When a signed application for service has been received, the State supervisor or his designee will complete a plant survey pursuant to
§ 56.30. The costs for completing the plant survey will be charged to the applicant on an unscheduled basis as described in
§ 56.46. No charges will be assessed when the application is required because of a change in name or ownership. If service is not installed within 6 months from the date the application is filed, or if service is inactive due to an approved request for removal of a grader or graders(s) for a period of 6 months, the application will be considered terminated. A new application may be filed at any time. In addition, there will be a charge of $300 if the application is terminated at the request of the applicant for reasons other than for a change in location within 12 months from the date of the inauguration of service.