§652.22. Certification process for individuals. — Inbound Citations

7 C.F.R. § 652.22

Cited by 11 regulations in release Current.

Citations to 7 C.F.R. § 652.22 as a whole

Citations to §652.22(c)(1)

  • (c) NRCS will, within 60 days of receipt of an application, make a determination on the application submitted by an entity. If NRCS determines that all requirements for the private-sector entity and the identified individual(s) are met, NRCS will complete the actions described in paragraphs (c)(1) through (c)(3) of § 652.22.
  • (c) NRCS will, within 60 days of receipt of an application, make a determination on the application submitted by a public agency. If NRCS determines that all requirements for the public agency and the identified individual(s) are met, NRCS will perform the actions described in paragraph (c)(1) through (c)(3) of § 652.22. The Certification Agreement entered into with the public agency shall:
    (1) Identify the certified individuals that are authorized to perform technical services on behalf of and under the auspices of the public agency's certification;
    (2) Require that the public agency have, at all times, an individual that is a certified technical service provider and is an authorized official of the public agency;
    (3) Require that the public agency promptly provide to NRCS for NRCS approval an amended Certification Agreement when the list of certified individuals performing technical services under its auspices changes;
    (4) Require that responsibility for any work performed by non-certified individuals be assumed by a certified individual that is authorized to act on the public agency's behalf; and
    (5) Require that the public agency be legally responsible for the work performed by any individual working under the auspices of its certification.
  • (d) NRCS will, within 60 days, make a determination on the recommendation for certification issued by the recommending organization. If NRCS determines that all requirements for certification are met by the recommended individual(s), NRCS will perform the actions described in paragraphs (c)(1) through (c)(3) of § 652.22.

Citations to §652.22(c)(2)

  • (c) NRCS will, within 60 days of receipt of an application, make a determination on the application submitted by an entity. If NRCS determines that all requirements for the private-sector entity and the identified individual(s) are met, NRCS will complete the actions described in paragraphs (c)(1) through (c)(3) of § 652.22.
  • (c) NRCS will, within 60 days of receipt of an application, make a determination on the application submitted by a public agency. If NRCS determines that all requirements for the public agency and the identified individual(s) are met, NRCS will perform the actions described in paragraph (c)(1) through (c)(3) of § 652.22. The Certification Agreement entered into with the public agency shall:
    (1) Identify the certified individuals that are authorized to perform technical services on behalf of and under the auspices of the public agency's certification;
    (2) Require that the public agency have, at all times, an individual that is a certified technical service provider and is an authorized official of the public agency;
    (3) Require that the public agency promptly provide to NRCS for NRCS approval an amended Certification Agreement when the list of certified individuals performing technical services under its auspices changes;
    (4) Require that responsibility for any work performed by non-certified individuals be assumed by a certified individual that is authorized to act on the public agency's behalf; and
    (5) Require that the public agency be legally responsible for the work performed by any individual working under the auspices of its certification.
  • (d) NRCS will, within 60 days, make a determination on the recommendation for certification issued by the recommending organization. If NRCS determines that all requirements for certification are met by the recommended individual(s), NRCS will perform the actions described in paragraphs (c)(1) through (c)(3) of § 652.22.

Citations to §652.22(c)(3)

  • (c) NRCS will, within 60 days of receipt of an application, make a determination on the application submitted by an entity. If NRCS determines that all requirements for the private-sector entity and the identified individual(s) are met, NRCS will complete the actions described in paragraphs (c)(1) through (c)(3) of § 652.22.
  • (c) NRCS will, within 60 days of receipt of an application, make a determination on the application submitted by a public agency. If NRCS determines that all requirements for the public agency and the identified individual(s) are met, NRCS will perform the actions described in paragraph (c)(1) through (c)(3) of § 652.22. The Certification Agreement entered into with the public agency shall:
    (1) Identify the certified individuals that are authorized to perform technical services on behalf of and under the auspices of the public agency's certification;
    (2) Require that the public agency have, at all times, an individual that is a certified technical service provider and is an authorized official of the public agency;
    (3) Require that the public agency promptly provide to NRCS for NRCS approval an amended Certification Agreement when the list of certified individuals performing technical services under its auspices changes;
    (4) Require that responsibility for any work performed by non-certified individuals be assumed by a certified individual that is authorized to act on the public agency's behalf; and
    (5) Require that the public agency be legally responsible for the work performed by any individual working under the auspices of its certification.
  • (d) NRCS will, within 60 days, make a determination on the recommendation for certification issued by the recommending organization. If NRCS determines that all requirements for certification are met by the recommended individual(s), NRCS will perform the actions described in paragraphs (c)(1) through (c)(3) of § 652.22.