§3275.13. How must the facility operator measure the geothermal resources?

43 C.F.R. § 3275.13

The facility operator must:
(a)
Measure all production, injection and utilization in accordance with methods and standards approved by BLM (see § 3275.15);
(b)
Maintain and test all metering equipment. If your equipment is defective or out of tolerance, you must promptly recalibrate, repair, or replace it; and
(c)
Determine the amount of production and/or utilization in accordance with methods and procedures approved by BLM (see § 3275.17).
Notes, amendments, and revision history

Authority

Authority: 30 U.S.C. 1001-1028; 43 U.S.C. 1701 et seq.; and Pub. L. 109-58.

Source

Source: 72 FR 24400, May 2, 2007, unless otherwise noted.