US Codex
Pub. L.
Notes

Title III — Energy

115th Congress · Approved Oct 23, 2018 · 132 Stat. 3765

TITLE III Energy

SEC. 3001. Modernizing Authorizations for Necessary Hydropower Approvals.

(a)
Preliminary Permits.— Section 5 of the Federal Power Act (16 U.S.C. 798) is amended—
(1)
in subsection (a), by striking “ three” and inserting “ 4”; and
(2)
in subsection (b)—
(A)
by striking “ Commission may extend the period of a preliminary permit once for not more than 2 additional years beyond the 3 years” and inserting the following:

“(1) extend the period of a preliminary permit once for not more than 4 additional years beyond the 4 years”

(B)
by striking the period at the end and inserting “ ; and”; and
(C)
by adding at the end the following:

“(2) after the end of an extension period granted under paragraph (1), issue an additional permit to the permittee if the Commission determines that there are extraordinary circumstances that warrant the issuance of the additional permit.”

(b)
Time Limit for Construction of Project Works.— Section 13 of the Federal Power Act (16 U.S.C. 806) is amended in the second sentence by striking “ once but not longer than two additional years” and inserting “ for not more than 8 additional years,”.
(c)
Obligation for Payment of Annual Charges.— Any obligation of a licensee or exemptee for the payment of annual charges under section 10(e) of the Federal Power Act (16 U.S.C. 803(e)) for a project that has not commenced construction as of the date of enactment of this Act shall commence not earlier than the latest of—
(1)
the date by which the licensee or exemptee is required to commence construction; or
(2)
the date of any extension of the deadline under paragraph (1).

SEC. 3002. Qualifying Conduit Hydropower Facilities.

Section 30(a) of the Federal Power Act (16 U.S.C. 823a(a)) is amended—
(1)
in paragraph (2)(C), by striking “ 45 days” and inserting “ 30 days”; and
(2)
in paragraph (3)(C)(ii), by striking “ 5” and inserting “ 40”.

SEC. 3003. Promoting Hydropower Development at Existing Nonpowered Dams.

Part I of the Federal Power Act (16 U.S.C. 792 et seq.) is amended by adding at the end the following:

“SEC. 34. PROMOTING HYDROPOWER DEVELOPMENT AT EXISTING NONPOWERED DAMS.

“(a) Expedited Licensing Process for Non-Federal Hydropower Projects at Existing Nonpowered Dams.—

“(1) In general.—As provided in this section, the Commission may issue and amend licenses, as appropriate, for any facility the Commission determines is a qualifying facility.

“(2) Rule.—Not later than 180 days after the date of enactment of this section, the Commission shall issue a rule establishing an expedited process for issuing and amending licenses for qualifying facilities under this section.

“(3) Interagency task force.—

“(A) In establishing the expedited process under this section, the Commission shall convene an interagency task force, with appropriate Federal and State agencies and Indian tribes represented, to coordinate the regulatory processes associated with the authorizations required to construct and operate a qualifying facility.

“(B) The task force shall develop procedures that are consistent with subsection (e)(1)(E) to seek to ensure that, for projects licensed pursuant to this section, the Commission and appropriate Federal and State agencies and Indian tribes shall exercise their authorities in a manner that, to the extent practicable, will not result in any material change to the storage, release, or flow operations of the associated nonpowered dam existing at the time an applicant files its license application.

“(4) Length of process.—The Commission shall seek to ensure that the expedited process under this section will result in a final decision on an application for a license by not later than 2 years after receipt of a completed application for the license.

“(b) Dam Safety.—

“(1) Assessment.—Before issuing any license for a qualifying facility, the Commission shall assess the safety of existing non-Federal dams and other non-Federal structures related to the qualifying facility (including possible consequences associated with failure of such structures).

“(2) Requirements.—In issuing any license for a qualifying facility at a non-Federal dam, the Commission shall ensure that the Commission’s dam safety requirements apply to such qualifying facility, and the associated qualifying nonpowered dam, over the term of such license.

