§53.480. Earthquake engineering. — Inbound Citations

10 C.F.R. § 53.480

Cited by 5 regulations in release Current.

Citations to 10 U.S.C. § 53.480 as a whole

  • (b) The approved information collection requirements contained in this part appear in §§ 53.070, 53.080, 53.240, 53.410, 53.420, 53.425, 53.430, 53.440, 53.450, 53.480, 53.500, 53.540, 53.605, 53.610, 53.620, 53.700, 53.710, 53.715, 53.720, 53.730, 53.780, 53.785, 53.805, 53.810, 53.815, 53.830, 53.850, 53.855, 53.865, 53.870, 53.875, 53.880, 53.910, 53.1010, 53.1020, 53.1030, 53.1045, 53.1060, 53.1070, 53.1075, 53.1080, 53.1100, 53.1109, 53.1115, 53.1130, 53.1140, 53.1144, 53.1146, 53.1173, 53. 1182, 53.1188, 53.1200, 53.1206, 53.1209, 53.1210, 53.1221, 53.1230, 53.1236, 53.1239, 53.1241, 53.1254, 53.1257, 53,1263, 53.1270, 53.1276, 53.1279, 53.1282, 53.1288, 53.1295, 53.1300, 53.1306, 53.1309, 53.1312, 53.1327, 53.1330, 53.1333, 53.1336, 53.1348, 53.1360, 53.1366, 53.1369, 53.1372, 53.1384, 53.1410, 53.1413, 53.1416, 53.1419, 53.1437, 53.1449, 53.1452, 53.1458, 53.1470, 53.1505, 53.1510, 53.1515, 53.1525, 53.1530, 53.1535, 53.1540, 53.1545, 53.1550, 53.1560, 53.1565, 53.1570, 53.1575, 53.1580, 53.1620, 53.1630, 53.1645, 53.1690, 53.1720.
  • (B) The information necessary to demonstrate that the commercial nuclear plant complies with the earthquake engineering criteria in § 53.480.
  • Safety-related SSCs must be protected against or must be designed to withstand the effects of natural phenomena (e.g., earthquakes, tornadoes, hurricanes, floods, tsunami, and seiches) and constructed hazards (e.g., dams, transportation routes, military and industrial facilities) considering an event severity up to the design-basis external hazard levels as determined under § 53.510 without losing the capability to perform the safety functions identified under § 53.230. Specific requirements for earthquake engineering are included in § 53.480.
  • (a) The siting of each commercial nuclear plant is supported by assessments of proposed sites such that the design, including design features and programmatic controls corresponding to the site characteristics, satisfies the safety criteria defined in §§ 53.210 and 53.220. The siting assessment addresses the site characteristics that might contribute to the initiation, progression, or consequences of licensing-basis events (LBEs) analyzed under §§ 53.450 and 53.480 that are identified and mitigated by design features or programmatic controls. The siting assessment takes into consideration the potential adverse impacts that a commercial nuclear plant may have on nearby populations as a result of normal operations or LBEs.
  • (b) As used in this section, the following terms mean:
    Geological Siting Factors are geological and seismic factors that may affect the design and operation of the proposed commercial nuclear plant.
    Ground Motion Response Spectra (GMRS) are the site-specific GMRS resulting from the geologic investigations and evaluations of the site vicinity and region and used to determine design-basis ground motions for structures, systems, and components under § 53.480.
    Probabilistic Seismic Hazard Analysis is an analytical methodology that incorporates uncertainty into estimates of an annual frequency of exceedance for a certain ground motion parameter (e.g., peak ground acceleration, peak ground velocity, response spectral values) at a site.