§52.249-14. Excusable Delays.
48 C.F.R. § 52.249-14
As prescribed in 49.505(b), insert the following clause in solicitations and contracts for supplies, services, construction, and research and development on a fee basis whenever a cost-reimbursement contract is contemplated. Also insert the clause in time-and-material contracts, and labor-hour contracts. When used in construction contracts, substitute the words “completion time” for “delivery schedule” in the last sentence of the clause.
Notes, amendments, and revision history
Amendments
[48 FR 42478, Sept. 19, 1983, as amended at 72 FR 27394, May 15, 2007]
Authority
Authority: 41 U.S.C. 1121(b); 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113.
Source
Source: 48 FR 42478, Sept. 19, 1983, unless otherwise noted.
Amendments
[48 FR 42478, Sept. 19, 1983, as amended at 72 FR 27394, May 15, 2007]