§2553.107. What must a sponsor do if it cannot meet its performance measures?
45 C.F.R. § 2553.107
When a sponsor finds it is not on track to meet its performance measures, the sponsor must develop a plan to get back on track or submit a request to AmeriCorps to amend its performance measures. AmeriCorps may limit when amendments to performance measure can be submitted, as well as limit the types of changes a sponsor can make to performance measures. The request must include all of the following:
Why the project is not on track to meet its performance requirements;
How the project has been tracking performance measures;
Evidence of corrective steps taken;
Any new proposed performance measures; and
A plan to ensure that the project will meet the new proposed measure(s).
Notes, amendments, and revision history
Amendments
[76 FR 20247, Apr. 12, 2011, as amended at 83 FR 64658, Dec. 17, 2018]
Source
Source: 76 FR 20247, Apr. 12, 2011, unless otherwise noted.
Authority
Authority: 42 U.S.C. 4950 et seq.
Source
Source: 64 FR 14135, Mar. 24, 1999, unless otherwise noted.
Amendments
[76 FR 20247, Apr. 12, 2011, as amended at 83 FR 64658, Dec. 17, 2018]