§42.503-1. Postaward conference arrangements.

48 C.F.R. § 42.503-1

(a)
The contracting officer who decides that a conference is needed is responsible for—
(1)
Establishing the time and place of the conference;
(2)
Preparing the agenda, when necessary;
(3)
Notifying appropriate Government representatives (e.g., contracting/contract administration office) and the contractor;
(4)
Designating or acting as the chairperson;
(5)
Conducting a preliminary meeting of Government personnel; and
(6)
Preparing a summary report of the conference.
(b)
When the contracting office initiates a conference, the arrangements may be made by that office or, at its request, by the contract administration office.
Notes, amendments, and revision history

Authority

Authority: 41 U.S.C. 1121(b); 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113.

Source

Source: 48 FR 42370, Sept. 19, 1983, unless otherwise noted.