i) A written plan must be developed for all of the fugitive emissions components designated unsafe-to-monitor and incorporated into the fugitive emissions monitoring plan;
(ii) The plan must include the identification and location of each fugitive emissions component designated unsafe-to-monitor.
(iii) The plan must include an explanation of why each fugitive emissions component designated as unsafe-to-monitor is unsafe-to-monitor.
(iv) The plan must include a schedule for monitoring the unsafe-to-monitor fugitive emissions components as frequently as practicable during safe to inspect times and for repairing such fugitive emissions components according to paragraph (c)(1)(v)(B)(3) of this section;
(3) If the repair or replacement of a fugitive emissions component designated difficult-to-monitor or unsafe-to-monitor is technically infeasible; would require a vent blowdown, a compressor station shutdown, a well shutdown, or well shut-in; or would be unsafe to repair during operation of the unit, the repair or replacement must be completed during the next scheduled compressor station shutdown, well shutdown, or well shut-in; after a planned vent blowdown; or within 2 years, whichever is earlier; and