§11.80. Damage determination phase—general.

43 C.F.R. § 11.80

(a)
Requirement.
(1)
The authorized official shall make his damage determination by estimating the monetary damages resulting from the discharge of oil or release of a hazardous substance based upon the information provided in the Quantification phase and the guidance provided in this Damage Determination phase.
(2)
The Damage Determination phase consists of § 11.80—general; § 11.81—Restoration and Compensation Determination Plan; § 11.82—alternatives for restoration, rehabilitation, replacement, and/or acquisition of equivalent resources; § 11.83—cost estimating and valuation methodologies; and § 11.84—implementation guidance, of this part.
(b)
Purpose. The purpose of the Damage Determination phase is to establish the amount of money to be sought in compensation for injuries to natural resources resulting from a discharge of oil or release of a hazardous substance. The measure of damages is the cost of (i) restoration or rehabilitation of the injured natural resources to a condition where they can provide the level of services available at baseline, or (ii) the replacement and/or acquisition of equivalent natural resources capable of providing such services. Damages may also include, at the discretion of the authorized official, the compensable value of all or a portion of the services lost to the public for the time period from the discharge or release until the attainment of the restoration, rehabilitation, replacement, and/or acquisition of equivalent of baseline.
(c)
Steps in the Damage Determination phase. The authorized official shall develop a Restoration and Compensation Determination Plan, described in § 11.81 of this part. To prepare this Restoration and Compensation Determination Plan, the authorized official shall develop a reasonable number of possible alternatives for restoration, rehabilitation, replacement, and/or acquisition of equivalent resources and select, pursuant to the guidance of § 11.82 of this part, the most appropriate of those alternatives; and identify the cost estimating and valuation methodologies, described in § 11.83 of this part, that will be used to calculate damages. The guidance provided in § 11.84 of this part shall be followed in implementing the cost estimating and valuation methodologies. After public review of the Restoration and Compensation Determination Plan, the authorized official shall implement the Restoration and Compensation Determination Plan.
(d)
Completion of the Damage Determination phase. Upon completion of the Damage Determination phase, the type B assessment is completed. The results of the Damage Determination phase shall be documented in the Report of Assessment described in § 11.90 of this part.
Notes, amendments, and revision history

Amendments

[59 FR 14283, Mar. 25, 1994, as amended at 73 FR 75266, Oct. 2, 2008]

Authority

Authority: 42 U.S.C. 9651(c), as amended.

Source

Source: 51 FR 27725, Aug. 1, 1986, unless otherwise noted.

Amendments

[59 FR 14283, Mar. 25, 1994, as amended at 73 FR 75266, Oct. 2, 2008]

§11.81. Damage determination phase—restoration and compensation determination plan.

43 C.F.R. § 11.81

(a)
Requirement.
(1)
The authorized official shall develop a Restoration and Compensation Determination Plan that will list a reasonable number of possible alternatives for (i) the restoration or rehabilitation of the injured natural resources to a condition where they can provide the level of services available at baseline, or (ii) the replacement and/or acquisition of equivalent natural resources capable of providing such services, and, where relevant, the compensable value; select one of the alternatives and the actions required to implement that alternative; give the rationale for selecting that alternative; and identify the methodologies that will be used to determine the costs of the selected alternative and, at the discretion of the authorized official, the compensable value of the services lost to the public associated with the selected alternative.
(2)
The Restoration and Compensation Determination Plan shall be of sufficient detail to evaluate the possible alternatives for the purpose of selecting the appropriate alternative to use in determining the cost of baseline restoration, rehabilitation, replacement, and/or acquisition of equivalent resources, and, where relevant, the compensable value.
(b)
The authorized official shall use the guidance in §§ 11.82, 11.83, and 11.84 of this part to develop the Restoration and Compensation Determination Plan.
(c)
The authorized official shall list the methodologies he expects to use to determine the costs of all actions considered within the selected alternative and, where relevant, the compensable value of the lost services through the recovery period associated with the selected alternative. The methodologies to use in determining costs and compensable value are described in § 11.83 of this part.
(d)
(1)
The Restoration and Compensation Determination Plan shall be part of the Assessment Plan developed in subpart B of this part. If existing data are not sufficient to develop the Restoration and Compensation Determination Plan at the time that the overall Assessment Plan is made available for public review and comment, the Restoration and Compensation Determination Plan may be developed later, after the completion of the Injury Determination or Quantification phases.
(2)
If the Restoration and Compensation Determination Plan is prepared later than the Assessment Plan, it shall be made available separately for public review by any identified potentially responsible party, other natural resource trustees, other affected Federal or State agencies or Indian tribes, and any other interested members of the public for a period of no less than 30 calendar days. Reasonable extensions may be granted as appropriate.
(3)
Comments received from any identified potentially responsible party, other natural resource trustees, other affected Federal or State agencies or Indian tribes, or any other interested members of the public, together with responses to those comments, shall be included as part of the Report of Assessment, described in § 11.90 of this part.
(4)
Appropriate public review of the plan must be completed before the authorized official performs the methodologies listed in the Restoration and Compensation Determination Plan.
(e)
The Restoration and Compensation Determination Plan may be expanded to incorporate requirements from procedures required under other portions of CERCLA or the CWA or from other Federal, State, or tribal laws applicable to restoration, rehabilitation, replacement, and/or acquisition of the equivalent of the injured resources or may be combined with other plans for related purposes, so long as the requirements of this section are fulfilled.
Notes, amendments, and revision history

