§285.701. What must I include in my Facility Design Report? — Inbound Citations
30 C.F.R. § 285.701
Statutory Authority
Cited by 3 regulations in release Current.
Citations to 30 U.S.C. § 285.701 as a whole
-
(a) Within 20 business days after receiving your proposed FDR, FIR, or project verification report, BSEE will review your submission. BSEE will deem your FDR, FIR, or project verification report submitted if BSEE determines it is sufficiently complete and accurate to fulfill the applicable requirements of § 285.701, § 285.702, or § 285.712.
Citations to §285.701(c)
-
(c) You must provide BSEE with the location of these records, as required in §§ 285.701(c) and (d), 285.702(c) and (d), 285.703(b), and 285.708(a)(5) and (7).
Citations to §285.701(d)
-
(c) You must provide BSEE with the location of these records, as required in §§ 285.701(c) and (d), 285.702(c) and (d), 285.703(b), and 285.708(a)(5) and (7).