§107.260. Rated load test for cranes.

46 C.F.R. § 107.260

(a)
To meet the requirements in § 107.231(l), each crane must meet the following rated load test at both the maximum and minimum boom angles usually employed in material transfers over the side of the unit:
(b)
The weight of the hook, hook blocks, slings, rib, and other rigging, except the hoist rope, must be considered part of the load for the rated load test.
(c)
The rated load test must be performed—
(1)
When the crane is installed;
(2)
Each 60 months; and
(3)
After repairs or alterations to any structural component of the crane.
Notes, amendments, and revision history

Amendments

[CGD 73-251, 43 FR 56802, Dec. 4, 1978, as amended by USCG-1999-6216, 64 FR 53226, Oct. 1, 1999; USCG-1999-4976, 65 FR 6504, Feb. 9, 2000]

Authority

Authority: 43 U.S.C. 1333; 46 U.S.C. 3306, 3307, 3316; DHS Delegation No. 00170.1, Revision No. 01.4; § 107.05 also issued under the authority of 44 U.S.C. 3507.

Source

Source: CGD 73-251, 43 FR 56802, Dec. 4, 1978, unless otherwise noted.

Amendments

[CGD 73-251, 43 FR 56802, Dec. 4, 1978, as amended by USCG-1999-6216, 64 FR 53226, Oct. 1, 1999; USCG-1999-4976, 65 FR 6504, Feb. 9, 2000]