“(c) Interagency Communications.—Interagency cooperation in the preparation of environmental documents under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) with respect to an application for a license for a qualifying facility under this section, and interagency communications relating to licensing process coordination pursuant to this section, shall not—

“(1) be considered to be ex parte communications under Commission rules; or

“(2) preclude an agency from participating in a licensing proceeding under this part, providing that any agency participating as a party in a licensing proceeding under this part shall, to the extent practicable, demonstrate a separation of staff cooperating with the Commission under the National Environmental Policy Act (42 U.S.C. 4321 et seq.) and staff participating in the applicable proceeding under this part.

“(d) Identification of Nonpowered Dams for Hydropower Development.—

“(1) In general.—Not later than 12 months after the date of enactment of this section, the Commission, with the Secretary of the Army, the Secretary of the Interior, and the Secretary of Agriculture, shall jointly develop a list of existing nonpowered Federal dams that the Commission and the Secretaries agree have the greatest potential for non-Federal hydropower development.

“(2) Considerations.—In developing the list under paragraph (1), the Commission and the Secretaries may consider the following:

“(A) The compatibility of hydropower generation with existing purposes of the dam.

“(B) The proximity of the dam to existing transmission resources.

“(C) The existence of studies to characterize environmental, cultural, and historic resources relating to the dam.

“(D) The effects of hydropower development on release or flow operations of the dam.

“(3) Availability.—The Commission shall—

“(A) provide the list developed under paragraph (1) to—

“(i) the Committee on Energy and Commerce, the Committee on Transportation and Infrastructure, and the Committee on Natural Resources, of the House of Representatives; and

“(ii) the Committee on Environment and Public Works, and the Committee on Energy and Natural Resources, of the Senate; and

“(B) make such list available to the public.

“(e) Definitions.—For purposes of this section:

“(1) Qualifying criteria.—The term ‘qualifying criteria’ means, with respect to a facility—

“(A) as of the date of enactment of this section, the facility is not licensed under, or exempted from the license requirements contained in, this part;

“(B) the facility will be associated with a qualifying nonpowered dam;

“(C) the facility will be constructed, operated, and maintained for the generation of electric power;

“(D) the facility will use for such generation any withdrawals, diversions, releases, or flows from the associated qualifying nonpowered dam, including its associated impoundment or other infrastructure; and

“(E) the operation of the facility will not result in any material change to the storage, release, or flow operations of the associated qualifying nonpowered dam.

“(2) Qualifying facility.—The term ‘qualifying facility’ means a facility that is determined under this section to meet the qualifying criteria.

“(3) Qualifying nonpowered dam.—The term ‘qualifying nonpowered dam’ means any dam, dike, embankment, or other barrier—

“(A) the construction of which was completed on or before the date of enactment of this section;

“(B) that is or was operated for the control, release, or distribution of water for agricultural, municipal, navigational, industrial, commercial, environmental, recreational, aesthetic, drinking water, or flood control purposes; and

“(C) that, as of the date of enactment of this section, is not generating electricity with hydropower generating works that are licensed under, or exempted from the license requirements contained in, this part.

“(f) Savings Clause.—Nothing in this section affects—

“(1) any authority of the Commission to license a facility at a nonpowered dam under this part; and

“(2) any authority of the Commission to issue an exemption to a small hydroelectric power project under the Public Utility Regulatory Policies Act of 1978.”

SEC. 3004. Closed-Loop Pumped Storage Projects.

Part I of the Federal Power Act (16 U.S.C. 792 et seq.), as amended, is further amended by adding at the end the following:

“SEC. 35. CLOSED-LOOP PUMPED STORAGE PROJECTS.

“(a) Expedited Licensing Process for Closed-Loop Pumped Storage Projects.—

“(1) In general.—As provided in this section, the Commission may issue and amend licenses, as appropriate, for closed-loop pumped storage projects.

“(2) Rule.—Not later than 180 days after the date of enactment of this section, the Commission shall issue a rule establishing an expedited process for issuing and amending licenses for closed-loop pumped storage projects under this section.

