§137.364. What constitutes a significant change in the original scope of work?

42 C.F.R. § 137.364

A significant change in the original scope of work is:
(a)
A change that would result in a cost that exceeds the total of the project funds available and the Self-Governance Tribe's contingency funds; or
(b)
A material departure from the original scope of work, including substantial departure from timelines negotiated in the construction project agreement.
Notes, amendments, and revision history

Authority

Authority: 25 U.S.C. 458 et seq.

Source

Source: 67 FR 35342, May 17, 2002, unless otherwise noted.