Contract method. This method of development will be used for all complex construction except in cases where owner-builder method is authorized. Development under this method is done in accordance with
§ 1924.6(a) of this subpart except as modified by this paragraph. All construction work will be completed under one written construction contract. Guide 1, “Contract Documents,” of this subpart (available in any Agency office) is provided to assist Agency personnel and applicants in assembling and reviewing contract documents for more complex construction such as that administered under this section.
(ii)
Contract documents. Contract documents will conform with recognized professional practices as prescribed in this paragraph. Such contract documents will contain substantially the following:
(A)
Substitution of term “architect” for “engineer” may be necessary on some of the forms. Other modifications may be necessary in some cases to conform to the nature and extent of the project. All such contract documents and related items will be concurred with by the State Director, with the assistance of OGC prior to the release of invitations to bid.
(B)
Items listed as I through IV and item XI of
paragraph (e)(1)(ii) of this section may be omitted when an exception to the competitive bidding requirement is granted in accordance with
paragraph (e)(1)(vii) of this section, thereby permitting a negotiated contract.
(C)
All negotiated contracts shall include a provision to the effect that the borrower, USDA, the Comptroller General of the United States, or any of their duly authorized representatives, shall have access to any books, documents, papers, and records of the contractor which are directly pertinent to a specific Federal loan program for the purpose of making audit, examination, excerpts, and transcriptions.
(D)
A provision of liquidated damages <I>will</I> be included in all contracts. The liquidated damage amount must be reasonable and represent the best estimate possible of how much interest or other costs will accrue on the loan, and also represent any loss of rent or other income which would result from a delay in the completion of the project beyond the estimated completion date.
(E)
All contracts shall include a provision for compliance with the Copeland “Anti-Kickback” Act (
18 U.S.C. 874) as supplemented in Department of Labor regulations (
29 CFR part 3). This Act prohibits anyone from inducing any person in connection with the construction to give up any part of the compensation to which the person is otherwise entitled.
(F)
All contracts will contain a certification by the applicant indicating that there is not now nor will there be an identity of interest between the applicant and any of the following: Contractor, architect, engineer, attorney, subcontractors, material suppliers, equipment lessors, or any of their members, directors, officers, stockholders, partners, or beneficiaries unless specifically identified to the Agency in writing prior to the award of the contract. All contracts must also indicate that when any identity of interest exists or comes into being, the contractor agrees to have construction costs as reported to the Agency on Form 1924-13, “Estimate and Certificate of Actual Cost,” audited by a Certified Public Accountant (CPA) or Licensed Public Accountant (LPA) licensed prior to December 31, 1970, who will provide an opinion as to whether the Form RD 1924-13 presents fairly the costs of construction in conformity with eligible construction costs as prescribed in Agency regulations.
(G)
All contracts on any form other than Form RD 1924-6, must contain the language of
clause (D) of Form RD 1924-6, which is available in all Agency offices. The language of
clause (D) of Form RD 1924-6 sets forth the Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity required by Executive Order 11246, the Equal Opportunity clause published at 41 CFR
60-1.4 (a) and
(b), and the Standard Federal Equal Employment Opportunity Construction Contract Specifications required by Executive Order 11246. For contract forms other than Form RD 1924-6, Form AD 767, “Equal Employment Opportunity Contract Compliance Notices,” which can be obtained from the Finance Office, should be attached and made a part of the contract.
(H)
All contracts will contain a provision that they are not in full force and effect until concurred with by the State Director or the State Director's delegate, in writing. Therefore, before loan closing or before the start of construction, whichever occurs first, the State Director or the State Director's delegate will concur in the contract form, content, and execution if acceptable, by including the following paragraph at the end of the contract:
(I)
The requirements of
§ 1924.6 (a)(11)(iv) of this subpart apply to all contracts or subcontracts in excess of $10,000.
(iii)
Surety. When multiple advances of loan or grant funds are utilized, surety that guarantees both payment and performance in the full amount of the contract will be provided in accordance with
§ 1924.6(a)(3)(ii) of this subpart. Exceptions to the surety requirements shall be governed by the following:
(A)
In accordance with the guidance and recommendations of OMB Circulars A-102 and A-110, exceptions to the surety requirements of
§ 1924.6(a)(3)(ii) of this subpart will not be granted for nonprofit organization or public body applicants.
