§2448.103. Processing value engineering change proposals.

48 C.F.R. § 2448.103

Upon receipt of a Value Engineering Change Proposal (VECP), the Contracting Officer shall promptly forward it to the program office responsible for the contract, indicating:
(a)
The date the VECP was received;
(b)
The date by which the contractor must be informed of the government's acceptance or rejection of the VECP, unless additional time is required for evaluation;
(c)
The date by which the Contracting Officer must know of the technical officer's decision in order to timely accept or reject the VECP;
(d)
The need for information required to inform the contractor if the VECP is to be rejected or if additional time is needed to evaluate the VECP;
(e)
The potential for awarding concurrent, future, or collateral savings to the contractor, if the VECP is accepted;
(f)
That if the VECP is accepted, precise information will be needed with regard to the type of savings, and government costs, that can be expected from its acceptance;
(g)
The need for a procurement request setting forth the specification changes to be used in a contract modification accepting the VECP in whole or in part; and
(h)
The need for additional funds, if acceptance of the VECP will result in an increase in the cost of contract performance.