§52.249-10. Default (Fixed-Price Construction).
48 C.F.R. § 52.249-10
Alternate I (APR 1984). If the contract is for dismantling, demolition, or removal of improvements, substitute the following paragraph (a) for paragraph (a) of the basic clause:
Alternate II (APR 1984). If the contract is to be awarded during a period of national emergency, subparagraph (b)(1) below may be substituted for subparagraph (b)(1) of the basic clause:
Alternate III (APR 1984). If the contract is for dismantling, demolition, or removal of improvements and is to be awarded during a period of national emergency, substitute the following paragraph (a) for paragraph (a) of the basic clause. The following subparagraph (b)(1) may be substituted for subparagraph (b)(1) of the basic clause:
Notes, amendments, and revision history
Amendments
[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34762, July 3, 1995]
Authority
Authority: 41 U.S.C. 1121(b); 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113.
Source
Source: 48 FR 42478, Sept. 19, 1983, unless otherwise noted.
Amendments
[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34762, July 3, 1995]