US Codex
C.F.R.
Browse by date
Notes

§49.405. Completion by another contractor.

48 C.F.R. § 49.405

If the surety does not arrange for completion of the contract, the contracting officer normally will arrange for completion of the work by awarding a new contract based on the same plans and specifications. The new contract may be the result of sealed bidding or any other appropriate contracting method or procedure. The contracting officer shall exercise reasonable diligence to obtain the lowest price available for completion.
Notes, amendments, and revision history

Amendments

[48 FR 42447, Sept. 19, 1983, as amended at 50 FR 1746, Jan. 11, 1985; 50 FR 52429, Dec. 23, 1985]

Authority

Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113.

Source

Source: 48 FR 42447, Sept. 19, 1983, unless otherwise noted.

Amendments

[48 FR 42447, Sept. 19, 1983, as amended at 50 FR 1746, Jan. 11, 1985; 50 FR 52429, Dec. 23, 1985]