§217.7403. Policy.

48 C.F.R. § 217.7403

DoD policy is that undefinitized contract actions shall—
(a)
Be used only when—
(1)
The negotiation of a definitive contract action is not possible in sufficient time to meet the Government's requirements; and
(2)
The Government's interest demands that the contractor be given a binding commitment so that contract performance can begin immediately.
(b)
Be as complete and definite as practicable under the particular circumstances.