US Codex
C.F.R.
Browse by date
Notes

§11.502. Procedures.

48 C.F.R. § 11.502

(a)
Include the applicable liquidated damages clause and liquidated damages rates in solicitations when the contract will contain liquidated damages provisions.
(b)
Construction contracts with liquidated damages provisions must describe the rate(s) of liquidated damages assessed per day of delay. The rate(s) should include the estimated daily cost of Government inspection and superintendence. The rate(s) should also include an amount for other expected expenses associated with delayed completion such as—
(1)
Renting substitute property; or
(2)
Paying additional allowance for living quarters.
Notes, amendments, and revision history

Source

Source: 65 FR 46064, July 26, 2000, unless otherwise noted.

Authority

Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113.

Source

Source: 60 FR 48238, Sept. 18, 1995, unless otherwise noted.