Amendments

[59 FR 14283, Mar. 25, 1994, as amended at 73 FR 57266, Oct. 2, 2008]

Authority

Authority: 42 U.S.C. 9651(c), as amended.

Source

Source: 51 FR 27725, Aug. 1, 1986, unless otherwise noted.

Amendments

[59 FR 14283, Mar. 25, 1994, as amended at 73 FR 57266, Oct. 2, 2008]

§11.82. Damage determination phase—alternatives for restoration, rehabilitation, replacement, and/or acquisition of equivalent resources.

43 C.F.R. § 11.82

(a)
Requirement. The authorized official shall develop a reasonable number of possible alternatives for (i) the restoration or rehabilitation of the injured natural resources to a condition where they can provide the level of services available at baseline, or (ii) the replacement and/or acquisition of equivalent natural resources capable of providing such services. For each possible alternative developed, the authorized official will identify an action, or set of actions, to be taken singly or in combination by the trustee agency to achieve the baseline restoration, rehabilitation, replacement, and/or acquisition of equivalent natural resources. The authorized official shall then select from among the possible alternatives the alternative that he determines to be the most appropriate based on the guidance provided in this section.
(b)
Steps.
(1)
The authorized official shall develop a reasonable number of possible alternatives that would restore, rehabilitate, replace, and/or acquire the equivalent of the injured resources. Each of the possible alternatives may, at the discretion of the authorized official, consist of actions, singly or in combination, that would achieve those purposes.
(i)
Restoration or rehabilitation actions are those actions undertaken to return injured resources to their baseline condition, as measured in terms of the physical, chemical, or biological properties that the injured resources would have exhibited or the services that would have been provided by those resources had the discharge of oil or release of the hazardous substance under investigation not occurred. Such actions would be in addition to response actions completed or anticipated pursuant to the National Contingency Plan (NCP).
(ii)
Replacement or acquisition of the equivalent means the substitution for injured resources with resources that provide the same or substantially similar services, when such substitutions are in addition to any substitutions made or anticipated as part of response actions and when such substitutions exceed the level of response actions determined appropriate to the site pursuant to the NCP.
(iii)
Possible alternatives are limited to those actions that (i) restore or rehabilitate the injured natural resources to a condition where they can provide the level of services available at baseline, or (ii) replace and/or acquire equivalent natural resources capable of providing such services.
(2)
Services provided by the resources.
(i)
In developing each of the possible alternatives, the authorized official shall list the proposed actions that would restore, rehabilitate, replace, and/or acquire the equivalent of the services provided by the injured natural resources that have been lost, and the period of time over which these services would continue to be lost.
(ii)
The authorized official shall identify services previously provided by the resources in their baseline condition in accordance with § 11.72 of this part and compare those services with services now provided by the injured resources, that is, the with-a-discharge-or-release condition. All estimates of the with-a-discharge-or-release condition shall incorporate consideration of the ability of the resources to recover as determined in § 11.73 of this part.
(c)
Range of possible alternatives.
(1)
The possible alternatives considered by the authorized official that return the injured resources to their baseline level of services could range from intensive action on the part of the authorized official to return the various resources and services provided by those resources to baseline conditions as quickly as possible, to natural recovery with minimal management actions. Possible alternatives within this range could reflect varying rates of recovery, combinations of management actions, and needs for resource replacements or acquisitions.
(2)
An alternative considering natural recovery with minimal management actions, based upon the “No Action-Natural Recovery” determination made in § 11.73(a)(1) of this part, shall be one of the possible alternatives considered.
(d)
Factors to consider when selecting the alternative to pursue. When selecting the alternative to pursue, the authorized official shall evaluate each of the possible alternatives based on all relevant considerations, including the following factors:
(1)
Technical feasibility, as that term is used in this part.
(2)
The relationship of the expected costs of the proposed actions to the expected benefits from the restoration, rehabilitation, replacement, and/or acquisition of equivalent resources.
(3)
Cost-effectiveness, as that term is used in this part.
(4)
The results of any actual or planned response actions.
(5)
Potential for additional injury resulting from the proposed actions, including long-term and indirect impacts, to the injured resources or other resources.
(6)
The natural recovery period determined in § 11.73(a)(1) of this part.
(7)
Ability of the resources to recover with or without alternative actions.
(8)
Potential effects of the action on human health and safety.
(9)
Consistency with relevant Federal, State, and tribal policies.
(10)
Compliance with applicable Federal, State, and tribal laws.
(e)
A Federal authorized official shall not select an alternative that requires acquisition of land for Federal management unless the Federal authorized official determines that restoration, rehabilitation, and/or other replacement of the injured resources is not possible.
Notes, amendments, and revision history

