§26.51. What means do recipients use to meet overall goals?

49 C.F.R. § 26.51

(a)
You must meet the maximum feasible portion of your overall goal by using DBE-neutral means of facilitating DBE-neutral participation. DBE-neutral participation includes any time a DBE wins a prime contract through customary competitive procurement procedures or is awarded a subcontract on a prime contract that does not carry a DBE contract goal.
(b)
DBE-neutral means include, but are not limited to, the following:
(1)
Arranging solicitations, times for the presentation of bids, quantities, specifications, and delivery schedules in ways that facilitate participation by DBEs and other small businesses and by making contracts more accessible to small businesses, by means such as those provided under § 26.39 of this part.
(2)
Providing assistance in overcoming limitations such as inability to obtain bonding or financing (e.g., by such means as simplifying the bonding process, reducing bonding requirements, eliminating the impact of surety costs from bids, and providing services to help DBEs, and other small businesses, obtain bonding and financing);
(3)
Providing technical assistance and other services;
(4)
Carrying out information and communications programs on contracting procedures and specific contract opportunities (e.g., ensuring the inclusion of DBEs, and other small businesses, on recipient mailing lists for bidders; ensuring the dissemination to bidders on prime contracts of lists of potential subcontractors; provision of information in languages other than English, where appropriate);
(5)
Implementing a supportive services program to develop and improve immediate and long-term business management, record keeping, and financial and accounting capability for DBEs and other small businesses;
(6)
Providing services to help DBEs, and other small businesses, improve long-term development, increase opportunities to participate in a variety of kinds of work, handle increasingly significant projects, and achieve eventual self-sufficiency;
(7)
Establishing a program to assist new, start-up firms, particularly in fields in which DBE participation has historically been low;
(8)
Ensuring distribution of your DBE directory, through print and electronic means, to the widest feasible universe of potential prime contractors; and
(9)
Assisting DBEs, and other small businesses, to develop their capability to utilize emerging technology and conduct business through electronic media.
(c)
Each time you submit your overall goal for review by the concerned operating administration, you must also submit your projection of the portion of the goal that you expect to meet through DBE-neutral means and your basis for that projection. This projection is subject to approval by the concerned operating administration, in conjunction with its review of your overall goal.
(d)
You must establish contract goals to meet any portion of your overall goal you do not project being able to meet using DBE-neutral means.
(e)
The following provisions apply to the use of contract goals—
(1)
You may use contract goals only on those DOT-assisted contracts that have subcontracting possibilities.
(2)
You are not required to set a contract goal on every DOT-assisted contract. You are not required to set each contract goal at the same percentage level as the overall goal. The goal for a specific contract may be higher or lower than that percentage level of the overall goal, depending on such factors as the type of work involved, the location of the work, and the availability of DBEs for the work of the particular contract. However, over the period covered by your overall goal, you must set contract goals so that they will cumulatively result in meeting any portion of your overall goal you do not project being able to meet through the use of DBE-neutral means.
(3)
Operating administration approval of each contract goal is not necessarily required. However, operating administrations may review and approve or disapprove any contract goal you establish.
(4)
Your contract goals must provide for participation by all certified DBEs and must not be subdivided into group-specific goals.
(f)
To ensure that your DBE program continues to be narrowly tailored to overcome the effects of social and economic disadvantage, you must adjust your use of contract goals as follows:
(1)
If your approved projection under paragraph (c) of this section estimates that you can meet your entire overall goal for a given year through DBE-neutral means, you must implement your program without setting contract goals during that year, unless it becomes necessary in order meet your overall goal.
(2)
If, during any year in which you are using contract goals, you determine that you will exceed your overall goal, you must reduce or eliminate the use of contract goals to the extent necessary to ensure that the use of contract goals does not result in exceeding the overall goal. If you determine that you will fall short of your overall goal, then you must make appropriate modifications in your use of DBE-neutral or DBE-conscious measures to allow you to meet the overall goal.
(3)
If the DBE participation you have obtained by DBE-neutral means alone meets or exceeds your overall goals for two consecutive years, you are not required to make a projection of the amount of your goal you can meet using such means in the next year. You do not set contract goals on any contracts in the next year. You continue using only DBE-neutral means to meet your overall goals unless and until you do not meet your overall goal for a year.
(4)
If you obtain DBE participation that exceeds your overall goal in two consecutive years using contract goals (i.e., not through DBE-neutral means alone), you must reduce your use of contract goals proportionately in the following year.
(g)
In any year in which you project meeting part of your goal through DBE-neutral means and the remainder through contract goals, you must maintain data separately on DBE achievements in those contracts with and without contract goals, respectively. You must report this data to the concerned operating administration as provided in § 26.11.
(h)
Effective October 3, 2025, you may not set any contract goals until the UCP that covers you has completed the reevaluation process described in § 26.111.
Notes, amendments, and revision history

