§336.570. Contract clause.

48 C.F.R. § 336.570

(a)
The contracting officer shall insert the clause at 352.236-70, Design-Build Contracts, in all solicitations and contracts for all design-build requirements.
(b)
The contracting officer shall use Alternate I to the clause at 352.236-70, Design-Build Contracts, in all solicitations and contracts for construction when Fast-Track procedures are being used.
(c)
Due to the importance of maintaining consistency in the contractor's personnel during design-build construction, the contracting officer should consider including the clause at 352.237-75, Key personnel.
Notes, amendments, and revision history

Authority

Authority: 5 U.S.C. 301; 40 U.S.C. 121(c)(2).

Source

Source: 80 FR 72151, Nov. 18, 2015, unless otherwise noted.