§3000.50. Limitations on time to institute suit to challenge a decision of the Secretary.
43 C.F.R. § 3000.50
No action challenging a decision of the Secretary involving any oil or gas lease (including decisions on offers or applications to lease) can be maintained unless such action is commenced or taken within 90 days after the final decision of the Secretary relating to such matter.
Notes, amendments, and revision history
Authority
Authority: 16 U.S.C. 3101 et seq.; 30 U.S.C. 181 et seq., 301-306, 351-359, and 601 et seq.; 31 U.S.C. 9701; 40 U.S.C. 471 et seq.; 42 U.S.C. 6508; 43 U.S.C. 1701 et seq.; and Pub. L. 97-35, 95 Stat. 357.
Source
Source: 89 FR 30963, Apr. 23, 2024, unless otherwise noted.