§285.702. What must I include in my Fabrication and Installation Report? — Inbound Citations
30 C.F.R. § 285.702
Statutory Authority
Cited by 7 regulations in release Current.
Citations to 30 U.S.C. § 285.702 as a whole
-
(a) Within 20 business days after receiving your proposed FDR, FIR, or project verification report, BSEE will review your submission. BSEE will deem your FDR, FIR, or project verification report submitted if BSEE determines it is sufficiently complete and accurate to fulfill the applicable requirements of § 285.701, § 285.702, or § 285.712.
Citations to §285.702(a)(8)
-
(2) Ensure Critical Safety Systems and Equipment are commissioned in accordance with the procedures identified in § 285.702(a)(8);
-
(6) Provide records documenting that Critical Safety Systems and Equipment are commissioned in accordance with the procedures identified in § 285.702(a)(8); and
Citations to §285.702(c)
-
(1) You submit information consistent with § 285.702(c) and (d) for facilities installed prior to commencing commercial operations;
-
(c) You must provide BSEE with the location of these records, as required in §§ 285.701(c) and (d), 285.702(c) and (d), 285.703(b), and 285.708(a)(5) and (7).
Citations to §285.702(d)
-
(1) You submit information consistent with § 285.702(c) and (d) for facilities installed prior to commencing commercial operations;
-
(c) You must provide BSEE with the location of these records, as required in §§ 285.701(c) and (d), 285.702(c) and (d), 285.703(b), and 285.708(a)(5) and (7).