§242.1107. Contract clause.

48 C.F.R. § 242.1107

(b)
When using the clause at FAR 52.242-2, include the following instructions in the contract schedule—
(i)
Frequency and timing of reporting (normally 5 working days after each reporting period);
(ii)
Contract line items, exhibits, or exhibit line items requiring reports;
(iii)
Offices (with addressees/codes) where reports should be sent (always include the contracting office and contract administration office); and
(iv)
The following requirements for report content—
(A)
The problem, actual or potential, and its cause;
(B)
Items and quantities affected;
(C)
When the delinquency started or will start;
(D)
Actions taken to overcome the delinquency;
(E)
Estimated recovery date; and/or
(F)
Proposed schedule revision.