(B)
For loans or grants to applicants other than non-profit organizations or public bodies that are within the State Director's approval authority, the State Director may, upon request of the borrower or grantee, grant exceptions to the surety requirements in accordance with the provisions of
§ 1924.6(a)(3)(iii) of this subpart. Before granting such an exception, however, the State Director should be provided the following information from the proposed contractor in order to fully evaluate the experience and capabilities of the contractor:
(1) A resume indicating the contractor's history, ability and experience.
(2) A current, dated and signed financial statement of the contractor's operations indicating the payment status of accounts and any contingent liabilities that may exist. Agency personnel will be responsible for analyzing the financial statement as to the sufficiency of the contractor's financial capability to carry out construction. The financial strength must demonstrate the ability of the contractor to pay all bills prior to receiving periodic draws of funds from the lender.
(3) A credit report (obtained at no expense to the Agency) attesting to the contractor's credit standing.
(4) A listing of trade references that could be contacted to substantiate the contractor's experience and good standing.
(5) Statements from owners for whom the contractor has done similar work, indicating the scope of the work and the owner's evaluation of the contractor's performance.
(C)
For loans or grants to applicants other than non-profit organization or public bodies that are in excess of the State Director's approval authority, the State Director may request National Office authorization to grant one of the exceptions to the surety requirements as indicated in
§ 1924.6(a)(3)(iii) of this subpart. The following information must be submitted with the request to the National Office:
(1) An explanation of why interim financing is not available.
(2) An explanation of why the proposed contractor cannot obtain surety bonds meeting the requirements of § 1924.6(a)(3)(ii) of this subpart.
(3) The information listed in paragraph (e)(1)(iii)(B) of this section.
(4) The drawings and specifications for the proposed project, together with the comments of the State architect/engineer.
(5) The applicant's written request for an exception.
(6) An explanation of why the requirements of § 1924.6(a)(3)(iii) (A) or (B) of this subpart cannot be met in those cases where the State Director requests authorization to grant an exception as indicated in § 1924.6(a)(3)(iii)(C) of this subpart. When such a request is made, the documentation required of the contractor under the provision must also be forwarded.
(7) The State Director's recommendation.
(D)
Adequate steps will be taken to protect the interests of the borrower and the government in accordance with the payment provisions of
§ 1924.6(a)(12)(i) of this subpart and any alternative as outlined in
§ 1924.6(a)(3)(iii)(c) of this subpart.
(v)
Cost certification. Whenever the State Director determines it appropriate, and in all situations where there is an identity of interest as defined in
§ 1924.4(i) of this subpart, the borrower, contractor and any subcontractor, material supplier, or equipment lessor having an identity of interest must each provide certification using Form RD 1924-13 as to the actual cost of the work performed in connection with the construction contract. The construction costs, as reported on Form RD 1924-13, must also be audited, in accordance with Government Auditing Standards, by a CPA, or LPA licensed on or before December 31, 1970. In addition, certain agreed upon procedures (available in any Agency office) will be performed in accordance with Attestation Standards. In some cases, the Agency will contract directly with a CPA or LPA for the cost certification. In that event, documentation necessary to have the costs of construction certified by an Agency contractor that they were the actual costs of the work performed, as reported on Form RD 1924-13, will be provided. Funds which were included in the loan for cost certification and which are ultimately not needed because Agency contracts for the cost certification will be returned on the loan. Agency personnel will utilize exhibit M of this subpart (available in any Agency office) and Form RD 1924-26, “Cost Certification Worksheet,” to assist in the evaluation of the cost certification process.
(A)
Prior to the start of construction, the borrower, contractor and any subcontractor, material supplier, or equipment lessor sharing an identity of interest must submit, to the CPA or LPA, the accounting system that the borrower, contractor, subcontractor, material supplier or equipment lessor and/or the CPA or LPA proposes to set up and use in maintaining a running record of the actual cost. In order to be acceptable, the borrower must provide a written assertion that it has an accounting system that is suitably designed to provide for a trade-item basis comparison of the actual cost as compared to the estimated cost submitted on Form RD 1924-13. Costs pertaining to a specific line item will be set up in the accounting system for that particular account. For instance, only costs of materials, supplies, equipment, and labor associated with concrete will be shown in the concrete account. The accounting system must also restrict costs to those pertaining to a specific project so that costs from multiple projects will not be co-mingled. The independent CPA or LPA shall report on the borrower's assertion in accordance with the Standards for Attestation Engagements of the American Institute of Certified Public Accountants (AICPA). The borrower's and the CPA or LPA's reports on the accounting system shall be provided to the Agency by the borrower.