“(3) Interagency task force.—In establishing the expedited process under this section, the Commission shall convene an interagency task force, with appropriate Federal and State agencies and Indian tribes represented, to coordinate the regulatory processes associated with the authorizations required to construct and operate closed-loop pumped storage projects.

“(4) Length of process.—The Commission shall seek to ensure that the expedited process under this section will result in final decision on an application for a license by not later than 2 years after receipt of a completed application for such license.

“(b) Dam Safety.—Before issuing any license for a closed-loop pumped storage project, the Commission shall assess the safety of existing dams and other structures related to the project (including possible consequences associated with failure of such structures).

“(c) Exceptions From Other Requirements.—

“(1) In general.—In issuing or amending a license for a closed-loop pumped storage project pursuant to the expedited process established under this section, the Commission may grant an exception from any other requirement of this part with respect to any part of the closed-loop pumped storage project (not including any dam or other impoundment).

“(2) Consultation.—In granting an exception under paragraph (1), the Commission shall consult with the United States Fish and Wildlife Service, the National Marine Fisheries Service, and the State agency exercising administration over the fish and wildlife resources of the State in which the closed-loop pumped storage project is or will be located, in the manner provided by the Fish and Wildlife Coordination Act (16 U.S.C. 661 et seq.).

“(3) Terms and conditions.—In granting an exception under paragraph (1), the Commission shall include in any such exception—

“(A) such terms and conditions as the United States Fish and Wildlife Service, the National Marine Fisheries Service, and the State agency described in paragraph (2) each determine are appropriate to prevent loss of, or damage to, fish and wildlife resources and to otherwise carry out the purposes of the Fish and Wildlife Coordination Act; and

“(B) such terms and conditions as the Commission deems appropriate to ensure that such closed-loop pumped storage project continues to comply with the provisions of this section and terms and conditions included in any such exception.

“(4) Fees.—The Commission, in addition to the requirements of section 10(e), shall establish fees which shall be paid by an applicant for a license for a closed-loop pumped storage project that is required to meet terms and conditions set by fish and wildlife agencies under paragraph (3). Such fees shall be adequate to reimburse the fish and wildlife agencies referred to in paragraph (3) for any reasonable costs incurred in connection with any studies or other reviews carried out by such agencies for purposes of compliance with this section. The fees shall, subject to annual appropriations Acts, be transferred to such agencies by the Commission for use solely for purposes of carrying out such studies and shall remain available until expended.

“(d) Transfers.—Notwithstanding section 5, and regardless of whether the holder of a preliminary permit for a closed-loop pumped storage project claimed municipal preference under section 7(a) when obtaining the permit, on request by a municipality, the Commission may, to facilitate development of a closed-loop pumped storage project—

“(1) add entities as joint permittees following issuance of a preliminary permit; and

“(2) transfer a license in part to one or more nonmunicipal entities as co-licensees with a municipality, if the municipality retains majority ownership of the project for which the license was issued.

“(e) Interagency Communications.—Interagency cooperation in the preparation of environmental documents under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) with respect to an application for a license for a closed-loop pumped storage project submitted pursuant to this section, and interagency communications relating to licensing process coordination pursuant to this section, shall not—

“(1) be considered to be ex parte communications under Commission rules; or

“(2) preclude an agency from participating in a licensing proceeding under this part, providing that any agency participating as a party in a licensing proceeding under this part shall, to the extent practicable, demonstrate a separation of staff cooperating with the Commission under the National Environmental Policy Act (42 U.S.C. 4321 et seq.) and staff participating in the applicable proceeding under this part.

“(f) Developing Abandoned Mines for Pumped Storage.—

“(1) Workshop.—Not later than 6 months after the date of enactment of this section, the Commission shall hold a workshop to explore potential opportunities for development of closed-loop pumped storage projects at abandoned mine sites.

“(2) Guidance.—Not later than 1 year after the date of enactment of this section, the Commission shall issue guidance to assist applicants for licenses or preliminary permits for closed-loop pumped storage projects at abandoned mine sites.

