§90.155. Time in which station must be placed in operation. — Inbound Citations

47 C.F.R. § 90.155

Cited by 5 regulations in release Current.

Citations to 47 U.S.C. § 90.155 as a whole

Citations to §90.155(b)

  • Each station authorized under this subpart to operate in the 769-775 MHz and 799-805 MHz frequency bands must be constructed and placed into operation within 12 months from the date of grant of the authorization, except for State channels. However, licensees may request a longer construction period, up to but not exceeding 5 years, pursuant to § 90.155(b). State channels are subject to the build-out requirements in § 90.529.
  • (f) Pursuant to § 90.155(b), the provisions of this section shall apply to local government entities applying for any frequency in the Public Safety Pool.