(B)
Prior to final payment to anyone required to cost certify, a trade-item breakdown showing the actual cost compared to the estimated cost must be provided to the owner and the Agency. Form RD 1924-13 is the form of comparative breakdown that must be used, and contains the certifications required of the applicant and contractor prior to final payment. The amounts for builder's general overhead, builder's profit, and general requirements, respectively, shall not exceed the amounts represented on the estimate of cost breakdown provided in accordance with
paragraph (e)(1)(iv) of this section for any contractor, subcontractor, material supplier, or equipment lessor having or sharing an identity of interest with the borrower. The amounts for general overhead, builder's profit, and general requirements must be established prior to the Agency approving the construction contract and will not be changed during the course of construction. This applies to all contractors, subcontractors, material suppliers, or equipment lessors having or sharing an identity of interest with the applicant. Contract change orders will be processed to adjust the contract amount downward prior to the final payment to the contractor, if necessary, to assure that the amounts shown in the certificate of actual costs do not exceed the amounts represented in the contract cost breakdown. Reduction in the builder's profit, and general overhead if needed, will counterbalance any increase reflected in the contract costs. Any funds remaining as a result of hard cost savings will be applied to the account as an extra payment or used for eligible loan purposes approved by the Agency as long as the improvements are genuinely needed and will enhance marketability of the project. All increases or decreases of 15 percent or more in line item costs will require documentation as to the reason for the increases and/or decreases. The State Director may require documentation for increases and/or decreases of less than 15 percent, if he/she determines it necessary. This information will be required with the cost certification.
(C)
The CPA or LPA audit, performed in accordance with Government Auditing Standards, will include such tests of the accounting records and such other auditing procedures of the borrower and the contractor (and any subcontractor, material supplier or equipment lessor sharing an identity of interest) concerning the work performed, services rendered, and materials supplied in accordance with the construction contract he/she considers necessary to express an opinion on the construction costs as reported on Form RD 1924-13. The CPA or LPA shall also perform the additional agreed upon procedures specified by the Agency (available in any Agency office), performed in accordance with Attestation Standards, for the applicant and the contractor (and any subcontractor, material supplier, or equipment lessor sharing an identity of interest) concerning the work performed, services rendered, and materials supplied in accordance with the construction contract.
(D)
Upon completion of construction and prior to final payment, the CPA or LPA will provide an opinion concerning whether the construction costs, as reported on Form RD 1924-13, present fairly the costs of construction in conformity with eligible construction costs as prescribed in Agency regulations.
(E)
In some cases, cost certification will be obtained by the Agency through direct contract with the CPA or LPA. The borrower and his/her CPA or LPA will cooperate fully with the contract CPA or LPA by providing all documentation necessary to conduct the certification. The Agency reserves the right to determine, upon receipt of the certified Form RD 1924-13 and the auditor's report, whether they are satisfactory to the Agency. If not satisfactory to the Agency, the borrower will be responsible for providing additional information.
(F)
There will exist no business relationship between the CPA or LPA and the borrower except for the performance of the examination of the cost certification, accounting systems work, and tax preparation. Any CPA or LPA who acts as the borrower's accountant (performing manual or automated bookkeeping services or maintains the official accounting records) will not be the same CPA or LPA who cost certifies the project.
(G)
Forms RD 1944-30, “Identity of Interest (IOI) Disclosure Certificate” and RD 1944-31, “Identity of Interest (IOI) Qualification Form,” provide written notification to the borrower that willful and intentional falsification of cost certification documents will result in debarment of all violators in accordance with the provisions of RD Instruction 1940-M (available in any Agency office). These forms require the disclosure of all identities of interest associated with project construction, certify the entity's ability to provide the contracted service, and cite the penalties for failure to disclose or falsify such certification. Each applicant/borrower will be required to complete and sign the forms (available in any Agency office).