“(g) Qualifying Criteria for Closed-Loop Pumped Storage Projects.—

“(1) In general.—The Commission shall establish criteria that a pumped storage project shall meet in order to qualify as a closed-loop pumped storage project eligible for the expedited process established under this section.

“(2) Inclusions.—In establishing the criteria under paragraph (1), the Commission shall include criteria requiring that the pumped storage project—

“(A) cause little to no change to existing surface and ground water flows and uses; and

“(B) is unlikely to adversely affect species listed as a threatened species or endangered species under the Endangered Species Act of 1973.

“(h) Savings Clause.—Nothing in this section affects any authority of the Commission to license a closed-loop pumped storage project under this part.”

SEC. 3005. Considerations for Relicensing Terms.

Part I of the Federal Power Act (16 U.S.C. 792 et seq.), as amended, is further amended by adding at the end the following:

“SEC. 36. CONSIDERATIONS FOR RELICENSING TERMS.

“(a) In General.—In determining the term of a new license issued when an existing license under this part expires, the Commission shall take into consideration, among other things—

“(1) project-related investments by the licensee under the new license; and

“(2) project-related investments by the licensee over the term of the existing license.

“(b) Equal Weight.—The determination of the Commission under subsection (a) shall give equal weight to—

“(1) investments by the licensee to implement the new license under this part, including investments relating to redevelopment, new construction, new capacity, efficiency, modernization, rehabilitation or replacement of major equipment, safety improvements, or environmental, recreation, or other protection, mitigation, or enhancement measures required or authorized by the new license; and

“(2) investments by the licensee over the term of the existing license (including any terms under annual licenses) that—

“(A) resulted in redevelopment, new construction, new capacity, efficiency, modernization, rehabilitation or replacement of major equipment, safety improvements, or environmental, recreation, or other protection, mitigation, or enhancement measures conducted over the term of the existing license; and

“(B) were not expressly considered by the Commission as contributing to the length of the existing license term in any order establishing or extending the existing license term.

“(c) Commission Determination.—At the request of the licensee, the Commission shall make a determination as to whether any planned, ongoing, or completed investment meets the criteria under subsection (b)(2). Any determination under this subsection shall be issued within 60 days following receipt of the licensee’s request. When issuing its determination under this subsection, the Commission shall not assess the incremental number of years that the investment may add to the new license term. All such assessment shall occur only as provided in subsection (a).”

SEC. 3006. Fair Ratepayer Accountability, Transparency, and Efficiency Standards.

Section 205 of the Federal Power Act (16 U.S.C. 824d) is amended by adding at the end the following:

“(g) Inaction of Commissioners.—

“(1) In general.—With respect to a change described in subsection (d), if the Commission permits the 60-day period established therein to expire without issuing an order accepting or denying the change because the Commissioners are divided two against two as to the lawfulness of the change, as a result of vacancy, incapacity, or recusal on the Commission, or if the Commission lacks a quorum—

“(A) the failure to issue an order accepting or denying the change by the Commission shall be considered to be an order issued by the Commission accepting the change for purposes of section 313(a); and

“(B) each Commissioner shall add to the record of the Commission a written statement explaining the views of the Commissioner with respect to the change.

“(2) Appeal.—If, pursuant to this subsection, a person seeks a rehearing under section 313(a), and the Commission fails to act on the merits of the rehearing request by the date that is 30 days after the date of the rehearing request because the Commissioners are divided two against two, as a result of vacancy, incapacity, or recusal on the Commission, or if the Commission lacks a quorum, such person may appeal under section 313(b).”

SEC. 3007. J. Bennett Johnston Waterway Hydropower Extension.