Amendments

[64 FR 5126, Feb. 2, 1999, as amended at 76 FR 5098, Jan. 28, 2011; 79 FR 59595, Oct. 2, 2014; 89 FR 24967, Apr. 9, 2024; 90 FR 47981, Oct. 3, 2025]

Authority

Authority: 23 U.S.C. 304 and 324; 42 U.S.C. 2000d, et seq.; 49 U.S.C. 47113, 47123; Sec. 1101(b), Pub. L. 114-94, 129 Stat. 1312, 1324 (23 U.S.C. 101 note); Sec. 150, Pub. L. 115-254, 132 Stat. 3215 (23 U.S.C. 101 note); Pub. L. 117-58, 135 Stat. 429 (23 U.S.C. 101 note).

Source

Source: 64 FR 5126, Feb. 2, 1999, unless otherwise noted.

Amendments

[64 FR 5126, Feb. 2, 1999, as amended at 76 FR 5098, Jan. 28, 2011; 79 FR 59595, Oct. 2, 2014; 89 FR 24967, Apr. 9, 2024; 90 FR 47981, Oct. 3, 2025]

§26.53. What are the good faith efforts procedures recipients follow in situations where there are contract goals?

49 C.F.R. § 26.53

(a)
When you have established a DBE contract goal, you must award the contract only to a bidder/offeror who makes good faith efforts to meet it. You must determine that a bidder/offeror has made good faith efforts if the bidder/offeror does either of the following things:
(1)
Documents that it has obtained enough DBE participation to meet the goal; or
(2)
Documents that it made adequate good faith efforts to meet the goal, even though it did not succeed in obtaining enough DBE participation to do so. If the bidder/offeror does document adequate good faith efforts, you must not deny award of the contract on the basis that the bidder/offeror failed to meet the goal. See appendix A of this part for guidance in determining the adequacy of a bidder/offeror's good faith efforts.
(b)
In your solicitations for DOT-assisted contracts for which a contract goal has been established, you must require the following:
(1)
Award of the contract will be conditioned on meeting the requirements of this section;
(2)
All bidders or offerors will be required to submit the following information to the recipient, at the time provided in paragraph (b)(3) of this section:
(i)
The names and addresses of DBE firms that will participate in the contract;
(ii)
A description of the work that each DBE will perform. To count toward meeting a goal, each DBE firm must be certified in a NAICS code applicable to the kind of work the firm would perform on the contract;
(iii)
The dollar amount of the participation of each DBE firm participating;
(iv)
Written documentation of the bidder/offeror's commitment to use a DBE subcontractor whose participation it submits to meet a contract goal; and
(v)
Written confirmation from each listed DBE firm that it is participating in the contract in the kind and amount of work provided in the prime contractor's commitment. Each DBE listed to perform work as a regular dealer or distributor must confirm its participation according to the requirements of paragraph (c)(1) of this section.
(vi)
If the contract goal is not met, evidence of good faith efforts (see Appendix A of this part). The documentation of good faith efforts must include copies of each DBE and non-DBE subcontractor quote submitted to the bidder when a non-DBE subcontractor was selected over a DBE for work on the contract; and
(3)
(i)
At your discretion, the bidder/offeror must present the information required by paragraph (b)(2) of this section—
(A)
Under sealed bid procedures, as a matter of responsiveness, or with initial proposals, under contract negotiation procedures; or
(B)
No later than 7 days after bid opening as a matter of responsibility. The 7 days shall be reduced to 5 days beginning January 1, 2017.
(ii)
Provided that, in a negotiated procurement, such as a procurement for professional services, the bidder/offeror may make a contractually binding commitment to meet the goal at the time of bid submission or the presentation of initial proposals but provide the information required by paragraph (b)(2) of this section before the final selection for the contract is made by the recipient. This paragraph (b)(3)(ii) does not apply to a design-build procurement, which must follow the provisions in paragraph (e) of this section.
(c)
You must make sure all information is complete and accurate and adequately documents the bidder/offeror's good faith efforts before committing yourself to the performance of the contract by the bidder/offeror.
(1)
For each DBE listed as a regular dealer or distributor you must make a preliminary counting determination to assess its eligibility for 60 or 40 percent credit, respectively, of the cost of materials and supplies based on its demonstrated capacity and intent to perform as a regular dealer or distributor, as defined in § 26.55(e)(2)(iv)(A), (B), and (C) and (e)(3) under the contract at issue. Your preliminary determination shall be made based on the DBE's written responses to relevant questions and its affirmation that its subsequent performance of a commercially useful function will be consistent with the preliminary counting of such participation. Where the DBE supplier does not affirm that its participation will meet the specific requirements of either a regular dealer or distributor, you are required to make appropriate adjustments in counting such participation toward the bidder's good faith efforts to meet the contract goal. The bidder is responsible for verifying that the information provided by the DBE supplier is consistent with the counting of such participation toward the contract goal.
