§495.340. As-needed HIT PAPD update and as-needed HIT IAPD update requirements.

42 C.F.R. § 495.340

Each State must submit a HIT PAPD update or a HIT IAPD no later than 60 days after the occurrence of project changes including but not limited to any of the following:
(a)
A projected cost increase of $100,000 or more.
(b)
A schedule extension of more than 60 days for major milestones.
(c)
A significant change in planning approach or implementation approach, or scope of activities beyond that approved in the HIT planning advance planning document or the HIT implementation advance planning document.
(d)
A change in implementation concept or a change to the scope of the project.
(e)
A change to the approved cost allocation methodology.
Notes, amendments, and revision history

Authority

Authority: 42 U.S.C. 1302 and 1395hh.

Source

Source: 75 FR 44565, July 28, 2010, unless otherwise noted.