§3282.7. What is the effective date of an initial participating area or revision of an existing participating area? — Inbound Citations
43 C.F.R. § 3282.7
Statutory Authority
Cited by 1 regulation in release Current.
Citations to 43 U.S.C. § 3282.7 as a whole
-
(c) The unit operator may submit a written request to BLM to delay a participation area revision decision when drilling multiple wells in the unit is actively pursued or the drilling is providing additional technical information. A delay will not affect the effective date of any participation area revision (see § 3282.7). The request must include:(1) The well locations;(2) Anticipated spud and completion dates of each well;(3) The timing of well testing and analyses of technical information; and(4) The anticipated date BLM will receive the participation area revision for review.