§285.702. What must I include in my Fabrication and Installation Report?
30 C.F.R. § 285.702
Your Fabrication and Installation Report must describe how your facilities will be fabricated and installed in accordance with the design criteria identified in the Facility Design Report; your BOEM-approved SAP, COP, or GAP; and generally accepted industry standards and practices. Your Fabrication and Installation Report must demonstrate how your facilities will be fabricated and installed in a manner that conforms to your responsibilities listed in § 285.105(a). You must include the following items in your Fabrication and Installation Report:
You must submit your FIR to BSEE pursuant to § 285.110.
You must provide the location of records, as required in § 285.714(c).
If you are required to use a CVA, the FIR must include the following certification statement with accompanying justification: “The fabrication and installation of this structure has been certified by a BSEE-approved CVA to be in accordance with accepted engineering practices, the FDR, and the approved SAP, GAP, or COP, as applicable. The certified design and as-built plans and specifications will be on file at [provide location].”
Notes, amendments, and revision history
Amendments
[88 FR 6413, Jan. 31, 2023, as amended at 89 FR 42716, May 15, 2024]
Authority
Authority: 43 U.S.C. 1331 et seq.
Source
Source: 88 FR 6413, Jan. 31, 2023, unless otherwise noted.
Amendments
[88 FR 6413, Jan. 31, 2023, as amended at 89 FR 42716, May 15, 2024]