§192.619. Maximum allowable operating pressure: Steel or plastic pipelines. — Inbound Citations

49 C.F.R. § 192.619

Cited by 28 regulations in release Current.

Citations to 49 U.S.C. § 192.619 as a whole

  • (c) Unless otherwise specified, if an operator submits, pursuant to § 192.8, § 192.9, § 192.13, § 192.179, § 192.319, § 192.461, § 192.506, § 192.607, § 192.619, § 192.624, § 192.632, § 192.634, § 192.636, § 192.710, § 192.712, § 192.714, § 192.745, § 192.917, § 192.921, § 192.927, § 192.933, or § 192.937, a notification for use of a different integrity assessment method, analytical method, compliance period, sampling approach, pipeline material, or technique (e.g., “other technology” or “alternative equivalent technology”) than otherwise prescribed in those sections, that notification must be submitted to PHMSA for review at least 90 days in advance of using the other method, approach, compliance timeline, or technique. An operator may proceed to use the other method, approach, compliance timeline, or technique 91 days after submitting the notification unless it receives a letter from the Associate Administrator for Pipeline Safety informing the operator that PHMSA objects to the proposal or that PHMSA requires additional time and/or more information to conduct its review.
  • (1) It has been tested in accordance with this subpart and § 192.619 to substantiate the maximum allowable operating pressure; and
  • (d) Except as provided in § 192.555(c), a new maximum allowable operating pressure established under this subpart may not exceed the maximum that would be allowed under §§ 192.619 and 192.621 for a new segment of pipeline constructed of the same materials in the same location. However, when uprating a steel pipeline, if any variable necessary to determine the design pressure under the design formula (§ 192.105) is unknown, the MAOP may be increased as provided in § 192.619(a)(1).
  • (c) After complying with paragraph (b) of this section, an operator may increase the maximum allowable operating pressure of a segment of pipeline constructed before September 12, 1970, to the highest pressure that is permitted under § 192.619, using as test pressure the highest pressure to which the segment of pipeline was previously subjected (either in a strength test or in actual operation).
  • (a) If a class location change on a transmission pipeline occurs after October 5, 2022, and results in pipe replacement, of 2 or more miles, in the aggregate, within any 5 contiguous miles within a 24-month period, to meet the maximum allowable operating pressure (MAOP) requirements in § 192.611, § 192.619, or § 192.620, then the requirements in §§ 192.179, 192.634, and 192.636, as applicable, apply to the new class location, and the operator must install valves, including rupture-mitigation valves (RMV) or alternative equivalent technologies, as necessary, to comply with those sections. Such valves must be installed within 24 months of the class location change in accordance with the timing requirement in § 192.611(d) for compliance after a class location change.
  • (5) Establish a public education program under § 192.616;

Citations to §192.619(a)

  • (b) If a segment of pipeline is determined to be in unsatisfactory condition but no immediate hazard exists, the operator shall initiate a program to recondition or phase out the segment involved, or, if the segment cannot be reconditioned or phased out, reduce the maximum allowable operating pressure in accordance with § 192.619 (a) and (b).
  • (e) Notwithstanding the requirements in paragraphs (a) through (d) of this section, operators of onshore steel transmission pipelines that meet the criteria specified in § 192.624(a) must establish and document the maximum allowable operating pressure in accordance with § 192.624.
  • (a) An operator calculates the alternative maximum allowable operating pressure by using different factors in the same formulas used for calculating maximum allowable operating pressure under § 192.619(a) as follows:
    (1) In determining the alternative design pressure under § 192.105, use a design factor determined in accordance with § 192.111(b), (c), or (d) or, if none of these paragraphs apply, in accordance with the following table:
    (i) For facilities installed prior to December 22, 2008, for which § 192.111(b), (c), or (d) applies, use the following design factors as alternatives for the factors specified in those paragraphs: § 192.111(b)−0.67 or less; 192.111(c) and (d)−0.56 or less.
    (ii) [Reserved]
    (i) The design pressure of the weakest element in the pipeline segment, determined under subparts C and D of this part.
    (ii) The pressure obtained by dividing the pressure to which the pipeline segment was tested after construction by a factor determined in the following table:
  • (4) ASME/ANSI B31G-1991 (Reaffirmed 2004), Manual for Determining the Remaining Strength of Corroded Pipelines, 2004, (ASME/ANSI B31G); IBR approved for §§ 192.632(a); 192.712(b).
  • (4) For the purpose of identifying Type C lines in table 1 to paragraph (c)(2) of this section, if an operator has not calculated MAOP consistent with the methods at § 192.619(a) or (c)(1), the operator must either:
    (i) Calculate MAOP consistent with the methods at § 192.619(a) or (c)(1); or
    (ii) Use as a substitute for MAOP the highest operating pressure to which the segment was subjected during the preceding 5 operating years.
  • (6) Establish the MAOP of the line under § 192.619(a), (b), and (c);

Citations to §192.619(a)(1)

  • (d) Except as provided in § 192.555(c), a new maximum allowable operating pressure established under this subpart may not exceed the maximum that would be allowed under §§ 192.619 and 192.621 for a new segment of pipeline constructed of the same materials in the same location. However, when uprating a steel pipeline, if any variable necessary to determine the design pressure under the design formula (§ 192.105) is unknown, the MAOP may be increased as provided in § 192.619(a)(1).

Citations to §192.619(a)(2)

Citations to §192.619(a)(2)(ii)

Citations to §192.619(b)

Citations to §192.619(c)

Citations to §192.619(c)(1)

  • (4) For the purpose of identifying Type C lines in table 1 to paragraph (c)(2) of this section, if an operator has not calculated MAOP consistent with the methods at § 192.619(a) or (c)(1), the operator must either:
    (i) Calculate MAOP consistent with the methods at § 192.619(a) or (c)(1); or
    (ii) Use as a substitute for MAOP the highest operating pressure to which the segment was subjected during the preceding 5 operating years.

Citations to §192.619(d)

Citations to §192.619(e)