§1105.8. Historic Reports. — Inbound Citations
49 C.F.R. § 1105.8
Statutory Authority
Cited by 10 regulations in release Current.
Citations to 49 C.F.R. § 1105.8 as a whole
-
(b) In preparing an Environmental Assessment, OEA will verify and independently analyze the Environmental Report and/or Historic Report and related material submitted by an applicant pursuant to sections 1105.7 and 1105.8. The Environmental Assessment will discuss relevant environmental and historic preservation issues. OEA will serve copies of the Environmental Assessment on all parties to the proceeding and appropriate federal, state, and local agencies, and will announce its availability to the public through a notice in the Federal Register. In the case of abandonment applications processed under 49 U.S.C. 10903, the availability of the Environmental Assessment must be announced in the applicant's Notice of Intent filed under 49 CFR 1152.21. The deadline for submission of comments on the Environmental Assessment will generally be within 30 days of its service (15 days in the case of a notice of abandonment under 49 CFR 1152.50). The comments received will be addressed in the Board's decision. A supplemental Environmental Assessment may be issued where appropriate.
-
(c) No environmental documentation will normally be prepared (although a Historic Report may be required under section 1105.8) for the following actions:(1) Any action that does not result in significant changes in carrier operations (i.e., changes that do not exceed the thresholds established in section 1105.7(e) (4) or (5)), including (but not limited to) all of the following actions that meet this criterion:(i) An acquisition, lease, or operation under 49 U.S.C. 10901, 10902, or 10907, or consolidation, merger, or acquisition of control under 49 U.S.C. 11323 and 14303 that does not come within subsection (b)(4) of this section.(ii) Transactions involving corporate changes (such as a change in the ownership or the operator, or the issuance of securities or reorganization) including grants of authority to hold position as an officer or director;(iii) Declaratory orders, interpretation or clarification of operating authority, substitution of an applicant, name changes, and waiver of lease and interchange regulations;(iv) Pooling authorizations, approval of rate bureau agreements, and approval of shipper antitrust immunity;(v) Determinations of the fact of competition;(2) Rate, fare, and tariff actions;(3) Common use of rail terminals and trackage rights;(4) Discontinuance of rail freight service under a modified certificate issued pursuant to 49 CFR 1150.21;(5) Discontinuance of trackage rights where the affected line will continue to be operated; and(6) A rulemaking, policy statement, or legislative proposal that has no potential for significant environmental impacts.
-
(e) The Environmental Report shall include all of the information specified in this paragraph, except to the extent that applicant explains why any portion(s) are inapplicable. If an historic report is required under § 1105.8, the Environmental Report should also include the Historic Report required by that section.(1) Describe the proposed action, including commodities transported, the planned disposition (if any) of any rail line and other structures that may be involved, and any possible changes in current operations or maintenance practices. Also describe any reasonable alternatives to the proposed action. Include a readable, detailed map and drawings clearly delineating the project.(2) Describe the effects of the proposed action on regional or local transportation systems and patterns. Estimate the amount of traffic (passenger or freight) that will be diverted to other transportation systems or modes as a result of the proposed action.(i) Based on consultation with local and/or regional planning agencies and/or a review of the official planning documents prepared by such agencies, state whether the proposed action is consistent with existing land use plans. Describe any inconsistencies.(ii) Based on consultation with the U.S. Soil Conservation Service, state the effect of the proposed action on any prime agricultural land.(iii) If the action affects land or water uses within a designated coastal zone, include the coastal zone information required by § 1105.9.(iv) If the proposed action is an abandonment, state whether or not the right-of-way is suitable for alternative public use under 49 U.S.C. 10905 and explain why.(iii) State whether the proposed action will result in an increase or decrease in overall energy efficiency and explain why.(iv) If the proposed action will cause diversions from rail to motor carriage of more than:(A) 1,000 rail carloads a year; or(B) An average of 50 rail carloads per mile per year for any part of the affected line, quantify the resulting net change in energy consumption and show the data and methodology used to arrive at the figure given. To minimize the production of repetitive data, the information on overall energy efficiency in § 1105.7(e)(4)(iii) need not be supplied if the more detailed information in § 1105.7(e)(4)(iv) is required.(i) If the proposed action will result in either:(A) An increase in rail traffic of at least 100 percent (measured in gross ton miles annually) or an increase of at least eight trains a day on any segment of rail line affected by the proposal, or(B) An increase in rail yard activity of at least 100 percent (measured by carload activity), or(C) An average increase in truck traffic of more than 10 percent of the average daily traffic or 50 vehicles a day on any affected road segment, quantify the anticipated effect on air emissions. For a proposal under 49 U.S.C. 10901 (or 10502) to construct a new line or reinstitute service over a previously abandoned line, only the eight train a day provision in subsection (5)(i)(A) will apply.