US Codex
C.F.R.
Browse by date
Notes

§418.23. Diversion of Rock Dam Ditch water. — Inbound Citations

43 C.F.R. § 418.23

Cited by 1 regulation in release Current.

Citations to 43 U.S.C. § 418.23 as a whole

  • (2) The MAD will be calculated annually to ensure an adequate water supply for all water right holders whose water use complies with their decreed entitlement and this part. The MAD is the maximum amount of water permitted to be diverted for irrigation use on the Project in that year. It is calculated to ensure full entitlements can be provided, but is expected to significantly exceed Project requirements. The MAD will be established by the Bureau at least 2 weeks before the start of each irrigation season. All releases of water from Lahontan Reservoir and diversions from the Truckee Canal (including any diversions from the Truckee Canal to Rock Dam Ditch) must be charged to the MAD except as provided in §§ 418.23 and 418.35 of this part.