§1105.10. Board procedures. — Inbound Citations
49 C.F.R. § 1105.10
Statutory Authority
Cited by 11 regulations in release Current.
Citations to 49 U.S.C. § 1105.10 as a whole
-
(d) The Board's procedures set forth in 49 CFR 1105.10 for implementation of environmental laws are controlling unless superseded by provisions in this Part.
Citations to §1105.10(a)
-
(3) The Board, through the Chief Counsel, shall publish a notice in the Federal Register within 20 days after the notice of exemption is received that describes the construction project and invites comments. OEA will then prepare an EA (or, if necessary, an EIS). The EA generally will be made available 15 days after the Federal Register notice. It will be served on all parties and appropriate agencies. Others may request a copy from OEA. The deadline for submission of comments on the EA will generally be within 30 days of its availability (see 49 CFR 1105.10(b)). If an EIS is prepared, the time frames and procedures set forth in 49 CFR 1105.10(a) generally will apply.
Citations to §1105.10(a)(1)
-
(2) Requests for waiver of § 1105.10(a)(1) must describe as completely as possible the anticipated environmental effects of the proposed action, and the timing of the proposed action, and show that all or part of the six month lead period is not appropriate.
-
(d) The Board may reclassify or modify these requirements for individual proceedings. For actions that generally require no environmental documentation, the Board may decide that a particular action has the potential for significant environmental impacts and that, therefore, the applicant should provide an environmental report and either an EA or an EIS will be prepared. For actions generally requiring an EA, the Board may prepare a full EIS where the probability of significant impacts from the particular proposal is high enough to warrant an EIS. Alternatively, in a rail construction, an applicant can seek to demonstrate (with supporting information addressing the pertinent aspects of § 1105.7(e)) that an EA, rather than an EIS, will be sufficient because the particular proposal is not likely to have a significant environmental impact. Any request for reclassification must be in writing and, in a rail construction, should be presented with the prefiling notice required by § 1105.10(a)(1) (or a request to waive that prefiling notice period).
Citations to §1105.10(a)(4)
-
(b) Interested persons, including the applicant, within 30 days after the close of OEA's environmental review, may comment on how the information developed during OEA's environmental review concerning the considerations at 49 U.S.C. 10909(d)(1) through (5) should be weighed with the remaining transportation and other relevant considerations at 49 U.S.C. 10909(d)(6) through (7). The parties will have an additional 15 days to respond to other parties' arguments. All pleadings shall be limited to weighing the information developed during OEA's environmental review with transportation and other concerns, and should not be directed towards the adequacy of OEA's environmental review. (Interested persons may comment on the adequacy of OEA's environmental review during the normal comment period for the EIS as provided in 49 CFR 1105.10(a)(4). See 49 CFR 1155.24(a).) All comments under this paragraph shall contain the information required in paragraphs (a)(1) through (2) of this section.
Citations to §1105.10(b)
-
(3) The Board, through the Chief Counsel, shall publish a notice in the Federal Register within 20 days after the notice of exemption is received that describes the construction project and invites comments. OEA will then prepare an EA (or, if necessary, an EIS). The EA generally will be made available 15 days after the Federal Register notice. It will be served on all parties and appropriate agencies. Others may request a copy from OEA. The deadline for submission of comments on the EA will generally be within 30 days of its availability (see 49 CFR 1105.10(b)). If an EIS is prepared, the time frames and procedures set forth in 49 CFR 1105.10(a) generally will apply.
Citations to §1105.10(c)
-
(b) The environmental regulations at 49 CFR part 1105 must be complied with fully. An environmental report containing the information specified at 49 CFR 1105.7(e), as well as an historic report containing the information specified at 49 CFR 1105.8(d), must be filed either before or at the same time as the notice of exemption is filed. See 49 CFR 1105.7(a). The entity seeking the exemption authority must also serve copies of the environmental report on the agencies listed at 49 CFR 1105.7(b). Because the environmental report must include a certification that appropriate agencies have been consulted in its preparation (see 49 CFR 1105.7(c)), parties should begin environmental and historic consultations well before the notice of exemption is filed. Environmental requirements may be waived or modified where a petitioner demonstrates in writing that such action is appropriate. See 49 CFR 1105.10(c). It is to the advantage of parties to consult with the Board's Office of Environmental Analysis (OEA) at the earliest possible date to begin environmental review.
Citations to §1105.10(d)
-
(d) An environmental and historic report required under 49 CFR 1105.7 and 1105.8 will not be required where a petitioner engages a third-party consultant who is approved by OEA and acts under OEA's direction and supervision in preparing the EA or EIS. In such a case, the third-party consultant must act on behalf of the Board, working under OEA's direction to collect the environmental information that is needed and to compile it into a draft EA or EIS, which is prepared under OEA's direction and then submitted to OEA for its final review and approval. See 49 CFR 1105.10(d).
-
(c) The Board strongly encourages applicants to use third-party contractors to assist OEA in preparing the appropriate environmental documentation in land-use-exemption-permit proceedings. See 49 CFR 1105.10(d). The environmental reporting requirements outlined above that would otherwise apply are waived if an applicant hires a third-party contractor, OEA approves the scope of the contractor's work, and the contractor works under OEA's direct supervision. See 49 CFR 1105.10(d). If an applicant does not hire an independent third-party contractor, the Board may hire a third-party contractor and charge the costs for the contractor to the applicant. See 49 U.S.C. 10909(h).
Citations to §1105.10(g)
-
(9) Where there has been full environmental review and no significant environmental issues have been raised or discovered, the Board, through the Chief Counsel, shall issue, on or before the effective date of the exemption, a final decision consisting of a Finding of No Significant Impact (FONSI) to show that the environmental record has been considered (see 49 CFR 1105.10(g)).