Amendments

[59 FR 14284, Mar. 25, 1994, as amended at 73 FR 57266, Oct. 2, 2008; 73 FR 65274, Nov. 3, 2008]

Authority

Authority: 42 U.S.C. 9651(c), as amended.

Source

Source: 51 FR 27725, Aug. 1, 1986, unless otherwise noted.

Amendments

[59 FR 14284, Mar. 25, 1994, as amended at 73 FR 57266, Oct. 2, 2008; 73 FR 65274, Nov. 3, 2008]

§11.83. Damage determination phase—use value methodologies.

43 C.F.R. § 11.83

(a)
General.
(1)
This section contains guidance and methodologies for determining— The costs of the selected alternative for (i) the restoration or rehabilitation of the injured natural resources to a condition where they can provide the level of services available at baseline, or (ii) the replacement and/or acquisition of equivalent natural resources capable of providing such services; and the compensable value of the services lost to the public through the completion of the baseline restoration, rehabilitation, replacement, and/or acquisition of equivalent natural resources.
(2)
(i)
The authorized official shall select among the cost estimating and valuation methodologies set forth in this section, or methodologies that meet the acceptance criterion of either paragraph (b)(3) or (c)(3) of this section.
(ii)
The authorized official shall define the objectives to be achieved by the application of the methodologies.
(iii)
The authorized official shall follow the guidance provided in this section for choosing among the methodologies that will be used in the Damage Determination phase.
(iv)
The authorized official shall describe his selection of methodologies and objectives in the Restoration and Compensation Determination Plan.
(3)
The authorized official shall determine that the following criteria have been met when choosing among the cost estimating and valuation methodologies. The authorized official shall document this determination in the Report of the Assessment. Only those methodologies shall be chosen:
(i)
That are feasible and reliable for a particular incident and type of damage to be measured.
(ii)
That can be performed at a reasonable cost, as that term is used in this part.
(iii)
That avoid double counting or that allow any double counting to be estimated and eliminated in the final damage calculation.
(iv)
That are cost-effective, as that term is used in this part.
(4)
Factors that may be considered by trustees to evaluate the feasibility and reliability of methodologies can include:
(i)
Is the methodology capable of providing information of use in determining the restoration cost or compensable value appropriate for a particular natural resource injury?
(ii)
Does the methodology address the particular natural resource injury and associated service loss in light of the nature, degree, and spatial and temporal extent of the injury?
(iii)
Has the methodology been subject to peer review, either through publication or otherwise?
(iv)
Does the methodology enjoy general or widespread acceptance by experts in the field?
(v)
Is the methodology subject to standards governing its application?
(vi)
Are methodological inputs and assumptions supported by a clearly articulated rationale?
(vii)
Are cutting edge methodologies tested or analyzed sufficiently so as to be reasonably reliable under the circumstances?
(5)
All of the above factors may not be applicable to every case, and other factors may be considered to evaluate feasibility and reliability. The authorized official shall document any consideration of factors deemed applicable in the Report of Assessment.
(b)
Costs of restoration, rehabilitation, replacement, and/or acquisition of equivalent resources.
(1)
Costs for restoration, rehabilitation, replacement, and/or acquisition of equivalent resources are the amount of money determined by the authorized official as necessary to complete all actions identified in the selected alternative for restoration, rehabilitation, replacement, and/or acquisition of equivalent resources, as selected in the Restoration and Compensation Determination Plan of § 11.81 of this part. Such costs shall include direct and indirect costs, consistent with the provisions of this section.
(i)
Direct costs are those that are identified by the authorized official as attributed to the selected alternative. Direct costs are those charged directly to the conduct of the selected alternative including, but not limited to, the compensation of employees for the time and effort devoted to the completion of the selected alternative; cost of materials acquired, consumed, or expended specifically for the purpose of the action; equipment and other capital expenditures; and other items of expense identified by the authorized official that are expected to be incurred in the performance of the selected alternative.
(ii)
Indirect costs are costs of activities or items that support the selected alternative, but that cannot practically be directly accounted for as costs of the selected alternative. The simplest example of indirect costs is traditional overhead, e.g., a portion of the lease costs of the buildings that contain the offices of trustee employees involved in work on the selected alternative may, under some circumstances, be considered as an indirect cost. In referring to costs that cannot practically be directly accounted for, this subpart means to include costs that are not readily assignable to the selected alternative without a level of effort disproportionate to the results achieved.
(iii)
