§925.103. Exceptions.
48 C.F.R. § 925.103
Nonavailabilty—
Individual determinations. Contracting officers may make the determination required by 48 CFR 25.103(b)(2)(i), provided such determination is factually supported in writing. If the contract is estimated to exceed $1 million, the Head of the Contracting Activity must approve the determination.
Proposals to add an article to the list of nonavailable articles at 48 CFR 25.104, with appropriate justifications, must be submitted for approval by the Senior Procurement Executive and submission to the appropriate council.
Notes, amendments, and revision history
Amendments
[74 FR 36366, July 22, 2009, as amended at 75 FR 69013, Nov. 10, 2010; 81 FR 45977, July 15, 2016]
Authority
Authority: 42 U.S.C. 7101 et seq. and 50 U.S.C. 2401 et seq.
Source
Source: 49 FR 12003, Mar. 28, 1984, unless otherwise noted.
Amendments
[74 FR 36366, July 22, 2009, as amended at 75 FR 69013, Nov. 10, 2010; 81 FR 45977, July 15, 2016]