§3809.598. What if the amount forfeited will not cover the cost of reclamation?
43 C.F.R. § 3809.598
If the amount forfeited is insufficient to pay for the full cost of reclamation, the operators and mining claimants are liable for the remaining costs as set forth in § 3809.116. BLM may complete or authorize completion of reclamation of the area covered by the financial guarantee and may recover from responsible persons all costs of reclamation in excess of the amount forfeited.
Notes, amendments, and revision history
Amendments
[66 FR 54862, Oct. 30, 2001]
Authority
Authority: 16 U.S.C. 1280; 30 U.S.C. 22; 30 U.S.C. 612; 43 U.S.C. 1201; and 43 U.S.C. 1732, 1733, 1740, 1781, and 1782.
Source
Source: 65 FR 70112, Nov. 21, 2000, unless otherwise noted.
Authority
Authority: 16 U.S.C. 3101 et seq.; 30 U.S.C. 22-42, 181 et seq., 301-306, 351-359, and 601 et seq.; 31 U.S.C. 9701; 40 U.S.C. 471 et seq.; 42 U.S.C. 6508; 43 U.S.C. 1701 et seq.; and Pub. L. No. 97-35, 95 Stat. 357.
Source
Source: 45 FR 13974, Mar. 3, 1980, unless otherwise noted.
Amendments
[66 FR 54862, Oct. 30, 2001]