An indirect cost rate for overhead costs may, at the discretion of the authorized official, be applied instead of calculating indirect costs where the benefits derived from the estimation of indirect costs do not outweigh the costs of the indirect cost estimation. When an indirect cost rate is used, the authorized official shall document the assumptions from which that rate has been derived.
(2)
Cost estimating methodologies. The authorized official may choose among the cost estimating methodologies listed in this section or may choose other methodologies that meet the acceptance criterion in paragraph (b)(3) of this section. Nothing in this section precludes the use of a combination of cost estimating methodologies so long as the authorized official does not double count or uses techniques that allow any double counting to be estimated and eliminated in the final damage calculation.
(i)
Comparison methodology. This methodology may be used for unique or difficult design and estimating conditions. This methodology requires the construction of a simple design for which an estimate can be found and applied to the unique or difficult design.
(ii)
Unit methodology. This methodology derives an estimate based on the cost per unit of a particular item. Many other names exist for describing the same basic approach, such as order of magnitude, lump sum, module estimating, flat rates, and involve various refinements. Data used by this methodology may be collected from technical literature or previous cost expenditures.
(iii)
Probability methodologies. Under these methodologies, the cost estimate represents an “average” value. These methodologies require information which is called certain, or deterministic, to derive the expected value of the cost estimate. Expected value estimates and range estimates represent two types of probability methodologies that may be used.
(iv)
Factor methodology. This methodology derives a cost estimate by summing the product of several items or activities. Other terms such as ratio and percentage methodologies describe the same basic approach.
(v)
Standard time data methodology. This methodology provides for a cost estimate for labor. Standard time data are a catalogue of standard tasks typically undertaken in performing a given type of work.
(vi)
Cost- and time-estimating relationships (CERs and TERs). CERs and TERs are statistical regression models that mathematically describe the cost of an item or activity as a function of one or more independent variables. The regression models provide statistical relationships between cost or time and physical or performance characteristics of past designs.
(3)
Other cost estimating methodologies. Other cost estimating methodologies that are based upon standard and accepted cost estimating practices and are cost-effective are acceptable methodologies to determine the costs of restoration, rehabilitation, replacement, and/or acquisition of equivalent resources under this part.
(c)
Compensable value.
(1)
Compensable value is the amount of money required to compensate the public for the loss in services provided by the injured resources between the time of the discharge or release and the time the resources are fully returned to their baseline conditions, or until the resources are replaced and/or equivalent natural resources are acquired. The compensable value can include the economic value of lost services provided by the injured resources, including both public use and nonuse values such as existence and bequest values. Economic value can be measured by changes in consumer surplus, economic rent, and any fees or other payments collectible by a Federal or State agency or an Indian tribe for a private party's use of the natural resources; and any economic rent accruing to a private party because the Federal or State agency or Indian tribe does not charge a fee or price for the use of the resources. Alternatively, compensable value can be determined utilizing a restoration cost approach, which measures the cost of implementing a project or projects that restore, replace, or acquire the equivalent of natural resource services lost pending restoration to baseline.
(i)
Use value is the economic value of the resources to the public attributable to the direct use of the services provided by the natural resources.
(ii)
Nonuse value is the economic value the public derives from natural resources that is independent of any direct use of the services provided.
(iii)
Restoration cost is the cost of a project or projects that restore, replace, or acquire the equivalent of natural resource services lost pending restoration to baseline.
(2)
Valuation methodologies. The authorized official may choose among the valuation methodologies listed in this section to estimate appropriate compensation for lost services or may choose other methodologies provided that the methodology can satisfy the acceptance criterion in paragraph (c)(3) of this section. Nothing in this section precludes the use of a combination of valuation methodologies so long as the authorized official does not double count or uses techniques that allow any double counting to be estimated and eliminated in the final damage calculation.
(3)
Other valuation methodologies. Other methodologies that measure compensable value in accordance with the public's willingness to pay for the lost service, or with the cost of a project that restores, replaces, or acquires services equivalent of natural resource services lost pending restoration to baseline in a cost-effective manner, are acceptable methodologies to determine compensable value under this part.
Notes, amendments, and revision history

