For each existing production facility having an H2S concentration of 100 ppm or more in the gas stream, the operator shall calculate and submit the calculations to the authorized officer within 180 days of January 22, 1991, the 100 and, if applicable, the 500 ppm radii of exposure for all facilities to determine if the applicability criteria in
§ 3176.7(a) are met. Radii of exposure calculations shall not be required for oil or water flowlines. Further, if any of the applicability criteria (
§ 3176.7(a)) are met, the operator shall submit a complete Public Protection Plan which meets the requirements of
§ 3176.7(b)(2) to the authorized officer within 1 year of January 22, 1991. For production facilities constructed after January 22, 1991, and meeting the minimum concentration (100 ppm in gas stream), the operator shall report the radii of exposure calculations, and if the applicability criteria in
§ 3176.7(a) are met, submit a complete Public Protection Plan (
§ 3176.7(b)(2)) to the authorized officer within 60 days after completion of production facilities.