§192.611. Change in class location: Confirmation or revision of maximum allowable operating pressure. — Inbound Citations
49 C.F.R. § 192.611
Statutory Authority
Cited by 12 regulations in release Current.
Citations to 49 U.S.C. § 192.611 as a whole
-
(a) If a class location change on a transmission pipeline occurs after October 5, 2022, and results in pipe replacement, of 2 or more miles, in the aggregate, within any 5 contiguous miles within a 24-month period, to meet the maximum allowable operating pressure (MAOP) requirements in § 192.611, § 192.619, or § 192.620, then the requirements in §§ 192.179, 192.634, and 192.636, as applicable, apply to the new class location, and the operator must install valves, including rupture-mitigation valves (RMV) or alternative equivalent technologies, as necessary, to comply with those sections. Such valves must be installed within 24 months of the class location change in accordance with the timing requirement in § 192.611(d) for compliance after a class location change.
-
(1) An operator may operate a segment of pipeline found to be in satisfactory condition, considering its operating and maintenance history, at the highest actual operating pressure to which the segment was subjected during the 5 years preceding the applicable date in the second column of the table in paragraph (a)(3) of this section. An operator must still comply with § 192.611.(2) For any Type C gas gathering pipeline under § 192.9 existing on or before May 16, 2022, that was not previously subject to this part and the operator cannot determine the actual operating pressure of the pipeline for the 5 years preceding May 16, 2023, the operator may establish MAOP using other criteria based on a combination of operating conditions, other tests, and design with approval from PHMSA. The operator must notify PHMSA in accordance with § 192.18. The notification must include the following information:(i) The proposed MAOP of the pipeline;(ii) Description of pipeline segment for which alternate methods are used to establish MAOP, including diameter, wall thickness, pipe grade, seam type, location, endpoints, other pertinent material properties, and age;(iii) Pipeline operating data, including operating history and maintenance history;(iv) Description of methods being used to establish MAOP;(v) Technical justification for use of the methods chosen to establish MAOP; and
-
(i) Where the pipeline segment has had a class location change in accordance with § 192.611, and records documenting diameter, wall thickness, seam type, grade (minimum yield strength and ultimate tensile strength), and pressure tests are not documented in traceable, verifiable, and complete records, the operator must reduce the pipeline segment MAOP as follows:(A) For pipeline segments where a class location changed from Class 1 to Class 2, from Class 2 to Class 3, or from Class 3 to Class 4, reduce the pipeline MAOP to no greater than the highest actual operating pressure sustained by the pipeline during the 5 years preceding October 1, 2019, divided by 1.39 for Class 1 to Class 2, 1.67 for Class 2 to Class 3, and 2.00 for Class 3 to Class 4.(B) For pipeline segments where a class location changed from Class 1 to Class 3, reduce the pipeline MAOP to no greater than the highest actual operating pressure sustained by the pipeline during the 5 years preceding October 1, 2019, divided by 2.00.
-
(v) Metal loss that is located at a crossing of another pipeline, is in an area with widespread circumferential corrosion, or could affect a girth weld, and that has a predicted failure pressure, determined in accordance with § 192.712(b), less than 1.39 times the MAOP for Class 1 locations or where Class 2 locations contain Class 1 pipe that has been uprated in accordance with § 192.611, or less than 1.50 times the MAOP for all other Class 2 locations and all Class 3 and 4 locations.
-
(ii) Performing a spike pressure test in accordance with § 192.506 based upon the class location of the pipeline segment. The MAOP must be no greater than the test pressure specified in § 192.506(a) divided by: 1.39 for Class 1 locations and Class 2 locations that contain Class 1 pipe that has been uprated in accordance with § 192.611; and 1.50 for all other Class 2 locations and all Class 3 and Class 4 locations. An operator must repair any test failures due to SCC by replacing the pipe segment and re-testing the segment until the pipe passes the test without failures (such as pipe seam or gasket leaks, or a pipe rupture). At a minimum, an operator must repair pipe segments that pass the pressure test but have SCC present by grinding the segment in accordance with paragraph (b)(4)(i) of this section.
-
(v) Metal loss that is located at a crossing of another pipeline, or is in an area with widespread circumferential corrosion, or could affect a girth weld, that has a predicted failure pressure, determined in accordance with § 192.712(b), of less than 1.39 times the MAOP for Class 1 locations or where Class 2 locations contain Class 1 pipe that has been uprated in accordance with § 192.611, or less than 1.50 times the MAOP for all other Class 2 locations and all Class 3 and 4 locations.
Citations to §192.611(a)
-
(8) A Class 1 and Class 2 location can be upgraded one class due to class changes per § 192.611(a). All class location changes from Class 1 to Class 2 and from Class 2 to Class 3 must have all anomalies evaluated and remediated per: The “original pipeline class grade” § 192.620(d)(11) anomaly repair requirements; and all anomalies with a wall loss equal to or greater than 40 percent must be excavated and remediated. Pipelines in Class 4 may not operate at an alternative MAOP.
Citations to §192.611(a)(4)
-
(vii) Confirmation of maximum allowable operating pressure pursuant to § 192.611(a)(4) is not authorized for gathering lines or distribution lines.
-
(v) Any area containing an eligible Class 3 segment with a maximum allowable operating pressure confirmed in accordance with § 192.611(a)(4).
Citations to §192.611(a)(4)(i)(1)
-
(G) Perform a coating survey of the eligible Class 3 segment and remediate in accordance with the requirements in § 192.461(f) through (h) if any of the following in paragraphs (a)(4)(i)(1) through (5) are present:(1) Ineffective external coating, as defined in § 192.457;(2) Adequacy of cathodic protection is measured using a minimum negative (cathodic) polarization voltage shift of 100 millivolts in accordance with paragraph I.A.(3) of appendix D to this part;(3) Linear anodes are required to maintain cathodic protection in accordance with § 192.463;(4) Tape wraps or shrink sleeves; or(5) A history of shielding pipe from cathodic protection.
Citations to §192.611(a)(5)
-
(G) Perform a coating survey of the eligible Class 3 segment and remediate in accordance with the requirements in § 192.461(f) through (h) if any of the following in paragraphs (a)(4)(i)(1) through (5) are present:(1) Ineffective external coating, as defined in § 192.457;(2) Adequacy of cathodic protection is measured using a minimum negative (cathodic) polarization voltage shift of 100 millivolts in accordance with paragraph I.A.(3) of appendix D to this part;(3) Linear anodes are required to maintain cathodic protection in accordance with § 192.463;(4) Tape wraps or shrink sleeves; or(5) A history of shielding pipe from cathodic protection.
Citations to §192.611(d)
-
(a) If a class location change on a transmission pipeline occurs after October 5, 2022, and results in pipe replacement, of 2 or more miles, in the aggregate, within any 5 contiguous miles within a 24-month period, to meet the maximum allowable operating pressure (MAOP) requirements in § 192.611, § 192.619, or § 192.620, then the requirements in §§ 192.179, 192.634, and 192.636, as applicable, apply to the new class location, and the operator must install valves, including rupture-mitigation valves (RMV) or alternative equivalent technologies, as necessary, to comply with those sections. Such valves must be installed within 24 months of the class location change in accordance with the timing requirement in § 192.611(d) for compliance after a class location change.