(2)
[Reserved]
(d)
If you determine that the apparent successful bidder/offeror has failed to meet the requirements of paragraph (a) of this section, you must, before awarding the contract, provide the bidder/offeror an opportunity for administrative reconsideration.
(1)
As part of this reconsideration, the bidder/offeror must have the opportunity to provide written documentation or argument concerning the issue of whether it met the goal or made adequate good faith efforts to do so.
(2)
Your decision on reconsideration must be made by an official who did not take part in the original determination that the bidder/offeror failed to meet the goal or make adequate good faith efforts to do so.
(3)
The bidder/offeror must have the opportunity to meet in person with your reconsideration official to discuss the issue of whether it met the goal or made adequate good faith efforts to do so.
(4)
You must send the bidder/offeror a written decision on reconsideration, explaining the basis for finding that the bidder did or did not meet the goal or make adequate good faith efforts to do so.
(5)
The result of the reconsideration process is not administratively appealable to the Department of Transportation.
(e)
In a design-build contracting situation, in which the recipient solicits proposals to design and build a project with minimal-project details at time of letting, the recipient may set a DBE goal that proposers must meet by submitting a DBE Open-Ended DBE Performance Plan (OEPP) with the proposal. The OEPP replaces the requirement to provide the information required in paragraph (b) of this section that applies to design-bid-build contracts. To be considered responsive, the OEPP must include a commitment to meet the goal and provide details of the types of subcontracting work or services (with projected dollar amount) that the proposer will solicit DBEs to perform. The OEPP must include an estimated time frame in which actual DBE subcontracts would be executed. Once the design-build contract is awarded, the recipient must provide ongoing monitoring and oversight to evaluate whether the design-builder is using good faith efforts to comply with the OEPP and schedule. The recipient and the design-builder may agree to make written revisions of the OEPP throughout the life of the project, e.g., replacing the type of work items the design-builder will solicit DBEs to perform and/or adjusting the proposed schedule, as long as the design-builder continues to use good faith efforts to meet the goal.
(f)
(1)
(i)
You must require that a prime contractor not terminate a DBE or any portion of its work listed in response to paragraph (b)(2) of this section (or an approved substitute DBE firm per paragraph (g) of this section) without your prior written consent, unless you cause the termination or reduction. A termination includes any reduction or underrun in work listed for a DBE not caused by a material change to the prime contract by the recipient. This requirement applies to instances that include, but are not limited to, when a prime contractor seeks to perform work originally designated for a DBE subcontractor with its own forces or those of an affiliate, a non-DBE firm, or with another DBE firm.
(ii)
You must include in each prime contract a provision stating that:
(A)
The contractor must utilize the specific DBEs listed to perform the work and supply the materials for which each is listed unless the contractor obtains your written consent as provided in this paragraph (f); and
(B)
Unless your consent is provided under this paragraph (f), the prime contractor must not be entitled to any payment for work or material unless it is performed or supplied by the listed DBE.
(2)
You may provide such written consent only if you agree, for reasons stated in your concurrence document, that the prime contractor has good cause to terminate the listed DBE or any portion of its work.
(3)
Good cause does not exist if the prime contractor seeks to terminate a DBE or any portion of its work that it relied upon to obtain the contract so that the prime contractor can self-perform the work for which the DBE contractor was engaged, or so that the prime contractor can substitute another DBE or non-DBE contractor after contract award. For purposes of this paragraph (f)(3), good cause includes the following circumstances:
(i)
The listed DBE subcontractor fails or refuses to execute a written contract;
(ii)
