§213.59. Elevation of curved track; runoff.
49 C.F.R. § 213.59
If a curve is elevated, the full elevation shall be provided throughout the curve, unless physical conditions do not permit. If elevation runoff occurs in a curve, the actual minimum elevation shall be used in computing the maximum allowable posted timetable operating speed for that curve under § 213.57(b).
Elevation runoff shall be at a uniform rate, within the limits of track surface deviation prescribed in § 213.63, and it shall extend at least the full length of the spirals. If physical conditions do not permit a spiral long enough to accommodate the minimum length of runoff, part of the runoff may be on tangent track.
Notes, amendments, and revision history
Amendments
[63 FR 34029, June 22, 1998, as amended at 78 FR 16101, Mar. 13, 2013]
Authority
Authority: 49 U.S.C. 20102-20114 and 20142; 28 U.S.C. 2461 note; and 49 CFR 1.89.
Source
Source: 63 FR 34029, June 22, 1998, unless otherwise noted.
Amendments
[63 FR 34029, June 22, 1998, as amended at 78 FR 16101, Mar. 13, 2013]