§3809.21. When do I have to submit a notice?
43 C.F.R. § 3809.21
You must submit a complete notice of your operations 15 calendar days before you commence exploration causing surface disturbance of 5 acres or less of public lands on which reclamation has not been completed. See § 3809.301 for information on what you must include in your notice.
You must not segment a project area by filing a series of notices for the purpose of avoiding filing a plan of operations. See §§ 3809.300 through 3809.336 for regulations applicable to notice-level operations.
Notes, amendments, and revision history
Authority
Authority: 16 U.S.C. 1280; 30 U.S.C. 22; 30 U.S.C. 612; 43 U.S.C. 1201; and 43 U.S.C. 1732, 1733, 1740, 1781, and 1782.
Source
Source: 65 FR 70112, Nov. 21, 2000, unless otherwise noted.
Authority
Authority: 16 U.S.C. 3101 et seq.; 30 U.S.C. 22-42, 181 et seq., 301-306, 351-359, and 601 et seq.; 31 U.S.C. 9701; 40 U.S.C. 471 et seq.; 42 U.S.C. 6508; 43 U.S.C. 1701 et seq.; and Pub. L. No. 97-35, 95 Stat. 357.
Source
Source: 45 FR 13974, Mar. 3, 1980, unless otherwise noted.