Amendments

[51 FR 27725, Aug. 1, 1986, as amended at 53 FR 5175, Feb. 22, 1988; 59 FR 14285, Mar. 25, 1994; 73 FR 57266, Oct. 2, 2008; 91 FR 42880, July 13, 2026]

Authority

Authority: 42 U.S.C. 9651(c), as amended.

Source

Source: 51 FR 27725, Aug. 1, 1986, unless otherwise noted.

Amendments

[51 FR 27725, Aug. 1, 1986, as amended at 53 FR 5175, Feb. 22, 1988; 59 FR 14285, Mar. 25, 1994; 73 FR 57266, Oct. 2, 2008; 91 FR 42880, July 13, 2026]

§11.84. Damage determination phase—implementation guidance.

43 C.F.R. § 11.84

(a)
Requirement. The authorized official should use the cost estimating and valuation methodologies in § 11.83 of this part following the appropriate guidance in this section.
(b)
Determining uses.
(1)
Before estimating damages for compensable value under § 11.83 of this part, the authorized official should determine the uses made of the resource services identified in the Quantification phase.
(2)
Only committed uses, as that phrase is used in this part, of the resource or services over the recovery period will be used to measure the change from the baseline resulting from injury to a resource. The baseline uses must be reasonably probable, not just in the realm of possibility. Purely speculative uses of the injured resource are precluded from consideration in the estimation of damages.
(3)
(i)
When resources or resource services have mutually exclusive uses, the highest-and-best use of the injured resource or services, as determined by the authorized official, shall be used as the basis of the analyses required in this part. This determination of the highest-and-best use must be consistent with the requirements of paragraph (b)(2) of this section.
(ii)
If the uses of the resource or service are not necessarily mutually exclusive, the sum of damages should be determined from individual services. However, the sum of the projected damages from individual services shall consider congestion or crowding out effects, if any, from the resulting projected total use of those services.
(c)
Double counting.
(1)
Double counting of damages should be avoided. Double counting means that a benefit or cost has been counted more than once in the damage assessment.
(2)
Natural resource damages are the residual to be determined by incorporating the effects, or anticipated effects, of any response actions. To avoid one aspect of double counting, the effects of response actions shall be factored into the analysis of damages. If response actions will not be completed until after the assessment has been initiated, the anticipated effects of such actions should be included in the assessment.
(d)
Uncertainty.
(1)
When there are significant uncertainties concerning the assumptions made in all phases of the assessment process, reasonable alternative assumptions should be examined. In such cases, uncertainty should be handled explicitly in the analysis and documented. The uncertainty should be incorporated in the estimates of benefits and costs.
(2)
To incorporate this uncertainty, the authorized official should derive a range of probability estimates for the important assumptions used to determine damages. In these instances, the damage estimate will be the net expected present value of the costs of restoration, rehabilitation, replacement, and/or acquisition of equivalent resources and, if relevant, compensable value.
(e)
Discounting.
(1)
Where possible, damages should be estimated in the form of an expected present value dollar amount. In order to perform this calculation, a discount rate must be selected.
(2)
The discount rate to be used is that specified in “Office of Management and Budget (OMB) Circular A-94 Revised” (dated March 27, 1972, available from the Executive Office of the President, Publications, 726 Jackson Place, NW., Washington, DC 20503; ph: (202) 395-7372).
(f)