(ii) If the proposed action affects a class I or nonattainment area under the Clean Air Act, and will result in either:(A) An increase in rail traffic of at least 50 percent (measured in gross ton miles annually) or an increase of at least three trains a day on any segment of rail line,(B) An increase in rail yard activity of at least 20 percent (measured by carload activity), or(C) An average increase in truck traffic of more than 10 percent of the average daily traffic or 50 vehicles a day on a given road segment, then state whether any expected increased emissions are within the parameters established by the State Implementation Plan. However, for a rail construction under 49 U.S.C. 10901 (or 49 U.S.C. 10502), or a case involving the reinstitution of service over a previously abandoned line, only the three train a day threshold in this item shall apply.(iii) If transportation of ozone depleting materials (such as nitrogen oxide and freon) is contemplated, identify: the materials and quantity; the frequency of service; safety practices (including any speed restrictions); the applicant's safety record (to the extent available) on derailments, accidents and spills; contingency plans to deal with accidental spills; and the likelihood of an accidental release of ozone depleting materials in the event of a collision or derailment.(6) If any of the thresholds identified in item (5)(i) of this section are surpassed, state whether the proposed action will cause:(i) An incremental increase in noise levels of three decibels Ldn or more; or(ii) If so, identify sensitive receptors (e.g., schools, libraries, hospitals, residences, retirement communities, and nursing homes) in the project area, and quantify the noise increase for these receptors if the thresholds are surpassed.(i) Describe any effects of the proposed action on public health and safety (including vehicle delay time at railroad grade crossings).(ii) If hazardous materials are expected to be transported, identify: the materials and quantity; the frequency of service; whether chemicals are being transported that, if mixed, could react to form more hazardous compounds; safety practices (including any speed restrictions); the applicant's safety record (to the extent available) on derailments, accidents and hazardous spills; the contingency plans to deal with accidental spills; and the likelihood of an accidental release of hazardous materials.(iii) If there are any known hazardous waste sites or sites where there have been known hazardous materials spills on the right-of-way, identify the location of those sites and the types of hazardous materials involved.(i) Based on consultation with the U.S. Fish and Wildlife Service, state whether the proposed action is likely to adversely affect endangered or threatened species or areas designated as a critical habitat, and if so, describe the effects.(ii) State whether wildlife sanctuaries or refuges, National or State parks or forests will be affected, and describe any effects.(i) Based on consultation with State water quality officials, state whether the proposed action is consistent with applicable Federal, State or local water quality standards. Describe any inconsistencies.(ii) Based on consultation with the U.S. Army Corps of Engineers, state whether permits under section 404 of the Clean Water Act (33 U.S.C. 1344) are required for the proposed action and whether any designated wetlands or 100-year flood plains will be affected. Describe the effects.(iii) State whether permits under section 402 of the Clean Water Act (33 U.S.C. 1342) are required for the proposed action. (Applicants should contact the U.S. Environmental Protection Agency or the state environmental protection or equivalent agency if they are unsure whether such permits are required.)(10) Describe any actions that are proposed to mitigate adverse environmental impacts, indicating why the proposed mitigation is appropriate.(11) The following additional information should be included for rail construction proposals (including connecting track construction):(i) Describe the proposed route(s) by State, county, and subdivision, including a plan view, at a scale not to exceed 1:24,000 (7 1/2 minute U.S.G.S. quadrangle map), clearly showing the relationship to the existing transportation network (including the location of all highway and road crossings) and the right-of-way according to ownership and land use requirements.(ii) Describe any alternative routes considered, and a no-build alternative (or why this would not be applicable), and explain why they were not selected.(iii) Describe the construction plans, including the effect on the human environment, labor force requirements, the location of borrow pits, if any, and earthwork estimates.(iv) Describe in detail the rail operations to be conducted upon the line, including estimates of freight (carloads and tonnage) to be transported, the anticipated daily and annual number of train movements, number of cars per train, types of cars, motive power requirements, proposed speeds, labor force, and proposed maintenance-of-way practices.(v) Describe the effects, including indirect or down-line impacts, of the new or diverted traffic over the line if the thresholds governing energy, noise and air impacts in § 1105.7(e)(4), (5), or (6) are met.(vi) Describe the effects, including impacts on essential public services (e.g., fire, police, ambulance, neighborhood schools), public roads, and adjoining properties, in communities to be traversed by the line.