The listed DBE subcontractor fails or refuses to perform the work of its subcontract in a way consistent with normal industry standards. Provided, however, that good cause does not exist if the failure or refusal of the DBE subcontractor to perform its work on the subcontract results from the bad faith or discriminatory action of the prime contractor;
(iii)
The listed DBE subcontractor fails or refuses to meet the prime contractor's reasonable, nondiscriminatory bond requirements;
(iv)
The listed DBE subcontractor becomes bankrupt, insolvent, or exhibits credit unworthiness;
(v)
The listed DBE subcontractor is ineligible to work on public works projects because of suspension and debarment proceedings pursuant to 2 CFR parts 180, 215, and 1200 or applicable State law;
(vi)
You have determined that the listed DBE subcontractor is not a responsible contractor;
(vii)
The listed DBE subcontractor voluntarily withdraws from the project and provides to you written notice of its withdrawal;
(viii)
The listed DBE is ineligible to receive DBE credit for the type of work required;
(ix)
A DBE owner dies or becomes disabled with the result that the listed DBE contractor is unable to complete its work on the contract; and
(x)
Other documented good cause that you determine compels the termination of the DBE subcontractor.
(4)
Before transmitting to you its request to terminate a DBE subcontractor or any portion of its work, the prime contractor must give notice in writing to the DBE subcontractor, with a copy to you sent concurrently, of its intent to request to terminate and the reason for the proposed request.
(5)
The prime contractor's written notice must give the DBE 5 days to respond, advising you and the contractor of the reasons, if any, why it objects to the proposed termination of its subcontract/or portion thereof and why you should not approve the prime contractor's request. If required in a particular case as a matter of public necessity (e.g., safety), you may provide a response period shorter than 5 days.
(6)
In addition to post-award terminations, the provisions of this section apply to pre-award deletions or changes to DBEs or their listed work put forward by offerors in negotiated procurements.
(g)
When a DBE subcontractor or any portion of its work is terminated by the prime contractor as provided in paragraph (f) of this section, or the firm fails to complete its work on the contract for any reason, including when work committed to a DBE is not countable or reduced due to overestimations made prior to award, the prime contractor must use good faith efforts to include additional DBE participation to the extent needed to meet the contract goal. The good faith efforts shall be documented by the contractor. If the recipient requests documentation under this provision, the contractor shall submit the documentation within 7 days, which may be extended for an additional 7 days, if necessary, at the request of the contractor, and the recipient shall provide a written determination to the contractor stating whether or not good faith efforts have been demonstrated.
(h)
You must include in each prime contract the contract clause required by § 26.13(b) stating that failure by the contractor to carry out the requirements of this part is a material breach of the contract and may result in the termination of the contract or such other remedies set forth in that section you deem appropriate if the prime contractor fails to comply with the requirements of this section.
(i)
You must apply the requirements of this section to DBE bidders/offerors for prime contracts. In determining whether a DBE bidder/offeror for a prime contract has met a contract goal, you count the work the DBE has committed to performing with its own forces as well as the work that it has committed to be performed by DBE subcontractors and DBE suppliers.
(j)
You must require the contractor awarded the contract to make available upon request a copy of all DBE subcontracts. The subcontractor shall ensure that all subcontracts or an agreement with DBEs to supply labor or materials require that the subcontract and all lower tier subcontractors be performed in accordance with this part's provisions.
Notes, amendments, and revision history

Amendments

[64 FR 5126, Feb. 2, 1999, as amended at 76 FR 5098, Jan. 28, 2011; 79 FR 59595, Oct. 2, 2014; 89 FR 24967, Apr. 9, 2024; 89 FR 55089, July 3, 2024]

Authority

Authority: 23 U.S.C. 304 and 324; 42 U.S.C. 2000d, et seq.; 49 U.S.C. 47113, 47123; Sec. 1101(b), Pub. L. 114-94, 129 Stat. 1312, 1324 (23 U.S.C. 101 note); Sec. 150, Pub. L. 115-254, 132 Stat. 3215 (23 U.S.C. 101 note); Pub. L. 117-58, 135 Stat. 429 (23 U.S.C. 101 note).

Source

Source: 64 FR 5126, Feb. 2, 1999, unless otherwise noted.

Amendments

[64 FR 5126, Feb. 2, 1999, as amended at 76 FR 5098, Jan. 28, 2011; 79 FR 59595, Oct. 2, 2014; 89 FR 24967, Apr. 9, 2024; 89 FR 55089, July 3, 2024]