§843.205. Contract clauses.

48 C.F.R. § 843.205

As authorized in the introductory text of clauses FAR 52.243-1, Changes—Fixed-Price; FAR 52.243-2, Changes—Cost-Reimbursement; and FAR 52.243-4, Changes, and in the prescription at FAR 43.205(c) for FAR 52.243-3, Changes—Time-and-Materials or Labor-Hours, the contracting officer may vary the period within which a contractor must assert its right to an equitable adjustment but the extended period shall not exceed 60 calendar days.