§250.867. Temporary quarters and temporary equipment.
30 C.F.R. § 250.867
You must equip temporary quarters with all safety devices required by API Recommended Practice 14C, Appendix C (incorporated by reference, see § 250.198). The District Manager must approve the safety system/safety devices associated with the temporary quarters prior to installation.
The District Manager may require you to install a temporary firewater system for temporary quarters in production processing areas or other classified areas.
Temporary equipment associated with the production process system, including equipment used for well testing and/or well clean-up, must be approved by the District Manager.
The District Manager must approve temporary generators that would require a change to the electrical one-line diagram in § 250.842(a).
Notes, amendments, and revision history
Amendments
[81 FR 61918, Sept. 7, 2016, as amended at 83 FR 49259, Sept. 28, 2018; 91 FR 35355, June 10, 2026]
Source
Source: 81 FR 61918, Sept. 7, 2016, unless otherwise noted.
Authority
Authority: 30 U.S.C. 1751, 31 U.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
Source
Source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.
Amendments
[81 FR 61918, Sept. 7, 2016, as amended at 83 FR 49259, Sept. 28, 2018; 91 FR 35355, June 10, 2026]