§137.364. What constitutes a significant change in the original scope of work?
42 C.F.R. § 137.364
A significant change in the original scope of work is:
A change that would result in a cost that exceeds the total of the project funds available and the Self-Governance Tribe's contingency funds; or
A material departure from the original scope of work, including substantial departure from timelines negotiated in the construction project agreement.