§285.712. What are the CVA's or project engineer's reporting requirements? — Inbound Citations
30 C.F.R. § 285.712
Statutory Authority
Cited by 2 regulations in release Current.
Citations to 30 U.S.C. § 285.712 as a whole
-
(a) Within 20 business days after receiving your proposed FDR, FIR, or project verification report, BSEE will review your submission. BSEE will deem your FDR, FIR, or project verification report submitted if BSEE determines it is sufficiently complete and accurate to fulfill the applicable requirements of § 285.701, § 285.702, or § 285.712.
Citations to §285.712(a)
-
(2) Your CVA submits the project verification report, as described in § 285.708(a)(5), including information required by § 285.708(b)(1), or interim report(s), as described in § 285.712(a) for facilities installed prior to commencing commercial operations;