§3282.7. What is the effective date of an initial participating area or revision of an existing participating area? — Inbound Citations

43 C.F.R. § 3282.7

Cited by 1 regulation in release Current.

Citations to 43 U.S.C. § 3282.7 as a whole

  • (c) The unit operator may submit a written request to BLM to delay a participation area revision decision when drilling multiple wells in the unit is actively pursued or the drilling is providing additional technical information. A delay will not affect the effective date of any participation area revision (see § 3282.7). The request must include:
    (1) The well locations;
    (2) Anticipated spud and completion dates of each well;
    (3) The timing of well testing and analyses of technical information; and
    (4) The anticipated date BLM will receive the participation area revision for review.