§3602.27. When will BLM extend the term of a contract?
43 C.F.R. § 3602.27
BLM may grant a one-time extension of the contract not to exceed 1 year, if:
For contracts with terms over 90 days, BLM receives your written request between 30 and 90 days before the contract expires; or
For contracts with terms of 90 days or less, BLM receives your written request not later than 15 days before the contract expires; and
You show in writing that the delay in removing the mineral materials was due to causes beyond your control and was not due to your fault or negligence.
Notes, amendments, and revision history
Authority
Authority: 30 U.S.C. 601 et seq.; 43 U.S.C. 1201, 1701 et seq.; Sec. 2, Act of September 28, 1962 (Pub. L. 87-713, 76 Stat. 652).
Source
Source: 66 FR 58901, Nov. 23, 2001, unless otherwise noted.