(a)
In General.— Notwithstanding the time period specified in section 13 of the Federal Power Act (16 U.S.C. 806) that would otherwise apply to Federal Energy Regulatory Commission project numbers 12756, 12757, and 12758, the Commission may, at the request of the licensee for the applicable project, and after reasonable notice, in accordance with the good faith, due diligence, and public interest requirements of that section and the Commission’s procedures under that section, extend the time period during which such licensee is required to commence the construction of its applicable project for up to 3 consecutive 2-year periods from the date of the expiration of the extension originally issued by the Commission under that section for such project.
(b)
Obligation for Payment of Annual Charges.— Any obligation of a licensee for a project described in subsection (a) for the payment of annual charges under section 10(e) of the Federal Power Act (16 U.S.C. 803(e)) shall commence when the construction of the project commences.
(c)
Reinstatement of License; Effective Date for Extension.—
(1)
Reinstatement.— If the time period required for commencement of construction of a project described in subsection (a) has expired prior to the date of the enactment of this Act, the Commission may reinstate the license for such project, effective as of the date of the expiration of the license.
(2)
Effective date for extension.— If the Commission reinstates a license under paragraph (1) for a project, the first extension authorized under subsection (a) with respect to such project shall take effect on the effective date of such reinstatement under paragraph (1).

SEC. 3008. Stay and Reinstatement of Ferc License No. 11393 for the Mahoney Lake Hydroelectric Project.

(a)
Definitions.— In this section:
(1)
Commission.— The term “Commission” means the Federal Energy Regulatory Commission.
(2)
License.— The term “license” means the license for the Commission project numbered 11393.
(3)
Licensee.— The term “licensee” means the holder of the license.
(b)
Stay of License.— On the request of the licensee, the Commission shall issue an order continuing the stay of the license.
(c)
Lifting of Stay.— On the request of the licensee, but not later than 10 years after the date of enactment of this Act, the Commission shall—
(1)
issue an order lifting the stay of the license under subsection (b); and
(2)
make the effective date of the license the date on which the stay is lifted under paragraph (1).
(d)
Extension of License.—
(1)
In general.— Notwithstanding the time period specified in section 13 of the Federal Power Act (16 U.S.C. 806) that would otherwise apply to the Commission project numbered 11393, the Commission may, at the request of the licensee, and after reasonable notice, in accordance with the good faith, due diligence, and public interest requirements of, and the procedures of the Commission under, that section, extend the time period during which the licensee is required to commence the construction of the project for not more than 3 consecutive 2-year periods from the date of the expiration of the extension originally issued by the Commission.
(2)
Reinstatement of expired license.—
(A)
In general.— If the period required for the commencement of construction of the project described in paragraph (1) has expired prior to the date of enactment of this Act, the Commission may reinstate the license effective as of the date of the expiration of the license.
(B)
Extension.— If the Commission reinstates the license under subparagraph (A), the first extension authorized under paragraph (1) shall take effect on the date of that expiration.
(e)
Effect.— Nothing in this Act prioritizes, or creates any advantage or disadvantage to, Commission project numbered 11393 under Federal law, including the Federal Power Act (16 U.S.C. 791a et seq.) or the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2601 et seq.), as compared to—
(1)
any electric generating facility in existence on the date of enactment of this Act; or
(2)
any electric generating facility that may be examined, proposed, or developed during the period of any stay or extension of the license under this Act.

SEC. 3009. Strategic Petroleum Reserve Drawdown.

(a)
Drawdown and Sale.—
(1)
In general.— Notwithstanding section 161 of the Energy Policy and Conservation Act (42 U.S.C. 6241), except as provided in subsection (b), the Secretary of Energy shall draw down and sell 5,000,000 barrels of crude oil from the Strategic Petroleum Reserve during fiscal year 2028.
(2)
Deposit of amounts received from sale.— Amounts received from a sale under paragraph (1) shall be deposited in the general fund of the Treasury during the fiscal year in which the sale occurs.
(b)
Emergency Protection.— The Secretary of Energy may not draw down and sell crude oil under this section in quantities that would limit the authority to sell petroleum products under subsection (h) of section 161 of the Energy Policy and Conservation Act (42 U.S.C. 6241) in the full quantity authorized by that subsection.