(H)
(Subcontracting development work. (1) Contractors will not be allowed to obtain a profit and overhead unless they are performing actual construction. “Actual construction” means “work” as defined in American Institute of Architects (AIA) documents: “* * * labor, materials, equipment, and services provided by the contractor to fulfill the contractor's obligations.” Under this definition, contractors who choose to subcontract out construction of the project to another contractor will not obtain a builder's fee (general overhead and profit) when:
(i) More than 50 percent of the contract sum in the construction contract is subcontracted to one subcontractor, material supplier, or equipment lessor, and/or
(ii) Seventy-five percent or more with three or fewer subcontractors, material suppliers and/or equipment lessors.
(2) Note: If two or more subcontractors have common ownership, they are considered as one subcontractor.
(3) How to apply rule:
(i) The 50 percent rule will apply when division of the amount of the largest subcontract by the contract sum of the construction contract results in more than 50 percent.
(ii) The 75 percent rule will apply when division of the sum of the amounts of the three largest subcontracts by the contract sum of the construction contract results in 75 percent or more.
(I)
(Qualified contracting entities. Contractors, subcontractors, material suppliers, and any other individual or organization sharing an identity of interest and providing materials or services for the project must certify that it is a viable, ongoing trade or business qualified and properly licensed to undertake the work for which it intends to contract. Form RD 1944-31 will be prepared and executed by the contracting entities. The form provides notification to the entities of the penalty, under law, for erroneously certifying to the statements contained therein. Debarment actions will be instituted against entities who fail to disclose an identity of interest in accordance with the provisions of RD Instruction 1940-M (available in any Agency office).
(vii)
Exception to competitive bidding—
(A)
For all applicants. An applicant may negotiate a construction contract provided the State Director grants an exception and documentation shows that:
(1) The contract price is competitive with other projects similar in construction and design being built in the area.
(2) The proposed contractor is experienced in construction of projects of similar size, scope, and complexity, and is recognized as a reliable builder.
(3) The proposed development work meets all requirements of this subpart.
(4) If appropriate for nonprofit organizations and public bodies, the applicant provides a copy of a duly authorized resolution by its governing body requesting the Agency to permit awarding the construction contract without formal bidding.
(5) The applicant is permitted by state law, local law and/or organizational by-laws to negotiate a construction contract.
(6) The requirements of paragraphs (e)(1) (ii), (iii), (iv) and (v) of this section are met.
(B)
In considering an exception to competitive bidding, the following additional steps will be taken in all cases.
(1) If, after a full review of the case documents by the appropriate members of the State Office staff, the State Director determines that the requirements have been met and the costs are reasonable, an exception to competitive bidding may be granted. Written documentation of the State Office review results will be placed in the application file.
(2) If after the full review by the State Office staff, the State Director determines that the negotiated contract price is not competitive with other similar projects in construction and design being built in the area, the applicant will be requested to competitively bid the construction of the project in accordance with paragraph (e)(1)(i) of this section.
(3) If there is no agreement by the Agency and the applicant as to the construction cost, the State Director will cease any further action on the preapplication and inform the applicant of the right to appeal in accordance with subpart B of part 1900 of this chapter.
(C)
Any requests for exceptions to competitive bidding that are not covered in this section may be submitted to the National Office for consideration.
(viii)
Exception to contract method—public body. With the approval of the National Office, the State Director may grant to a public body an exception to the requirement for using contract method construction under the following circumstances:
(A)
The loan or grant is for repair or rehabilitation of existing facilities and it is not practicable to perform all work by the contract method.
(B)
The applicant has the managerial ability and qualified employees necessary to complete the work successfully.
(C)
That applicant submits a written request to the District Director indicating— (1) The scope of work and construction timetable;
(2) What phases of work can be contracted and what cannot;
(3) Why is it not practicable to contract all phases;
(4) Management ability and employee qualifications for performing the work;
(5) Proposed method of fund control and frequency of payments;
(6) How changes in scope of work and construction timetable will be approved; and,
(7) Proposed method of certifying progress and requesting payments.
(D)
The request, recommendations of the District Director, appropriate members of the State Office staff and the State Director and the application file will be sent to the National Office.