US Codex
C.F.R.
Browse by date
Notes

§375.403. How must I provide a binding estimate? — Inbound Citations

49 C.F.R. § 375.403

Cited by 3 regulations in release Current.

Citations to 49 C.F.R. § 375.403 as a whole

Citations to §375.403(a)(6)(ii)

  • (h) The bill of lading must be provided to, signed, and dated by the individual shipper at least 3 days before the shipment is scheduled to be loaded. You must provide the individual shipper the opportunity to rescind the bill of lading without any penalty for a 3-day period after the individual shipper signs the bill of lading. If the individual shipper tenders additional items to be moved or requires additional services on the day of the move, resulting in a new binding estimate under § 375.403(a)(6)(ii) or a new non-binding estimate under § 375.405(b)(7)(ii), the corresponding changes to the bill of lading from the new estimate do not require a new 3-day period as otherwise required in this paragraph (h).