§3271.10. What do I need to start preparing a site and building and testing a utilization facility on Federal land leased for geothermal resources?
43 C.F.R. § 3271.10
In order to use Federal land to produce geothermal power, you must obtain a site license and construction permit from BLM before you start preparing the site. Send BLM a plan that shows what you want to do, and draft a proposed site license agreement that you think is fair and reasonable. We will review your proposal and decide whether to give you a permit and license to proceed with work on the site.
Notes, amendments, and revision history
Authority
Authority: 30 U.S.C. 1001-1028; 43 U.S.C. 1701 et seq.; and Pub. L. 109-58.
Source
Source: 72 FR 24400, May 2, 2007, unless otherwise noted.