Substitutability. In calculating compensable value, the authorized official should incorporate estimates of the ability of the public to substitute resource services or uses for those of the injured resources. This substitutability should be estimated only if the potential benefits from an increase in accuracy are greater than the potential costs.
(g)
Compensable value during the restoration, rehabilitation, replacement, and/or acquisition of equivalent resources.
(1)
In determining the amount of damages, the authorized official has the discretion to compute compensable value for the period of time required to achieve the restoration, rehabilitation, replacement, and/or acquisition of equivalent resources.
(2)
When calculating compensable value during the period of time required to achieve restoration, rehabilitation, replacement, and/or acquisition of equivalent resources, the authorized official should follow the procedures described below. The procedures need not be followed in sequence.
(i)
The ability of the injured resources to recover over the recovery period should be estimated. This estimate includes estimates of natural recovery rates as well as recovery rates that reflect management actions or resource acquisitions to achieve restoration, rehabilitation, replacement, and/or acquisition of equivalent resources.
(ii)
A recovery rate should be selected for this analysis that is based upon cost-effective management actions or resource acquisitions, including a “No Action-Natural Recovery” alternative. After the recovery rate is estimated, compensable value should be estimated.
(iii)
The rate at which the uses of the injured resources and their services will be restored through the restoration or replacement of the services should be estimated. This rate may be discontinuous, that is, no uses are restored until all, or some threshold level, of the services are restored, or continuous, that is, restoration or replacement of uses will be a function of the level and rate of restoration or replacement of the services. Where practicable, the supply of and demand for the restored services should be analyzed, rather than assuming that the services will be utilized at their full capacity at each period of time in the analysis. Compensable value should be discounted using the rate described in paragraph (e)(2) of this section. This estimate is the expected present value of uses obtained through restoration, rehabilitation, replacement, and/or acquisition of equivalent resources.
(iv)
The uses of the resource that would have occurred in the absence of the discharge or release should be estimated. This estimate should be done in accordance with the procedures in § 11.72 of this part. These uses should be estimated over the same time period using the same discount rate as that specified in paragraph (e)(2) of this section. This amount is the expected present value of uses forgone.
(v)
Subtraction of the present value of uses obtained through restoration or replacement from the expected present value of uses forgone gives the amount of compensation that may be included, if positive, in a measure of damages.
(h)
Scope of the analysis.
(1)
The authorized official must determine the scope of the analysis in order to estimate compensable value.
(2)
In assessments where the scope of analysis is Federal, only the compensable value to the Nation as a whole should be counted.
(3)
In assessments where the scope of analysis is at the State level, only the compensable value to the State should be counted.
(4)
In assessments where the scope of analysis is at the tribal level, only the compensable value to the tribe should be counted.
Notes, amendments, and revision history

Amendments

[51 FR 27725, Aug. 1, 1986, as amended at 53 FR 5176, Feb. 22, 1988; 59 FR 14286, Mar. 25, 1994]

Authority

Authority: 42 U.S.C. 9651(c), as amended.

Source

Source: 51 FR 27725, Aug. 1, 1986, unless otherwise noted.

Amendments

[51 FR 27725, Aug. 1, 1986, as amended at 53 FR 5176, Feb. 22, 1988; 59 FR 14286, Mar. 25, 1994]