-
(d) An environmental and historic report required under 49 CFR 1105.7 and 1105.8 will not be required where a petitioner engages a third-party consultant who is approved by OEA and acts under OEA's direction and supervision in preparing the EA or EIS. In such a case, the third-party consultant must act on behalf of the Board, working under OEA's direction to collect the environmental information that is needed and to compile it into a draft EA or EIS, which is prepared under OEA's direction and then submitted to OEA for its final review and approval. See 49 CFR 1105.10(d).
-
-
(f) The applicant shall submit information regarding the environmental impact of the proposed abandonment or discontinuance in compliance with §§ 1105.7 and 1105.8. If certain information required by the environmental regulations duplicates information required elsewhere in the application, the environmental information requirements may be met by a specific reference to the location of the information elsewhere in the application.
-
(c) Applicant must also submit an Environmental and/or Historic Report containing the information described at 49 CFR 1155.24(b), 1105.7, and 1105.8, to the extent applicable, at least 45 days prior to filing an application. OEA may reject any report that it deems inadequate. The environmental and historic reporting requirements that would otherwise apply are waived, however, if the applicant or the Board hires a third-party consultant, OEA approves the scope of the consultant's work, and the consultant works under OEA's supervision to prepare an EIS or other environmental documentation. In such a case, the consultant acts on behalf of the Board, working under OEA's direction to collect the needed environmental information and compile it into an EIS or other appropriate environmental documentation. See 49 U.S.C. 10909(h); 49 CFR 1155.24(c).
-
(c) The applicant shall certify that it has submitted an Environmental and/or Historic Report containing the information in 49 CFR 1155.24(b), 1105.7, and 1105.8, to the extent applicable, if an Environmental and/or Historic Report is required. See 49 CFR 1155.20(c).
-
(b) An applicant for a land-use-exemption permit must submit an Environmental Report, at least 45 days prior to filing a land-use-exemption-permit application, containing the information described at 49 CFR 1105.7 to the extent applicable to solid waste rail transfer facilities. Applicants shall concurrently file a Historic Report containing the information at 49 CFR 1105.8 if applicable. The Environmental Report must also contain a discussion of the five factors for consideration listed at 49 U.S.C. 10909(d)(1) through (5) and address any associated environmental impacts as they relate to the facility for which a land-use-exemption permit is sought.
Citations to §1105.8(d)
-
(b) The environmental regulations at 49 CFR part 1105 must be complied with fully. An environmental report containing the information specified at 49 CFR 1105.7(e), as well as an historic report containing the information specified at 49 CFR 1105.8(d), must be filed either before or at the same time as the notice of exemption is filed. See 49 CFR 1105.7(a). The entity seeking the exemption authority must also serve copies of the environmental report on the agencies listed at 49 CFR 1105.7(b). Because the environmental report must include a certification that appropriate agencies have been consulted in its preparation (see 49 CFR 1105.7(c)), parties should begin environmental and historic consultations well before the notice of exemption is filed. Environmental requirements may be waived or modified where a petitioner demonstrates in writing that such action is appropriate. See 49 CFR 1105.10(c). It is to the advantage of parties to consult with the Board's Office of Environmental Analysis (OEA) at the earliest possible date to begin environmental review.